Off-plan projects in Al Furjan
38 projects in Al Furjan are under construction. On average they are 32% built. 9 have passed their registered completion date. The next one due is Sunbliss Residences By Purvanchal Real Estate Developers, in December 2026.
- Rosalia ResidencesDeyaar Development93%No date set
- Equiti GardenB N H Real Estate Developer87%Due December 2025, passed
- Azizi ZainAzizi Developments80%Due October 2027
- The Stella ResidencesAlgouta Properties71%Due December 2025, passed
- W1Malina W1 Real Estate Development70%Due April 2026, passed
- Symbolic AuraSpeedex Aura Developers70%No date set
- Almaara ResidencesHamara Home Real Estate Development66%Due October 2026, passed
- Minati Homes 1Januss Real Estate Developers60%Due September 2026, passed
- Pristine By ZoyaZoya One Real Estate Developments58%Due January 2027
- Kingdom GateKingdom Gate Property Development56%Due March 2027
- Azizi JewelAzizi Developments43%No date set
- Celeste Heights By Zimaya PropertiesZimaya Properties41%Due September 2027
- Sunbliss Residences By Purvanchal Real Estate DevelopersPurvanchal Real Estate Developers40%Due December 2026
- Maison Cannelle Residences By Casa ModernaCasa Moderna Real Estate Development40%Due June 2026, passed
- Azizi NeilaAzizi Developments39%Due July 2027
- Evora ResidencesAnax Developments38%Due August 2026, passed
- Repose ResidenceSaion Real Estate Development37%Due March 2027
- Trussardi ResidencesM I R A Developments36%Due January 2026, passed
- La Cle By Maaia DevelopersMaaia Prime Real Estate Developers35%Due January 2027
- The Hub Residences By ZazenZazen Property Development34%Due January 2027
- Primero Residences By Main RealtyMain Realty Real Estate21%Due June 2026, passed
- Avenue Residence 8Nabni Almustaqbal Properties Development18%Due June 2028
- Avenue Residence 7 By NabniNabni Real Estate Development17%Due October 2027
- Pg MaisonPg Maison Real Estate Development15%Due December 2027
- 999 Residences By Reef Luxury DevelopmentReef Luxury Development13%Due June 2027
- Vistara HouseObject One Real Estate Development10%Due March 2027
- The Mansions By MagDigo Real Estate Development (Br Of Invest Group Overseas )9.3%Due April 2027
- Sparklz By DanubeDanube Properties Development7.8%Due May 2028
- Amaya ResidencesPolygon Real Estate Development6.9%Due March 2027
- Azizi SikanderAzizi Developments3.2%Due June 2027
- Raffi By AziziAzizi Developments2.8%Due January 2028
- Azizi AmirAzizi Developments2.4%Due June 2027
- Vistara House 2Obj1 Real Estate Development2.1%Due December 2027
- Symbolic Zen ResidencesMoizziyah Developers2.1%Due June 2027
- Gate Royale ResidencesBaron Prime Real Estate Development1.7%Due June 2027
- Al Ghaf 2Jersey Real Estate Development1.6%Due October 2027
- Orvessa Residences By Michel AdamBnw Echjay Real Estate Development1.5%Due September 2028
- Manam PearlManam Real Estate Development0%Due June 2028
Questions
How many off-plan projects are under construction in Al Furjan?
38 projects are under construction in Al Furjan, 32% built on average at the latest site inspections.
Which Al Furjan projects are due to finish next?
By registered completion date: Sunbliss Residences By Purvanchal Real Estate Developers (December 2026, 40% built), Pristine By Zoya (January 2027, 58% built) and La Cle By Maaia Developers (January 2027, 35% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
How many Al Furjan projects are past their completion date?
9 of 38, among them The Stella Residences, Equiti Garden and Trussardi Residences. A project counts as late once its registered completion date has passed before it reaches 100%.
Which developers are building in Al Furjan?
The developers with the most projects here are Azizi Developments (6), out of 33 building in Al Furjan.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.