Almaara Residences construction progress

Almaara Residences in Al Furjan is 66% built at the Land Department inspection of June 2026. Developer Hamara Home Real Estate Development. Completion registered for October 2026.

66%

Built, at the Land Department site inspection of 30 June 2026

Running behind its date

Completion date (Land Department)
October 2026
Finish at recent pace
January 2027
Construction started
November 2024
Registered with the Land Department
June 2025
Developer
Hamara Home Real Estate Development
Community
Al Furjan
Units
59
Escrow bank
Dubai Islamic Bank
Name in Arabic
المارا ريزيدنس
Land Department project number
3509
Land Department site inspections
4

Schedule

Between October 2025 and June 2026 the site added about 5.0 points a month. At that rate it would finish around January 2027, more than three months after the October 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 June 2026

66%+21 pts

  • Almaara Residences construction site, Land Department inspection photo 1, 30 June 2026
  • Almaara Residences construction site, Land Department inspection photo 2, 30 June 2026
  • Almaara Residences construction site, Land Department inspection photo 3, 30 June 2026
  • Almaara Residences construction site, Land Department inspection photo 4, 30 June 2026

25 February 2026

45%+23 pts

  • Almaara Residences construction site, Land Department inspection photo 1, 25 February 2026
  • Almaara Residences construction site, Land Department inspection photo 2, 25 February 2026
  • Almaara Residences construction site, Land Department inspection photo 3, 25 February 2026
  • Almaara Residences construction site, Land Department inspection photo 4, 25 February 2026

10 October 2025

22%+22 pts

  • Almaara Residences construction site, Land Department inspection photo 1, 10 October 2025
  • Almaara Residences construction site, Land Department inspection photo 2, 10 October 2025
  • Almaara Residences construction site, Land Department inspection photo 3, 10 October 2025
  • Almaara Residences construction site, Land Department inspection photo 4, 10 October 2025

24 January 2025

0%

  • Almaara Residences construction site, Land Department inspection photo 1, 24 January 2025
  • Almaara Residences construction site, Land Department inspection photo 2, 24 January 2025
  • Almaara Residences construction site, Land Department inspection photo 3, 24 January 2025

All 33 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average. Almaara Residences is ahead of that average.

Own a unit in Almaara Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Almaara Residences be completed?
The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Almaara Residences is built?
66%, measured at the Land Department site inspection on 30 June 2026. The Land Department engineers have inspected the site 4 times since January 2025.
Is Almaara Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2026.
Who is building Almaara Residences?
The registered developer is Hamara Home Real Estate Development.
Which bank holds the escrow account for Almaara Residences?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.