Evora Residences construction progress

Evora Residences in Al Furjan is 21% built at the Land Department inspection of April 2026. Developer Anax Developments. Completion registered for August 2026.

21%

Built, at the Land Department site inspection of 6 April 2026

2 months past its registered completion date

Completion date (Land Department)
August 2026
Finish at recent pace
August 2029
Construction started
December 2024
Registered with the Land Department
November 2024
Community
Al Furjan
Units
77
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
مساكن إيفورا
Land Department project number
3191
Land Department site inspections
4

Schedule

Evora Residences was registered to complete in August 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 2.0 points a month. Kept at that rate, the site would reach 100% around August 2029.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 April 2026

21%+5.2 pts

  • Evora Residences construction site, Land Department inspection photo 1, 6 April 2026
  • Evora Residences construction site, Land Department inspection photo 2, 6 April 2026
  • Evora Residences construction site, Land Department inspection photo 3, 6 April 2026
  • Evora Residences construction site, Land Department inspection photo 4, 6 April 2026

15 December 2025

15%+11 pts

  • Evora Residences construction site, Land Department inspection photo 1, 15 December 2025
  • Evora Residences construction site, Land Department inspection photo 2, 15 December 2025
  • Evora Residences construction site, Land Department inspection photo 3, 15 December 2025
  • Evora Residences construction site, Land Department inspection photo 4, 15 December 2025

30 July 2025

4.1%+4.1 pts

  • Evora Residences construction site, Land Department inspection photo 1, 30 July 2025
  • Evora Residences construction site, Land Department inspection photo 2, 30 July 2025
  • Evora Residences construction site, Land Department inspection photo 3, 30 July 2025

6 August 2024

0%

  • Evora Residences construction site, Land Department inspection photo 1, 6 August 2024
  • Evora Residences construction site, Land Department inspection photo 2, 6 August 2024
  • Evora Residences construction site, Land Department inspection photo 3, 6 August 2024

All 16 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Anax Developments has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Evora Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Evora Residences be completed?
The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around August 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Evora Residences is built?
21%, measured at the Land Department site inspection on 6 April 2026. The Land Department engineers have inspected the site 4 times since August 2024.
Is Evora Residences delayed?
Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
Who is building Evora Residences?
The registered developer is Anax Developments. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Evora Residences?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.