Kingdom Gate construction progress
Kingdom Gate in Al Furjan is 56% built at the Land Department inspection of June 2026. Developer Kingdom Gate Property Development. Completion registered for March 2027.
56%
Built, at the Land Department site inspection of 18 June 2026
Running behind its date
- Completion date (Land Department)
- March 2027
- Finish at recent pace
- July 2027
- Construction started
- March 2025
- Registered with the Land Department
- December 2025
- Developer
- Kingdom Gate Property Development
- Community
- Al Furjan
- Units
- 86
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- كينجدوم غيت
- Land Department project number
- 3826
- Land Department site inspections
- 3
Schedule
Between July 2025 and June 2026 the site added about 3.5 points a month. At that rate it would finish around July 2027, more than three months after the March 2027 date registered with the Land Department.
Site inspections
18 June 2026
56%+31 pts
17 October 2025
25%+8.2 pts
10 July 2025
17%
Context
Al Furjan has 40 projects under construction, 33% built on average.
Own a unit in Kingdom Gate?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Kingdom Gate be completed?
- The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Kingdom Gate is built?
- 56%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 3 times since July 2025.
- Is Kingdom Gate delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Kingdom Gate?
- The registered developer is Kingdom Gate Property Development.
- Which bank holds the escrow account for Kingdom Gate?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.