Symbolic Zen Residences construction progress

Symbolic Zen Residences in Al Furjan is 2.1% built at the Land Department inspection of April 2026. Developer Moizziyah Developers. Completion registered for June 2027.

2.1%

Built, at the Land Department site inspection of 17 April 2026

Running behind its date

Completion date (Land Department)
June 2027
Finish at recent pace
June 2043
Construction started
June 2025
Registered with the Land Department
May 2025
Developer
Moizziyah Developers
Community
Al Furjan
Units
92
Escrow bank
The National Bank of Fujairah
Name in Arabic
سيمبوليك زن ريزيدنسز
Land Department project number
3755
Land Department site inspections
3

Schedule

Between December 2025 and April 2026 the site added about 0.5 points a month. At that rate it would finish around June 2043, more than three months after the June 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 April 2026

2.1%+2.0 pts

  • Symbolic Zen Residences construction site, Land Department inspection photo 1, 17 April 2026
  • Symbolic Zen Residences construction site, Land Department inspection photo 2, 17 April 2026
  • Symbolic Zen Residences construction site, Land Department inspection photo 3, 17 April 2026
  • Symbolic Zen Residences construction site, Land Department inspection photo 4, 17 April 2026

10 December 2025

0.1%+0.1 pts

  • Symbolic Zen Residences construction site, Land Department inspection photo 1, 10 December 2025
  • Symbolic Zen Residences construction site, Land Department inspection photo 2, 10 December 2025
  • Symbolic Zen Residences construction site, Land Department inspection photo 3, 10 December 2025
  • Symbolic Zen Residences construction site, Land Department inspection photo 4, 10 December 2025

19 March 2025

0%

  • Symbolic Zen Residences construction site, Land Department inspection photo 1, 19 March 2025
  • Symbolic Zen Residences construction site, Land Department inspection photo 2, 19 March 2025

All 11 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Own a unit in Symbolic Zen Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Symbolic Zen Residences be completed?
The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around June 2043. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Symbolic Zen Residences is built?
2.1%, measured at the Land Department site inspection on 17 April 2026. The Land Department engineers have inspected the site 3 times since March 2025.
Is Symbolic Zen Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Symbolic Zen Residences?
The registered developer is Moizziyah Developers.
Which bank holds the escrow account for Symbolic Zen Residences?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.