Evora Residences construction progress
Evora Residences in Al Furjan is 21% built at the Land Department inspection of April 2026. Developer Anax Developments. Completion registered for August 2026.
21%
Built, at the Land Department site inspection of 6 April 2026
2 months past its registered completion date
- Completion date (Land Department)
- August 2026
- Finish at recent pace
- August 2029
- Construction started
- December 2024
- Registered with the Land Department
- November 2024
- Developer
- Anax Developments
- Community
- Al Furjan
- Units
- 77
- Escrow bank
- Al Ahli Bank of Kuwait
- Name in Arabic
- مساكن إيفورا
- Land Department project number
- 3191
- Land Department site inspections
- 4
Schedule
Evora Residences was registered to complete in August 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 2.0 points a month. Kept at that rate, the site would reach 100% around August 2029.
Site inspections
6 April 2026
21%+5.2 pts
15 December 2025
15%+11 pts
30 July 2025
4.1%+4.1 pts
6 August 2024
0%
Context
Al Furjan has 40 projects under construction, 33% built on average.
Anax Developments has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Evora Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Evora Residences be completed?
- The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around August 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Evora Residences is built?
- 21%, measured at the Land Department site inspection on 6 April 2026. The Land Department engineers have inspected the site 4 times since August 2024.
- Is Evora Residences delayed?
- Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
- Who is building Evora Residences?
- The registered developer is Anax Developments. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Evora Residences?
- Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vento TowerAlso by Anax Developments. 34%.
- Kyomi ResidenceAlso by Anax Developments. 0%.
- Elle ResidencesAlso by Anax Developments. 0%, Due September 2027.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)