Pristine By Zoya construction progress
Pristine By Zoya in Al Furjan is 58% built at the Land Department inspection of August 2026. Developer Zoya One Real Estate Developments. Completion registered for January 2027.
58%
Built, at the Land Department site inspection of 20 August 2026
Running behind its date
- Completion date (Land Department)
- January 2027
- Finish at recent pace
- April 2027
- Construction started
- September 2024
- Registered with the Land Department
- August 2024
- Developer
- Zoya One Real Estate Developments
- Community
- Al Furjan
- Units
- 73
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- البكر من زويا
- Land Department project number
- 3069
- Land Department site inspections
- 7
Schedule
Between November 2025 and August 2026 the site added about 5.2 points a month. At that rate it would finish around April 2027, more than three months after the January 2027 date registered with the Land Department.
Site inspections
20 August 2026
58%+17 pts
7 May 2026
41%+16 pts
15 April 2026
25%+3.6 pts
22 January 2026
22%+8.6 pts
26 November 2025
13%+13 pts
1 July 2025
0%
23 May 2024
0%
Context
Al Furjan has 40 projects under construction, 33% built on average.
Zoya One Real Estate Developments has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Pristine By Zoya?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Pristine By Zoya be completed?
- The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around April 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Pristine By Zoya is built?
- 58%, measured at the Land Department site inspection on 20 August 2026. The Land Department engineers have inspected the site 7 times since May 2024.
- Is Pristine By Zoya delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building Pristine By Zoya?
- The registered developer is Zoya One Real Estate Developments. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Pristine By Zoya?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Miorah By ZoyaAlso by Zoya One Real Estate Developments. 16%, Due August 2027.
- Nuve By ZoyaAlso by Zoya One Real Estate Developments. 0.8%, Due June 2028.
- Izel By ZoyaAlso by Zoya One Real Estate Developments. 0%.
- Elanora By ZoyaAlso by Zoya One Real Estate Developments. 0%.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.