Vistara House construction progress
The registered completion date for Vistara House in Al Furjan is March 2027. At the last site inspection, in November 2026, it was 10% built. The developer is Object One Real Estate Development.
10%
Built, at the site inspection of 12 November 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- May 2038
- Construction started
- December 2024
- First registered
- January 2025
- Developer
- Object One Real Estate Development
- Community
- Al Furjan
- Units
- 141
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- فيزتارا هاوس
- Project number
- 3448
- Site inspections
- 6
Schedule
Between April 2026 and November 2026 the site added about 0.7 points a month. At that rate it would finish around May 2038, more than three months after its registered date of March 2027.
Site inspections
12 November 2026
10%+3.5 pts
23 July 2026
7.0%+0.9 pts
20 April 2026
6.1%+1.0 pts
3 November 2025
5.1%+3.3 pts
28 July 2025
1.8%+1.8 pts
11 December 2024
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Vistara House?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Vistara House handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Vistara House?
- Vistara House was 10% built at the site inspection on 12 November 2026. The site has been inspected 6 times since December 2024. The Land Department took 21 site photos at its inspections.
- Is Vistara House delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Vistara House?
- The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
- Which bank holds the escrow account for Vistara House?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 1wood ResidenceAlso by Object One Real Estate Development. 94%.
- Ozone 1 ResidenceAlso by Object One Real Estate Development. 57%.
- Winner TowerAlso by Object One Real Estate Development. 36%.
- The Fifth TowerAlso by Object One Real Estate Development. 55%, Due July 2026, passed.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.