Pristine By Zoya construction progress
The registered completion date for Pristine By Zoya in Al Furjan is January 2027. At the last site inspection, in August 2026, it was 58% built. The developer is Zoya One Real Estate Developments.
58%
Built, at the site inspection of 20 August 2026
Running behind its date
- Registered completion date
- January 2027
- Finish at recent pace
- April 2027
- Construction started
- September 2024
- First registered
- August 2024
- Developer
- Zoya One Real Estate Developments
- Community
- Al Furjan
- Units
- 73
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- البكر من زويا
- Project number
- 3069
- Site inspections
- 7
Schedule
Between November 2025 and August 2026 the site added about 5.2 points a month. At that rate it would finish around April 2027, more than three months after its registered date of January 2027.
Site inspections
20 August 2026
58%+17 pts
7 May 2026
41%+16 pts
15 April 2026
25%+3.6 pts
22 January 2026
22%+8.6 pts
26 November 2025
13%+13 pts
1 July 2025
0%
23 May 2024
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Zoya One Real Estate Developments has 10 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Pristine By Zoya?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Pristine By Zoya handover date?
- The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Pristine By Zoya?
- Pristine By Zoya was 58% built at the site inspection on 20 August 2026. The site has been inspected 7 times since May 2024. The Land Department took 42 site photos at its inspections.
- Is Pristine By Zoya delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building Pristine By Zoya?
- The registered developer is Zoya One Real Estate Developments. It has 9 other projects under construction in Dubai.
- Which bank holds the escrow account for Pristine By Zoya?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Miorah By ZoyaAlso by Zoya One Real Estate Developments. 16%, Due August 2027.
- Nuve By ZoyaAlso by Zoya One Real Estate Developments. 0.8%, Due June 2028.
- Izel By ZoyaAlso by Zoya One Real Estate Developments. 0%, Due September 2028.
- Elanora By ZoyaAlso by Zoya One Real Estate Developments. 0%, Due March 2028.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)