Amaya Residences construction progress

The registered completion date for Amaya Residences in Al Furjan is March 2027. At the last site inspection, in November 2026, it was 6.9% built. The developer is Polygon Real Estate Development.

6.9%

Built, at the site inspection of 12 November 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
April 2041
Construction started
March 2025
First registered
May 2025
Developer
Polygon Real Estate Development
Community
Al Furjan
Units
78
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
أمايا ريزيدنسز
Project number
3516
Site inspections
3

Schedule

Between May 2026 and November 2026 the site added about 0.5 points a month. At that rate it would finish around April 2041, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 November 2026

6.9%+3.2 pts

  • Amaya Residences construction site, inspection photo 1, 12 November 2026
  • Amaya Residences construction site, inspection photo 2, 12 November 2026
  • Amaya Residences construction site, inspection photo 3, 12 November 2026
  • Amaya Residences construction site, inspection photo 4, 12 November 2026

15 May 2026

3.7%+3.7 pts

  • Amaya Residences construction site, inspection photo 1, 15 May 2026
  • Amaya Residences construction site, inspection photo 2, 15 May 2026
  • Amaya Residences construction site, inspection photo 3, 15 May 2026
  • Amaya Residences construction site, inspection photo 4, 15 May 2026

30 January 2025

0%

  • Amaya Residences construction site, inspection photo 1, 30 January 2025
  • Amaya Residences construction site, inspection photo 2, 30 January 2025

All 12 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Amaya Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Amaya Residences handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2041. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Amaya Residences?
Amaya Residences was 6.9% built at the site inspection on 12 November 2026. The site has been inspected 3 times since January 2025. The Land Department took 12 site photos at its inspections.
Is Amaya Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Amaya Residences?
The registered developer is Polygon Real Estate Development.
Which bank holds the escrow account for Amaya Residences?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.