Amaya Residences construction progress

Amaya Residences in Al Furjan is 3.7% built at the Land Department inspection of May 2026. Developer Polygon Real Estate Development. Completion registered for March 2027.

3.7%

Built, at the Land Department site inspection of 15 May 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
June 2059
Construction started
March 2025
Registered with the Land Department
May 2025
Developer
Polygon Real Estate Development
Community
Al Furjan
Units
78
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
أمايا ريزيدنسز
Land Department project number
3516
Land Department site inspections
2

Schedule

Between January 2025 and May 2026 the site added about 0.2 points a month. At that rate it would finish around June 2059, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

15 May 2026

3.7%+3.7 pts

  • Amaya Residences construction site, Land Department inspection photo 1, 15 May 2026
  • Amaya Residences construction site, Land Department inspection photo 2, 15 May 2026
  • Amaya Residences construction site, Land Department inspection photo 3, 15 May 2026
  • Amaya Residences construction site, Land Department inspection photo 4, 15 May 2026

30 January 2025

0%

  • Amaya Residences construction site, Land Department inspection photo 1, 30 January 2025
  • Amaya Residences construction site, Land Department inspection photo 2, 30 January 2025

All 7 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Own a unit in Amaya Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Amaya Residences be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around June 2059. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Amaya Residences is built?
3.7%, measured at the Land Department site inspection on 15 May 2026. The Land Department engineers have inspected the site 2 times since January 2025.
Is Amaya Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Amaya Residences?
The registered developer is Polygon Real Estate Development.
Which bank holds the escrow account for Amaya Residences?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.