Equiti Garden construction progress

Equiti Garden in Al Furjan is 87% built at the Land Department inspection of April 2026. Developer B N H Real Estate Developer. Completion registered for December 2025.

87%

Built, at the Land Department site inspection of 30 April 2026

10 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
October 2026
Construction started
December 2023
Registered with the Land Department
January 2025
Developer
B N H Real Estate Developer
Community
Al Furjan
Units
133
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ايكويتي جاردن
Land Department project number
3242
Land Department site inspections
4

Schedule

Equiti Garden was registered to complete in December 2025, 10 months ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around October 2026.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 April 2026

87%+16 pts

  • Equiti Garden construction site, Land Department inspection photo 1, 30 April 2026
  • Equiti Garden construction site, Land Department inspection photo 2, 30 April 2026
  • Equiti Garden construction site, Land Department inspection photo 3, 30 April 2026
  • Equiti Garden construction site, Land Department inspection photo 4, 30 April 2026

9 December 2025

71%+10.0 pts

  • Equiti Garden construction site, Land Department inspection photo 1, 9 December 2025
  • Equiti Garden construction site, Land Department inspection photo 2, 9 December 2025
  • Equiti Garden construction site, Land Department inspection photo 3, 9 December 2025
  • Equiti Garden construction site, Land Department inspection photo 4, 9 December 2025

15 May 2025

61%+23 pts

  • Equiti Garden construction site, Land Department inspection photo 1, 15 May 2025
  • Equiti Garden construction site, Land Department inspection photo 2, 15 May 2025
  • Equiti Garden construction site, Land Department inspection photo 3, 15 May 2025
  • Equiti Garden construction site, Land Department inspection photo 4, 15 May 2025

9 October 2024

39%

  • Equiti Garden construction site, Land Department inspection photo 1, 9 October 2024
  • Equiti Garden construction site, Land Department inspection photo 2, 9 October 2024
  • Equiti Garden construction site, Land Department inspection photo 3, 9 October 2024
  • Equiti Garden construction site, Land Department inspection photo 4, 9 October 2024

All 25 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

B N H Real Estate Developer has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Equiti Garden?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Equiti Garden be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around October 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Equiti Garden is built?
87%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 4 times since October 2024.
Is Equiti Garden delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Equiti Garden?
The registered developer is B N H Real Estate Developer. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Equiti Garden?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.