Vistara House construction progress

The registered completion date for Vistara House in Al Furjan is March 2027. At the last site inspection, in November 2026, it was 10% built. The developer is Object One Real Estate Development.

10%

Built, at the site inspection of 12 November 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
May 2038
Construction started
December 2024
First registered
January 2025
Community
Al Furjan
Units
141
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
فيزتارا هاوس
Project number
3448
Site inspections
6

Schedule

Between April 2026 and November 2026 the site added about 0.7 points a month. At that rate it would finish around May 2038, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 November 2026

10%+3.5 pts

  • Vistara House construction site, inspection photo 1, 12 November 2026
  • Vistara House construction site, inspection photo 2, 12 November 2026
  • Vistara House construction site, inspection photo 3, 12 November 2026
  • Vistara House construction site, inspection photo 4, 12 November 2026

23 July 2026

7.0%+0.9 pts

  • Vistara House construction site, inspection photo 1, 23 July 2026
  • Vistara House construction site, inspection photo 2, 23 July 2026
  • Vistara House construction site, inspection photo 3, 23 July 2026
  • Vistara House construction site, inspection photo 4, 23 July 2026

20 April 2026

6.1%+1.0 pts

  • Vistara House construction site, inspection photo 1, 20 April 2026
  • Vistara House construction site, inspection photo 2, 20 April 2026
  • Vistara House construction site, inspection photo 3, 20 April 2026

3 November 2025

5.1%+3.3 pts

  • Vistara House construction site, inspection photo 1, 3 November 2025
  • Vistara House construction site, inspection photo 2, 3 November 2025

28 July 2025

1.8%+1.8 pts

  • Vistara House construction site, inspection photo 1, 28 July 2025
  • Vistara House construction site, inspection photo 2, 28 July 2025
  • Vistara House construction site, inspection photo 3, 28 July 2025

11 December 2024

0%

  • Vistara House construction site, inspection photo 1, 11 December 2024
  • Vistara House construction site, inspection photo 2, 11 December 2024

All 21 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Vistara House?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vistara House handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vistara House?
Vistara House was 10% built at the site inspection on 12 November 2026. The site has been inspected 6 times since December 2024. The Land Department took 21 site photos at its inspections.
Is Vistara House delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Vistara House?
The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for Vistara House?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.