Skip to content

Azizi Riviera 53 construction progress

The registered completion date for Azizi Riviera 53 in Meydan One Community is March 2027. At the last site inspection, in July 2026, it was 63% built. The developer is Azizi Developments.

63%

Built, at the site inspection of 30 July 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
August 2027
Construction started
March 2025
First registered
September 2025
Units
225
Escrow bank
Commercial Bank of Dubai
Name in Arabic
عزيزي ريفيرا 53
Project number
3615
Site inspections
4

Schedule

Between August 2025 and July 2026 the site added about 3.0 points a month. At that rate it would finish around August 2027, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 July 2026

63%+17 pts

  • Azizi Riviera 53 construction site, inspection photo 1, 30 July 2026
  • Azizi Riviera 53 construction site, inspection photo 2, 30 July 2026
  • Azizi Riviera 53 construction site, inspection photo 3, 30 July 2026
  • Azizi Riviera 53 construction site, inspection photo 4, 30 July 2026

21 January 2026

46%+17 pts

  • Azizi Riviera 53 construction site, inspection photo 1, 21 January 2026
  • Azizi Riviera 53 construction site, inspection photo 2, 21 January 2026
  • Azizi Riviera 53 construction site, inspection photo 3, 21 January 2026
  • Azizi Riviera 53 construction site, inspection photo 4, 21 January 2026

18 August 2025

29%+16 pts

  • Azizi Riviera 53 construction site, inspection photo 1, 18 August 2025
  • Azizi Riviera 53 construction site, inspection photo 2, 18 August 2025
  • Azizi Riviera 53 construction site, inspection photo 3, 18 August 2025
  • Azizi Riviera 53 construction site, inspection photo 4, 18 August 2025

9 April 2025

13%

  • Azizi Riviera 53 construction site, inspection photo 1, 9 April 2025
  • Azizi Riviera 53 construction site, inspection photo 2, 9 April 2025
  • Azizi Riviera 53 construction site, inspection photo 3, 9 April 2025
  • Azizi Riviera 53 construction site, inspection photo 4, 9 April 2025

All 30 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 53?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 53 handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Riviera 53?
Azizi Riviera 53 was 63% built at the site inspection on 30 July 2026. The site has been inspected 4 times since April 2025. The Land Department took 30 site photos at its inspections.
Is Azizi Riviera 53 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Azizi Riviera 53?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 53?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.