Al Ghaf 2 construction progress

Al Ghaf 2 in Al Furjan is 1.6% built at the Land Department inspection of June 2026. Developer Jersey Real Estate Development. Completion registered for October 2027.

1.6%

Built, at the Land Department site inspection of 29 June 2026

Running behind its date

Completion date (Land Department)
October 2027
Finish at recent pace
March 2086
Construction started
August 2025
Registered with the Land Department
October 2025
Developer
Jersey Real Estate Development
Community
Al Furjan
Units
79
Escrow bank
Sharjah Islamic Bank
Name in Arabic
الغاف 2
Land Department project number
3873
Land Department site inspections
2

Schedule

Between July 2025 and June 2026 the site added about 0.1 points a month. At that rate it would finish around March 2086, more than three months after the October 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 June 2026

1.6%+1.6 pts

  • Al Ghaf 2 construction site, Land Department inspection photo 1, 29 June 2026
  • Al Ghaf 2 construction site, Land Department inspection photo 2, 29 June 2026
  • Al Ghaf 2 construction site, Land Department inspection photo 3, 29 June 2026
  • Al Ghaf 2 construction site, Land Department inspection photo 4, 29 June 2026

14 July 2025

0%

  • Al Ghaf 2 construction site, Land Department inspection photo 1, 14 July 2025
  • Al Ghaf 2 construction site, Land Department inspection photo 2, 14 July 2025

All 6 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Jersey Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Al Ghaf 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Al Ghaf 2 be completed?
The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around March 2086. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Al Ghaf 2 is built?
1.6%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 2 times since July 2025.
Is Al Ghaf 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Al Ghaf 2?
The registered developer is Jersey Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Al Ghaf 2?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.