Azizi Zain construction progress

The registered completion date for Azizi Zain in Al Furjan is October 2027. At the last site inspection, in October 2026, it was 80% built. The developer is Azizi Developments.

80%

Built, at the site inspection of 15 October 2026

On pace for its date

Registered completion date
October 2027
Finish at recent pace
April 2027
Construction started
October 2024
First registered
November 2024
Community
Al Furjan
Units
115
Escrow bank
First Abu Dhabi Bank
Name in Arabic
عزيزي زين
Project number
3335
Site inspections
6

Schedule

Since October 2025 Azizi Zain has added about 3.4 points a month. That puts 100% around April 2027, within three months of its registered completion date of October 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

80%+14 pts

  • Azizi Zain construction site, inspection photo 1, 15 October 2026
  • Azizi Zain construction site, inspection photo 2, 15 October 2026
  • Azizi Zain construction site, inspection photo 3, 15 October 2026
  • Azizi Zain construction site, inspection photo 4, 15 October 2026

30 June 2026

66%+13 pts

  • Azizi Zain construction site, inspection photo 1, 30 June 2026
  • Azizi Zain construction site, inspection photo 2, 30 June 2026
  • Azizi Zain construction site, inspection photo 3, 30 June 2026
  • Azizi Zain construction site, inspection photo 4, 30 June 2026

28 January 2026

53%+13 pts

  • Azizi Zain construction site, inspection photo 1, 28 January 2026
  • Azizi Zain construction site, inspection photo 2, 28 January 2026
  • Azizi Zain construction site, inspection photo 3, 28 January 2026
  • Azizi Zain construction site, inspection photo 4, 28 January 2026

22 October 2025

40%+11 pts

  • Azizi Zain construction site, inspection photo 1, 22 October 2025
  • Azizi Zain construction site, inspection photo 2, 22 October 2025
  • Azizi Zain construction site, inspection photo 3, 22 October 2025
  • Azizi Zain construction site, inspection photo 4, 22 October 2025

30 May 2025

29%+29 pts

  • Azizi Zain construction site, inspection photo 1, 30 May 2025
  • Azizi Zain construction site, inspection photo 2, 30 May 2025
  • Azizi Zain construction site, inspection photo 3, 30 May 2025
  • Azizi Zain construction site, inspection photo 4, 30 May 2025

15 October 2024

0%

  • Azizi Zain construction site, inspection photo 1, 15 October 2024
  • Azizi Zain construction site, inspection photo 2, 15 October 2024

All 46 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Zain?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Zain handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Zain?
Azizi Zain was 80% built at the site inspection on 15 October 2026. The site has been inspected 6 times since October 2024. The Land Department took 46 site photos at its inspections.
Is Azizi Zain delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of October 2027.
Who is building Azizi Zain?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Zain?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.