Kingdom Gate construction progress
The registered completion date for Kingdom Gate in Al Furjan is March 2027. At the last site inspection, in June 2026, it was 56% built. The developer is Kingdom Gate Property Development.
56%
Built, at the site inspection of 18 June 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- July 2027
- Construction started
- March 2025
- First registered
- December 2025
- Developer
- Kingdom Gate Property Development
- Community
- Al Furjan
- Units
- 86
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- كينجدوم غيت
- Project number
- 3826
- Site inspections
- 3
Schedule
Between July 2025 and June 2026 the site added about 3.5 points a month. At that rate it would finish around July 2027, more than three months after its registered date of March 2027.
Site inspections
18 June 2026
56%+31 pts
17 October 2025
25%+8.2 pts
10 July 2025
17%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Own a unit in Kingdom Gate?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Kingdom Gate handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Kingdom Gate?
- Kingdom Gate was 56% built at the site inspection on 18 June 2026. The site has been inspected 3 times since July 2025. The Land Department took 22 site photos at its inspections.
- Is Kingdom Gate delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Kingdom Gate?
- The registered developer is Kingdom Gate Property Development.
- Which bank holds the escrow account for Kingdom Gate?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpg&w=3840&q=75)
.jpg&w=3840&q=75)