Almaara Residences construction progress

Almaara Residences in Al Furjan was registered to complete in October 2026 and is still under construction. At the last site inspection, in June 2026, it was 66% built. The developer is Hamara Home Real Estate Development.

66%

Built, at the site inspection of 30 June 2026

1 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
January 2027
Construction started
November 2024
First registered
June 2025
Developer
Hamara Home Real Estate Development
Community
Al Furjan
Units
59
Escrow bank
Dubai Islamic Bank
Name in Arabic
المارا ريزيدنس
Project number
3509
Site inspections
4

Schedule

Almaara Residences was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 5.0 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 June 2026

66%+21 pts

  • Almaara Residences construction site, inspection photo 1, 30 June 2026
  • Almaara Residences construction site, inspection photo 2, 30 June 2026
  • Almaara Residences construction site, inspection photo 3, 30 June 2026
  • Almaara Residences construction site, inspection photo 4, 30 June 2026

25 February 2026

45%+23 pts

  • Almaara Residences construction site, inspection photo 1, 25 February 2026
  • Almaara Residences construction site, inspection photo 2, 25 February 2026
  • Almaara Residences construction site, inspection photo 3, 25 February 2026
  • Almaara Residences construction site, inspection photo 4, 25 February 2026

10 October 2025

22%+22 pts

  • Almaara Residences construction site, inspection photo 1, 10 October 2025
  • Almaara Residences construction site, inspection photo 2, 10 October 2025
  • Almaara Residences construction site, inspection photo 3, 10 October 2025
  • Almaara Residences construction site, inspection photo 4, 10 October 2025

24 January 2025

0%

  • Almaara Residences construction site, inspection photo 1, 24 January 2025
  • Almaara Residences construction site, inspection photo 2, 24 January 2025
  • Almaara Residences construction site, inspection photo 3, 24 January 2025

All 33 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Almaara Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Almaara Residences handover date?
The registered completion date was October 2026, and the register still lists Almaara Residences as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Almaara Residences?
Almaara Residences was 66% built at the site inspection on 30 June 2026. The site has been inspected 4 times since January 2025. The Land Department took 33 site photos at its inspections.
Is Almaara Residences delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building Almaara Residences?
The registered developer is Hamara Home Real Estate Development.
Which bank holds the escrow account for Almaara Residences?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.