Azizi Abraham construction progress
The registered completion date for Azizi Abraham in Down Town Jabal Ali is August 2027. At the last site inspection, in March 2026, it was 2.0% built. The developer is Azizi Developments.
2.0%
Built, at the site inspection of 24 March 2026
Running behind its date
- Registered completion date
- August 2027
- Finish at recent pace
- January 2057
- Construction started
- July 2026
- First registered
- August 2026
- Developer
- Azizi Developments
- Community
- Down Town Jabal Ali
- Units
- 420
- Escrow bank
- Ajman Bank
- Name in Arabic
- عزيزي ابراهام
- Project number
- 4024
- Site inspections
- 2
Schedule
Between August 2025 and March 2026 the site added about 0.3 points a month. At that rate it would finish around January 2057, more than three months after its registered date of August 2027.
Site inspections
24 March 2026
2.0%+2.0 pts
6 August 2025
0%
Context
Down Town Jabal Ali has 4 projects under construction, 6.5% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Abraham?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azizi Abraham handover date?
- The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2057. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azizi Abraham?
- Azizi Abraham was 2.0% built at the site inspection on 24 March 2026. The site has been inspected 2 times since August 2025. The Land Department took 4 site photos at its inspections.
- Is Azizi Abraham delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building Azizi Abraham?
- The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Abraham?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Eleve By DeyaarNearby in Down Town Jabal Ali. 20%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.