Skip to content

The Stella Residences construction progress

The Stella Residences in Al Furjan is 71% built at the Land Department inspection of September 2026. Developer Algouta Properties. Completion registered for December 2025.

71%

Built, at the Land Department site inspection of 24 September 2026

10 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
July 2027
Construction started
March 2024
Registered with the Land Department
April 2024
Developer
Algouta Properties
Community
Al Furjan
Units
236
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا ستيلا ريزيدنسس
Land Department project number
2951
Land Department site inspections
10

Schedule

The Stella Residences was registered to complete in December 2025, 10 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

24 September 2026

71%+6.0 pts

  • The Stella Residences construction site, Land Department inspection photo 1, 24 September 2026
  • The Stella Residences construction site, Land Department inspection photo 2, 24 September 2026
  • The Stella Residences construction site, Land Department inspection photo 3, 24 September 2026
  • The Stella Residences construction site, Land Department inspection photo 4, 24 September 2026

29 June 2026

65%+9.7 pts

  • The Stella Residences construction site, Land Department inspection photo 1, 29 June 2026
  • The Stella Residences construction site, Land Department inspection photo 2, 29 June 2026
  • The Stella Residences construction site, Land Department inspection photo 3, 29 June 2026
  • The Stella Residences construction site, Land Department inspection photo 4, 29 June 2026

23 March 2026

55%+12 pts

  • The Stella Residences construction site, Land Department inspection photo 1, 23 March 2026
  • The Stella Residences construction site, Land Department inspection photo 2, 23 March 2026
  • The Stella Residences construction site, Land Department inspection photo 3, 23 March 2026
  • The Stella Residences construction site, Land Department inspection photo 4, 23 March 2026

16 December 2025

43%+9.4 pts

  • The Stella Residences construction site, Land Department inspection photo 1, 16 December 2025
  • The Stella Residences construction site, Land Department inspection photo 2, 16 December 2025
  • The Stella Residences construction site, Land Department inspection photo 3, 16 December 2025
  • The Stella Residences construction site, Land Department inspection photo 4, 16 December 2025

29 September 2025

34%+5.4 pts

  • The Stella Residences construction site, Land Department inspection photo 1, 29 September 2025
  • The Stella Residences construction site, Land Department inspection photo 2, 29 September 2025
  • The Stella Residences construction site, Land Department inspection photo 3, 29 September 2025
  • The Stella Residences construction site, Land Department inspection photo 4, 29 September 2025

2 July 2025

29%+8.4 pts

  • The Stella Residences construction site, Land Department inspection photo 1, 2 July 2025
  • The Stella Residences construction site, Land Department inspection photo 2, 2 July 2025
  • The Stella Residences construction site, Land Department inspection photo 3, 2 July 2025
  • The Stella Residences construction site, Land Department inspection photo 4, 2 July 2025

19 March 2025

20%+4.2 pts

  • The Stella Residences construction site, Land Department inspection photo 1, 19 March 2025
  • The Stella Residences construction site, Land Department inspection photo 2, 19 March 2025
  • The Stella Residences construction site, Land Department inspection photo 3, 19 March 2025
  • The Stella Residences construction site, Land Department inspection photo 4, 19 March 2025

8 January 2025

16%+11 pts

  • The Stella Residences construction site, Land Department inspection photo 1, 8 January 2025
  • The Stella Residences construction site, Land Department inspection photo 2, 8 January 2025
  • The Stella Residences construction site, Land Department inspection photo 3, 8 January 2025
  • The Stella Residences construction site, Land Department inspection photo 4, 8 January 2025

17 September 2024

4.7%+2.9 pts

  • The Stella Residences construction site, Land Department inspection photo 1, 17 September 2024
  • The Stella Residences construction site, Land Department inspection photo 2, 17 September 2024
  • The Stella Residences construction site, Land Department inspection photo 3, 17 September 2024

12 March 2024

1.8%

  • The Stella Residences construction site, Land Department inspection photo 1, 12 March 2024
  • The Stella Residences construction site, Land Department inspection photo 2, 12 March 2024
  • The Stella Residences construction site, Land Department inspection photo 3, 12 March 2024

All 81 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Own a unit in The Stella Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Stella Residences be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Stella Residences is built?
71%, measured at the Land Department site inspection on 24 September 2026. The Land Department engineers have inspected the site 10 times since March 2024.
Is The Stella Residences delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building The Stella Residences?
The registered developer is Algouta Properties.
Which bank holds the escrow account for The Stella Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.