W1 construction progress

W1 in Al Furjan was registered to complete in April 2026 and is still under construction. At the last site inspection, in September 2026, it was 70% built. The developer is Malina W1 Real Estate Development.

70%

Built, at the site inspection of 16 September 2026

7 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
November 2027
Construction started
March 2024
First registered
March 2026
Developer
Malina W1 Real Estate Development
Community
Al Furjan
Units
83
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
دبليو 1
Project number
4130
Site inspections
4

Schedule

W1 was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around November 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 September 2026

70%+5.1 pts

  • W1 construction site, inspection photo 1, 16 September 2026
  • W1 construction site, inspection photo 2, 16 September 2026
  • W1 construction site, inspection photo 3, 16 September 2026
  • W1 construction site, inspection photo 4, 16 September 2026

17 June 2026

65%+12 pts

  • W1 construction site, inspection photo 1, 17 June 2026
  • W1 construction site, inspection photo 2, 17 June 2026
  • W1 construction site, inspection photo 3, 17 June 2026
  • W1 construction site, inspection photo 4, 17 June 2026

6 March 2026

53%+3.7 pts

  • W1 construction site, inspection photo 1, 6 March 2026
  • W1 construction site, inspection photo 2, 6 March 2026
  • W1 construction site, inspection photo 3, 6 March 2026
  • W1 construction site, inspection photo 4, 6 March 2026

24 November 2025

50%

  • W1 construction site, inspection photo 1, 24 November 2025
  • W1 construction site, inspection photo 2, 24 November 2025
  • W1 construction site, inspection photo 3, 24 November 2025
  • W1 construction site, inspection photo 4, 24 November 2025

All 40 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in W1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the W1 handover date?
The registered completion date was April 2026, and the register still lists W1 as under construction. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on W1?
W1 was 70% built at the site inspection on 16 September 2026. The site has been inspected 4 times since November 2025. The Land Department took 40 site photos at its inspections.
Is W1 delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building W1?
The registered developer is Malina W1 Real Estate Development.
Which bank holds the escrow account for W1?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.