Azizi Grand construction progress

Azizi Grand in Dubai Sports City was registered to complete in February 2025 and is still under construction. At the last site inspection, in June 2026, it was 82% built. The developer is Azizi Developments.

82%

Built, at the site inspection of 24 June 2026

22 months past its registered completion date

Registered completion date
February 2025
Finish at recent pace
December 2026
Construction started
February 2018
First registered
March 2018
Units
411
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي غراند
Project number
2036
Site inspections
8

Schedule

Azizi Grand was registered to complete in February 2025, 22 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%2019202120232025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 June 2026

82%+7.4 pts

  • Azizi Grand construction site, inspection photo 1, 24 June 2026
  • Azizi Grand construction site, inspection photo 2, 24 June 2026
  • Azizi Grand construction site, inspection photo 3, 24 June 2026
  • Azizi Grand construction site, inspection photo 4, 24 June 2026

29 January 2026

75%+18 pts

  • Azizi Grand construction site, inspection photo 1, 29 January 2026
  • Azizi Grand construction site, inspection photo 2, 29 January 2026
  • Azizi Grand construction site, inspection photo 3, 29 January 2026
  • Azizi Grand construction site, inspection photo 4, 29 January 2026

21 October 2025

57%+9.6 pts

  • Azizi Grand construction site, inspection photo 1, 21 October 2025
  • Azizi Grand construction site, inspection photo 2, 21 October 2025
  • Azizi Grand construction site, inspection photo 3, 21 October 2025
  • Azizi Grand construction site, inspection photo 4, 21 October 2025

3 June 2025

48%+21 pts

  • Azizi Grand construction site, inspection photo 1, 3 June 2025
  • Azizi Grand construction site, inspection photo 2, 3 June 2025
  • Azizi Grand construction site, inspection photo 3, 3 June 2025
  • Azizi Grand construction site, inspection photo 4, 3 June 2025

6 February 2025

26%+14 pts

  • Azizi Grand construction site, inspection photo 1, 6 February 2025
  • Azizi Grand construction site, inspection photo 2, 6 February 2025
  • Azizi Grand construction site, inspection photo 3, 6 February 2025
  • Azizi Grand construction site, inspection photo 4, 6 February 2025

8 October 2024

12%+3.4 pts

  • Azizi Grand construction site, inspection photo 1, 8 October 2024
  • Azizi Grand construction site, inspection photo 2, 8 October 2024
  • Azizi Grand construction site, inspection photo 3, 8 October 2024
  • Azizi Grand construction site, inspection photo 4, 8 October 2024

25 July 2024

8.8%+8.7 pts

  • Azizi Grand construction site, inspection photo 1, 25 July 2024
  • Azizi Grand construction site, inspection photo 2, 25 July 2024
  • Azizi Grand construction site, inspection photo 3, 25 July 2024
  • Azizi Grand construction site, inspection photo 4, 25 July 2024

11 September 2023

0%

  • Azizi Grand construction site, inspection photo 1, 11 September 2023
  • Azizi Grand construction site, inspection photo 2, 11 September 2023
  • Azizi Grand construction site, inspection photo 3, 11 September 2023
  • Azizi Grand construction site, inspection photo 4, 11 September 2023

All 62 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Grand?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azizi Grand handover date?
The registered completion date was February 2025, and the register still lists Azizi Grand as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azizi Grand?
Azizi Grand was 82% built at the site inspection on 24 June 2026. The site has been inspected 8 times since September 2023. The Land Department took 62 site photos at its inspections.
Is Azizi Grand delayed?
Yes. Its registered completion date of February 2025 has passed and the project is still listed as under construction.
Who is building Azizi Grand?
The registered developer is Azizi Developments. It has 55 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Grand?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.