Equiti Garden construction progress
Equiti Garden in Al Furjan is 87% built at the Land Department inspection of April 2026. Developer B N H Real Estate Developer. Completion registered for December 2025.
87%
Built, at the Land Department site inspection of 30 April 2026
10 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- October 2026
- Construction started
- December 2023
- Registered with the Land Department
- January 2025
- Developer
- B N H Real Estate Developer
- Community
- Al Furjan
- Units
- 133
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ايكويتي جاردن
- Land Department project number
- 3242
- Land Department site inspections
- 4
Schedule
Equiti Garden was registered to complete in December 2025, 10 months ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around October 2026.
Site inspections
30 April 2026
87%+16 pts
9 December 2025
71%+10.0 pts
15 May 2025
61%+23 pts
9 October 2024
39%
Context
Al Furjan has 40 projects under construction, 33% built on average.
B N H Real Estate Developer has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Equiti Garden?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Equiti Garden be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around October 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Equiti Garden is built?
- 87%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 4 times since October 2024.
- Is Equiti Garden delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Equiti Garden?
- The registered developer is B N H Real Estate Developer. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Equiti Garden?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Equiti TowerAlso by B N H Real Estate Developer. 70%, Due August 2025, passed.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)