Avenue Residence 8 construction progress

Avenue Residence 8 in Al Furjan is 18% built at the Land Department inspection of September 2026. Developer Nabni Almustaqbal Properties Development. Completion registered for June 2028.

18%

Built, at the Land Department site inspection of 17 September 2026

Running behind its date

Completion date (Land Department)
June 2028
Finish at recent pace
November 2030
Construction started
April 2025
Registered with the Land Department
March 2025
Developer
Nabni Almustaqbal Properties Development
Community
Al Furjan
Units
104
Escrow bank
Emirates NBD
Name in Arabic
8 أفينيو ريذدنس
Land Department project number
3551
Land Department site inspections
4

Schedule

Between December 2025 and September 2026 the site added about 1.6 points a month. At that rate it would finish around November 2030, more than three months after the June 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 September 2026

18%+12 pts

  • Avenue Residence 8 construction site, Land Department inspection photo 1, 17 September 2026
  • Avenue Residence 8 construction site, Land Department inspection photo 2, 17 September 2026
  • Avenue Residence 8 construction site, Land Department inspection photo 3, 17 September 2026
  • Avenue Residence 8 construction site, Land Department inspection photo 4, 17 September 2026

30 April 2026

6.3%+2.8 pts

  • Avenue Residence 8 construction site, Land Department inspection photo 1, 30 April 2026
  • Avenue Residence 8 construction site, Land Department inspection photo 2, 30 April 2026
  • Avenue Residence 8 construction site, Land Department inspection photo 3, 30 April 2026
  • Avenue Residence 8 construction site, Land Department inspection photo 4, 30 April 2026

26 December 2025

3.5%+3.5 pts

  • Avenue Residence 8 construction site, Land Department inspection photo 1, 26 December 2025
  • Avenue Residence 8 construction site, Land Department inspection photo 2, 26 December 2025
  • Avenue Residence 8 construction site, Land Department inspection photo 3, 26 December 2025

10 February 2025

0%

  • Avenue Residence 8 construction site, Land Department inspection photo 1, 10 February 2025
  • Avenue Residence 8 construction site, Land Department inspection photo 2, 10 February 2025

All 19 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average. Avenue Residence 8 is behind that average.

Own a unit in Avenue Residence 8?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Avenue Residence 8 be completed?
The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around November 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Avenue Residence 8 is built?
18%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 4 times since February 2025.
Is Avenue Residence 8 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Avenue Residence 8?
The registered developer is Nabni Almustaqbal Properties Development.
Which bank holds the escrow account for Avenue Residence 8?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.