Avenue Residence 8 construction progress

The registered completion date for Avenue Residence 8 in Al Furjan is June 2028. At the last site inspection, in September 2026, it was 18% built. The developer is Nabni Almustaqbal Properties Development.

18%

Built, at the site inspection of 17 September 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
November 2030
Construction started
April 2025
First registered
March 2025
Developer
Nabni Almustaqbal Properties Development
Community
Al Furjan
Units
104
Escrow bank
Emirates NBD
Name in Arabic
8 أفينيو ريذدنس
Project number
3551
Site inspections
4

Schedule

Between December 2025 and September 2026 the site added about 1.6 points a month. At that rate it would finish around November 2030, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 September 2026

18%+12 pts

  • Avenue Residence 8 construction site, inspection photo 1, 17 September 2026
  • Avenue Residence 8 construction site, inspection photo 2, 17 September 2026
  • Avenue Residence 8 construction site, inspection photo 3, 17 September 2026
  • Avenue Residence 8 construction site, inspection photo 4, 17 September 2026

30 April 2026

6.3%+2.8 pts

  • Avenue Residence 8 construction site, inspection photo 1, 30 April 2026
  • Avenue Residence 8 construction site, inspection photo 2, 30 April 2026
  • Avenue Residence 8 construction site, inspection photo 3, 30 April 2026
  • Avenue Residence 8 construction site, inspection photo 4, 30 April 2026

26 December 2025

3.5%+3.5 pts

  • Avenue Residence 8 construction site, inspection photo 1, 26 December 2025
  • Avenue Residence 8 construction site, inspection photo 2, 26 December 2025
  • Avenue Residence 8 construction site, inspection photo 3, 26 December 2025

10 February 2025

0%

  • Avenue Residence 8 construction site, inspection photo 1, 10 February 2025
  • Avenue Residence 8 construction site, inspection photo 2, 10 February 2025

All 19 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Avenue Residence 8?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Avenue Residence 8 handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Avenue Residence 8?
Avenue Residence 8 was 18% built at the site inspection on 17 September 2026. The site has been inspected 4 times since February 2025. The Land Department took 19 site photos at its inspections.
Is Avenue Residence 8 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Avenue Residence 8?
The registered developer is Nabni Almustaqbal Properties Development.
Which bank holds the escrow account for Avenue Residence 8?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.