The Mansions By Mag construction progress

The Mansions By Mag in Al Furjan is 9.3% built at the Land Department inspection of June 2026. Developer Digo Real Estate Development (Br Of Invest Group Overseas ). Completion registered for April 2027.

9.3%

Built, at the Land Department site inspection of 29 June 2026

Running behind its date

Completion date (Land Department)
April 2027
Finish at recent pace
May 2037
Construction started
August 2025
Registered with the Land Department
July 2025
Community
Al Furjan
Units
15
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا مانشنز باي ماج
Land Department project number
3779
Land Department site inspections
2

Schedule

Between May 2025 and June 2026 the site added about 0.7 points a month. At that rate it would finish around May 2037, more than three months after the April 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 June 2026

9.3%+9.3 pts

  • The Mansions By Mag construction site, Land Department inspection photo 1, 29 June 2026
  • The Mansions By Mag construction site, Land Department inspection photo 2, 29 June 2026

19 May 2025

0%

  • The Mansions By Mag construction site, Land Department inspection photo 1, 19 May 2025
  • The Mansions By Mag construction site, Land Department inspection photo 2, 19 May 2025

All 4 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average. The Mansions By Mag is behind that average.

Digo Real Estate Development (Br Of Invest Group Overseas ) has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Mansions By Mag?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will The Mansions By Mag be completed?
The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around May 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Mansions By Mag is built?
9.3%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 2 times since May 2025.
Is The Mansions By Mag delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building The Mansions By Mag?
The registered developer is Digo Real Estate Development (Br Of Invest Group Overseas ). It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for The Mansions By Mag?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.