Minati Homes 1 construction progress

Minati Homes 1 in Al Furjan is 51% built at the Land Department inspection of July 2026. Developer Januss Real Estate Developers. Completion registered for September 2026.

51%

Built, at the Land Department site inspection of 6 July 2026

0 months past its registered completion date

Completion date (Land Department)
September 2026
Finish at recent pace
March 2028
Construction started
April 2024
Registered with the Land Department
September 2024
Developer
Januss Real Estate Developers
Community
Al Furjan
Units
82
Escrow bank
First Abu Dhabi Bank
Name in Arabic
منازل ميناتي 1
Land Department project number
3047
Land Department site inspections
8

Schedule

Minati Homes 1 was registered to complete in September 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 2.3 points a month. Kept at that rate, the site would reach 100% around March 2028.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 July 2026

51%+7.9 pts

  • Minati Homes 1 construction site, Land Department inspection photo 1, 6 July 2026
  • Minati Homes 1 construction site, Land Department inspection photo 2, 6 July 2026
  • Minati Homes 1 construction site, Land Department inspection photo 3, 6 July 2026
  • Minati Homes 1 construction site, Land Department inspection photo 4, 6 July 2026

19 March 2026

43%+4.9 pts

  • Minati Homes 1 construction site, Land Department inspection photo 1, 19 March 2026
  • Minati Homes 1 construction site, Land Department inspection photo 2, 19 March 2026
  • Minati Homes 1 construction site, Land Department inspection photo 3, 19 March 2026
  • Minati Homes 1 construction site, Land Department inspection photo 4, 19 March 2026

17 December 2025

38%+9.1 pts

  • Minati Homes 1 construction site, Land Department inspection photo 1, 17 December 2025
  • Minati Homes 1 construction site, Land Department inspection photo 2, 17 December 2025
  • Minati Homes 1 construction site, Land Department inspection photo 3, 17 December 2025
  • Minati Homes 1 construction site, Land Department inspection photo 4, 17 December 2025

24 September 2025

29%+9.6 pts

  • Minati Homes 1 construction site, Land Department inspection photo 1, 24 September 2025
  • Minati Homes 1 construction site, Land Department inspection photo 2, 24 September 2025
  • Minati Homes 1 construction site, Land Department inspection photo 3, 24 September 2025
  • Minati Homes 1 construction site, Land Department inspection photo 4, 24 September 2025

11 June 2025

20%+10 pts

  • Minati Homes 1 construction site, Land Department inspection photo 1, 11 June 2025
  • Minati Homes 1 construction site, Land Department inspection photo 2, 11 June 2025
  • Minati Homes 1 construction site, Land Department inspection photo 3, 11 June 2025
  • Minati Homes 1 construction site, Land Department inspection photo 4, 11 June 2025

26 February 2025

9.6%+6.5 pts

  • Minati Homes 1 construction site, Land Department inspection photo 1, 26 February 2025
  • Minati Homes 1 construction site, Land Department inspection photo 2, 26 February 2025
  • Minati Homes 1 construction site, Land Department inspection photo 3, 26 February 2025
  • Minati Homes 1 construction site, Land Department inspection photo 4, 26 February 2025

29 November 2024

3.0%+3.0 pts

  • Minati Homes 1 construction site, Land Department inspection photo 1, 29 November 2024
  • Minati Homes 1 construction site, Land Department inspection photo 2, 29 November 2024
  • Minati Homes 1 construction site, Land Department inspection photo 3, 29 November 2024

9 May 2024

0%

  • Minati Homes 1 construction site, Land Department inspection photo 1, 9 May 2024
  • Minati Homes 1 construction site, Land Department inspection photo 2, 9 May 2024

All 41 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Own a unit in Minati Homes 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Minati Homes 1 be completed?
The completion date registered with the Dubai Land Department is September 2026. At the pace of its recent inspections the site would reach 100% around March 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Minati Homes 1 is built?
51%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 8 times since May 2024.
Is Minati Homes 1 delayed?
Yes. Its registered completion date of September 2026 has passed and the Land Department still lists it as under construction.
Who is building Minati Homes 1?
The registered developer is Januss Real Estate Developers.
Which bank holds the escrow account for Minati Homes 1?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.