Equiti Garden construction progress
Equiti Garden in Al Furjan was registered to complete in December 2025 and is still under construction. At the last site inspection, in April 2026, it was 87% built. The developer is B N H Real Estate Developer.
87%
Built, at the site inspection of 30 April 2026
11 months past its registered completion date
- Registered completion date
- December 2025
- Finish at recent pace
- October 2026
- Construction started
- December 2023
- First registered
- January 2025
- Developer
- B N H Real Estate Developer
- Community
- Al Furjan
- Units
- 133
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ايكويتي جاردن
- Project number
- 3242
- Site inspections
- 4
Schedule
Equiti Garden was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around October 2026.
Site inspections
30 April 2026
87%+16 pts
9 December 2025
71%+10.0 pts
15 May 2025
61%+23 pts
9 October 2024
39%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Own a unit in Equiti Garden?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Equiti Garden handover date?
- The registered completion date was December 2025, and the register still lists Equiti Garden as under construction. At the pace of its recent inspections the site would reach 100% around October 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Equiti Garden?
- Equiti Garden was 87% built at the site inspection on 30 April 2026. The site has been inspected 4 times since October 2024. The Land Department took 25 site photos at its inspections.
- Is Equiti Garden delayed?
- Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
- Who is building Equiti Garden?
- The registered developer is B N H Real Estate Developer.
- Which bank holds the escrow account for Equiti Garden?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.