Azizi Zain construction progress

Azizi Zain in Al Furjan is 66% built at the Land Department inspection of June 2026. Developer Azizi Developments. Completion registered for October 2027.

66%

Built, at the Land Department site inspection of 30 June 2026

On pace for its date

Completion date (Land Department)
October 2027
Finish at recent pace
May 2027
Construction started
October 2024
Registered with the Land Department
November 2024
Community
Al Furjan
Units
115
Escrow bank
Emirates NBD
Name in Arabic
عزيزي زين
Land Department project number
3335
Land Department site inspections
5

Schedule

Since October 2025 Azizi Zain has added about 3.1 points a month. That puts 100% around May 2027, within three months of its registered completion date of October 2027.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 June 2026

66%+13 pts

  • Azizi Zain construction site, Land Department inspection photo 1, 30 June 2026
  • Azizi Zain construction site, Land Department inspection photo 2, 30 June 2026
  • Azizi Zain construction site, Land Department inspection photo 3, 30 June 2026
  • Azizi Zain construction site, Land Department inspection photo 4, 30 June 2026

28 January 2026

53%+13 pts

  • Azizi Zain construction site, Land Department inspection photo 1, 28 January 2026
  • Azizi Zain construction site, Land Department inspection photo 2, 28 January 2026
  • Azizi Zain construction site, Land Department inspection photo 3, 28 January 2026
  • Azizi Zain construction site, Land Department inspection photo 4, 28 January 2026

22 October 2025

40%+11 pts

  • Azizi Zain construction site, Land Department inspection photo 1, 22 October 2025
  • Azizi Zain construction site, Land Department inspection photo 2, 22 October 2025
  • Azizi Zain construction site, Land Department inspection photo 3, 22 October 2025
  • Azizi Zain construction site, Land Department inspection photo 4, 22 October 2025

30 May 2025

29%+29 pts

  • Azizi Zain construction site, Land Department inspection photo 1, 30 May 2025
  • Azizi Zain construction site, Land Department inspection photo 2, 30 May 2025
  • Azizi Zain construction site, Land Department inspection photo 3, 30 May 2025
  • Azizi Zain construction site, Land Department inspection photo 4, 30 May 2025

15 October 2024

0%

  • Azizi Zain construction site, Land Department inspection photo 1, 15 October 2024
  • Azizi Zain construction site, Land Department inspection photo 2, 15 October 2024

All 36 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Zain?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Zain be completed?
The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around May 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Zain is built?
66%, measured at the Land Department site inspection on 30 June 2026. The Land Department engineers have inspected the site 5 times since October 2024.
Is Azizi Zain delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of October 2027.
Who is building Azizi Zain?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Zain?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.