Azizi Grand construction progress
Azizi Grand in Dubai Sports City is 82% built at the Land Department inspection of June 2026. Developer Azizi Developments. Completion registered for February 2025.
82%
Built, at the Land Department site inspection of 24 June 2026
20 months past its registered completion date
- Completion date (Land Department)
- February 2025
- Finish at recent pace
- December 2026
- Construction started
- February 2018
- Registered with the Land Department
- March 2018
- Developer
- Azizi Developments
- Community
- Dubai Sports City
- Units
- 411
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- عزيزي غراند
- Land Department project number
- 2036
- Land Department site inspections
- 8
Schedule
Azizi Grand was registered to complete in February 2025, 20 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2026.
Site inspections
24 June 2026
82%+7.4 pts
29 January 2026
75%+18 pts
21 October 2025
57%+9.6 pts
3 June 2025
48%+21 pts
6 February 2025
26%+14 pts
8 October 2024
12%+3.4 pts
25 July 2024
8.8%+8.7 pts
11 September 2023
0%
Context
Dubai Sports City has 21 projects under construction, 44% built on average.
Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.
Own a unit in Azizi Grand?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azizi Grand be completed?
- The completion date registered with the Dubai Land Department is February 2025. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azizi Grand is built?
- 82%, measured at the Land Department site inspection on 24 June 2026. The Land Department engineers have inspected the site 8 times since September 2023.
- Is Azizi Grand delayed?
- Yes. Its registered completion date of February 2025 has passed and the Land Department still lists it as under construction.
- Who is building Azizi Grand?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Grand?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Azizi Venice 2Also by Azizi Developments. 57%, Due December 2025, passed.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Samana Golf ViewsNearby in Dubai Sports City. 56%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)