Symbolic Zen Residences construction progress
The registered completion date for Symbolic Zen Residences in Al Furjan is June 2027. At the last site inspection, in April 2026, it was 2.1% built. The developer is Moizziyah Developers.
2.1%
Built, at the site inspection of 17 April 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- June 2043
- Construction started
- June 2025
- First registered
- May 2025
- Developer
- Moizziyah Developers
- Community
- Al Furjan
- Units
- 92
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- سيمبوليك زن ريزيدنسز
- Project number
- 3755
- Site inspections
- 3
Schedule
Between December 2025 and April 2026 the site added about 0.5 points a month. At that rate it would finish around June 2043, more than three months after its registered date of June 2027.
Site inspections
17 April 2026
2.1%+2.0 pts
10 December 2025
0.1%+0.1 pts
19 March 2025
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Own a unit in Symbolic Zen Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Symbolic Zen Residences handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2043. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Symbolic Zen Residences?
- Symbolic Zen Residences was 2.1% built at the site inspection on 17 April 2026. The site has been inspected 3 times since March 2025. The Land Department took 11 site photos at its inspections.
- Is Symbolic Zen Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Symbolic Zen Residences?
- The registered developer is Moizziyah Developers.
- Which bank holds the escrow account for Symbolic Zen Residences?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.