Equiti Garden construction progress

Equiti Garden in Al Furjan was registered to complete in December 2025 and is still under construction. At the last site inspection, in April 2026, it was 87% built. The developer is B N H Real Estate Developer.

87%

Built, at the site inspection of 30 April 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
October 2026
Construction started
December 2023
First registered
January 2025
Developer
B N H Real Estate Developer
Community
Al Furjan
Units
133
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ايكويتي جاردن
Project number
3242
Site inspections
4

Schedule

Equiti Garden was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around October 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 April 2026

87%+16 pts

  • Equiti Garden construction site, inspection photo 1, 30 April 2026
  • Equiti Garden construction site, inspection photo 2, 30 April 2026
  • Equiti Garden construction site, inspection photo 3, 30 April 2026
  • Equiti Garden construction site, inspection photo 4, 30 April 2026

9 December 2025

71%+10.0 pts

  • Equiti Garden construction site, inspection photo 1, 9 December 2025
  • Equiti Garden construction site, inspection photo 2, 9 December 2025
  • Equiti Garden construction site, inspection photo 3, 9 December 2025
  • Equiti Garden construction site, inspection photo 4, 9 December 2025

15 May 2025

61%+23 pts

  • Equiti Garden construction site, inspection photo 1, 15 May 2025
  • Equiti Garden construction site, inspection photo 2, 15 May 2025
  • Equiti Garden construction site, inspection photo 3, 15 May 2025
  • Equiti Garden construction site, inspection photo 4, 15 May 2025

9 October 2024

39%

  • Equiti Garden construction site, inspection photo 1, 9 October 2024
  • Equiti Garden construction site, inspection photo 2, 9 October 2024
  • Equiti Garden construction site, inspection photo 3, 9 October 2024
  • Equiti Garden construction site, inspection photo 4, 9 October 2024

All 25 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Equiti Garden?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Equiti Garden handover date?
The registered completion date was December 2025, and the register still lists Equiti Garden as under construction. At the pace of its recent inspections the site would reach 100% around October 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Equiti Garden?
Equiti Garden was 87% built at the site inspection on 30 April 2026. The site has been inspected 4 times since October 2024. The Land Department took 25 site photos at its inspections.
Is Equiti Garden delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Equiti Garden?
The registered developer is B N H Real Estate Developer.
Which bank holds the escrow account for Equiti Garden?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.