Skip to content

Azizi Riviera 53 construction progress

Azizi Riviera 53 in Meydan One Community is 63% built at the Land Department inspection of July 2026. Developer Azizi Developments. Completion registered for March 2027.

63%

Built, at the Land Department site inspection of 30 July 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
August 2027
Construction started
March 2025
Registered with the Land Department
September 2025
Units
225
Escrow bank
Commercial Bank of Dubai
Name in Arabic
عزيزي ريفيرا 53
Land Department project number
3615
Land Department site inspections
4

Schedule

Between August 2025 and July 2026 the site added about 3.0 points a month. At that rate it would finish around August 2027, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 July 2026

63%+17 pts

  • Azizi Riviera 53 construction site, Land Department inspection photo 1, 30 July 2026
  • Azizi Riviera 53 construction site, Land Department inspection photo 2, 30 July 2026
  • Azizi Riviera 53 construction site, Land Department inspection photo 3, 30 July 2026
  • Azizi Riviera 53 construction site, Land Department inspection photo 4, 30 July 2026

21 January 2026

46%+17 pts

  • Azizi Riviera 53 construction site, Land Department inspection photo 1, 21 January 2026
  • Azizi Riviera 53 construction site, Land Department inspection photo 2, 21 January 2026
  • Azizi Riviera 53 construction site, Land Department inspection photo 3, 21 January 2026
  • Azizi Riviera 53 construction site, Land Department inspection photo 4, 21 January 2026

18 August 2025

29%+16 pts

  • Azizi Riviera 53 construction site, Land Department inspection photo 1, 18 August 2025
  • Azizi Riviera 53 construction site, Land Department inspection photo 2, 18 August 2025
  • Azizi Riviera 53 construction site, Land Department inspection photo 3, 18 August 2025
  • Azizi Riviera 53 construction site, Land Department inspection photo 4, 18 August 2025

9 April 2025

13%

  • Azizi Riviera 53 construction site, Land Department inspection photo 1, 9 April 2025
  • Azizi Riviera 53 construction site, Land Department inspection photo 2, 9 April 2025
  • Azizi Riviera 53 construction site, Land Department inspection photo 3, 9 April 2025
  • Azizi Riviera 53 construction site, Land Department inspection photo 4, 9 April 2025

All 30 site photos, by inspection date

Context

Meydan One Community has 10 projects under construction, 77% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Riviera 53?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Riviera 53 be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Riviera 53 is built?
63%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 4 times since April 2025.
Is Azizi Riviera 53 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Azizi Riviera 53?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 53?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.