Skip to content

Azizi Riviera 50 construction progress

The registered completion date for Azizi Riviera 50 in Meydan One Community is March 2027. At the last site inspection, in August 2026, it was 61% built. The developer is Azizi Developments.

61%

Built, at the site inspection of 7 August 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
January 2028
Construction started
March 2025
First registered
September 2025
Units
234
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفيرا 50
Project number
3614
Site inspections
4

Schedule

Between August 2025 and August 2026 the site added about 2.3 points a month. At that rate it would finish around January 2028, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 August 2026

61%+15 pts

  • Azizi Riviera 50 construction site, inspection photo 1, 7 August 2026
  • Azizi Riviera 50 construction site, inspection photo 2, 7 August 2026
  • Azizi Riviera 50 construction site, inspection photo 3, 7 August 2026
  • Azizi Riviera 50 construction site, inspection photo 4, 7 August 2026

19 January 2026

46%+12 pts

  • Azizi Riviera 50 construction site, inspection photo 1, 19 January 2026
  • Azizi Riviera 50 construction site, inspection photo 2, 19 January 2026
  • Azizi Riviera 50 construction site, inspection photo 3, 19 January 2026
  • Azizi Riviera 50 construction site, inspection photo 4, 19 January 2026

18 August 2025

35%+6.0 pts

  • Azizi Riviera 50 construction site, inspection photo 1, 18 August 2025
  • Azizi Riviera 50 construction site, inspection photo 2, 18 August 2025
  • Azizi Riviera 50 construction site, inspection photo 3, 18 August 2025
  • Azizi Riviera 50 construction site, inspection photo 4, 18 August 2025

8 April 2025

29%

  • Azizi Riviera 50 construction site, inspection photo 1, 8 April 2025
  • Azizi Riviera 50 construction site, inspection photo 2, 8 April 2025
  • Azizi Riviera 50 construction site, inspection photo 3, 8 April 2025
  • Azizi Riviera 50 construction site, inspection photo 4, 8 April 2025

All 28 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 50?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 50 handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Riviera 50?
Azizi Riviera 50 was 61% built at the site inspection on 7 August 2026. The site has been inspected 4 times since April 2025. The Land Department took 28 site photos at its inspections.
Is Azizi Riviera 50 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Azizi Riviera 50?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 50?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.