Vistara House construction progress

Vistara House in Al Furjan is 7.0% built at the Land Department inspection of July 2026. Developer Object One Real Estate Development. Completion registered for March 2027.

7.0%

Built, at the Land Department site inspection of 23 July 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
December 2043
Construction started
December 2024
Registered with the Land Department
January 2025
Community
Al Furjan
Units
141
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
فيزتارا هاوس
Land Department project number
3448
Land Department site inspections
5

Schedule

Between July 2025 and July 2026 the site added about 0.4 points a month. At that rate it would finish around December 2043, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 July 2026

7.0%+0.9 pts

  • Vistara House construction site, Land Department inspection photo 1, 23 July 2026
  • Vistara House construction site, Land Department inspection photo 2, 23 July 2026
  • Vistara House construction site, Land Department inspection photo 3, 23 July 2026
  • Vistara House construction site, Land Department inspection photo 4, 23 July 2026

20 April 2026

6.1%+1.0 pts

  • Vistara House construction site, Land Department inspection photo 1, 20 April 2026
  • Vistara House construction site, Land Department inspection photo 2, 20 April 2026
  • Vistara House construction site, Land Department inspection photo 3, 20 April 2026

3 November 2025

5.1%+3.3 pts

  • Vistara House construction site, Land Department inspection photo 1, 3 November 2025
  • Vistara House construction site, Land Department inspection photo 2, 3 November 2025

28 July 2025

1.8%+1.8 pts

  • Vistara House construction site, Land Department inspection photo 1, 28 July 2025
  • Vistara House construction site, Land Department inspection photo 2, 28 July 2025
  • Vistara House construction site, Land Department inspection photo 3, 28 July 2025

11 December 2024

0%

  • Vistara House construction site, Land Department inspection photo 1, 11 December 2024
  • Vistara House construction site, Land Department inspection photo 2, 11 December 2024

All 14 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Vistara House?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vistara House be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around December 2043. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vistara House is built?
7.0%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 5 times since December 2024.
Is Vistara House delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Vistara House?
The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for Vistara House?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.