Pristine By Zoya construction progress

Pristine By Zoya in Al Furjan is 58% built at the Land Department inspection of August 2026. Developer Zoya One Real Estate Developments. Completion registered for January 2027.

58%

Built, at the Land Department site inspection of 20 August 2026

Running behind its date

Completion date (Land Department)
January 2027
Finish at recent pace
April 2027
Construction started
September 2024
Registered with the Land Department
August 2024
Community
Al Furjan
Units
73
Escrow bank
Emirates Islamic Bank
Name in Arabic
البكر من زويا
Land Department project number
3069
Land Department site inspections
7

Schedule

Between November 2025 and August 2026 the site added about 5.2 points a month. At that rate it would finish around April 2027, more than three months after the January 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 August 2026

58%+17 pts

  • Pristine By Zoya construction site, Land Department inspection photo 1, 20 August 2026
  • Pristine By Zoya construction site, Land Department inspection photo 2, 20 August 2026
  • Pristine By Zoya construction site, Land Department inspection photo 3, 20 August 2026
  • Pristine By Zoya construction site, Land Department inspection photo 4, 20 August 2026

7 May 2026

41%+16 pts

  • Pristine By Zoya construction site, Land Department inspection photo 1, 7 May 2026
  • Pristine By Zoya construction site, Land Department inspection photo 2, 7 May 2026
  • Pristine By Zoya construction site, Land Department inspection photo 3, 7 May 2026
  • Pristine By Zoya construction site, Land Department inspection photo 4, 7 May 2026

15 April 2026

25%+3.6 pts

  • Pristine By Zoya construction site, Land Department inspection photo 1, 15 April 2026
  • Pristine By Zoya construction site, Land Department inspection photo 2, 15 April 2026
  • Pristine By Zoya construction site, Land Department inspection photo 3, 15 April 2026
  • Pristine By Zoya construction site, Land Department inspection photo 4, 15 April 2026

22 January 2026

22%+8.6 pts

  • Pristine By Zoya construction site, Land Department inspection photo 1, 22 January 2026
  • Pristine By Zoya construction site, Land Department inspection photo 2, 22 January 2026
  • Pristine By Zoya construction site, Land Department inspection photo 3, 22 January 2026
  • Pristine By Zoya construction site, Land Department inspection photo 4, 22 January 2026

26 November 2025

13%+13 pts

  • Pristine By Zoya construction site, Land Department inspection photo 1, 26 November 2025
  • Pristine By Zoya construction site, Land Department inspection photo 2, 26 November 2025
  • Pristine By Zoya construction site, Land Department inspection photo 3, 26 November 2025
  • Pristine By Zoya construction site, Land Department inspection photo 4, 26 November 2025

1 July 2025

0%

  • Pristine By Zoya construction site, Land Department inspection photo 1, 1 July 2025
  • Pristine By Zoya construction site, Land Department inspection photo 2, 1 July 2025

23 May 2024

0%

  • Pristine By Zoya construction site, Land Department inspection photo 1, 23 May 2024
  • Pristine By Zoya construction site, Land Department inspection photo 2, 23 May 2024

All 42 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Zoya One Real Estate Developments has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Pristine By Zoya?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Pristine By Zoya be completed?
The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around April 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Pristine By Zoya is built?
58%, measured at the Land Department site inspection on 20 August 2026. The Land Department engineers have inspected the site 7 times since May 2024.
Is Pristine By Zoya delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building Pristine By Zoya?
The registered developer is Zoya One Real Estate Developments. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Pristine By Zoya?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.