Al Ghaf 2 construction progress

The registered completion date for Al Ghaf 2 in Al Furjan is October 2027. At the last site inspection, in June 2026, it was 1.6% built. The developer is Jersey Real Estate Development.

1.6%

Built, at the site inspection of 29 June 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
March 2086
Construction started
August 2025
First registered
October 2025
Developer
Jersey Real Estate Development
Community
Al Furjan
Units
79
Escrow bank
Sharjah Islamic Bank
Name in Arabic
الغاف 2
Project number
3873
Site inspections
2

Schedule

Between July 2025 and June 2026 the site added about 0.1 points a month. At that rate it would finish around March 2086, more than three months after its registered date of October 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 June 2026

1.6%+1.6 pts

  • Al Ghaf 2 construction site, inspection photo 1, 29 June 2026
  • Al Ghaf 2 construction site, inspection photo 2, 29 June 2026
  • Al Ghaf 2 construction site, inspection photo 3, 29 June 2026
  • Al Ghaf 2 construction site, inspection photo 4, 29 June 2026

14 July 2025

0%

  • Al Ghaf 2 construction site, inspection photo 1, 14 July 2025
  • Al Ghaf 2 construction site, inspection photo 2, 14 July 2025

All 6 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Jersey Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Al Ghaf 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Al Ghaf 2 handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2086. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Al Ghaf 2?
Al Ghaf 2 was 1.6% built at the site inspection on 29 June 2026. The site has been inspected 2 times since July 2025. The Land Department took 6 site photos at its inspections.
Is Al Ghaf 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Al Ghaf 2?
The registered developer is Jersey Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Al Ghaf 2?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.