Evora Residences construction progress
Evora Residences in Al Furjan was registered to complete in August 2026 and is still under construction. At the last site inspection, in October 2026, it was 38% built. The developer is Anax Developments.
38%
Built, at the site inspection of 28 October 2026
3 months past its registered completion date
- Registered completion date
- August 2026
- Finish at recent pace
- March 2029
- Construction started
- December 2024
- First registered
- November 2024
- Developer
- Anax Developments
- Community
- Al Furjan
- Units
- 77
- Escrow bank
- Al Ahli Bank of Kuwait
- Name in Arabic
- مساكن إيفورا
- Project number
- 3191
- Site inspections
- 5
Schedule
Evora Residences was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around March 2029.
Site inspections
28 October 2026
38%+17 pts
6 April 2026
21%+5.2 pts
15 December 2025
15%+11 pts
30 July 2025
4.1%+4.1 pts
6 August 2024
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Anax Developments has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Evora Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Evora Residences handover date?
- The registered completion date was August 2026, and the register still lists Evora Residences as under construction. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Evora Residences?
- Evora Residences was 38% built at the site inspection on 28 October 2026. The site has been inspected 5 times since August 2024. The Land Department took 24 site photos at its inspections.
- Is Evora Residences delayed?
- Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
- Who is building Evora Residences?
- The registered developer is Anax Developments. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Evora Residences?
- Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Vento TowerAlso by Anax Developments. 43%.
- Kyomi ResidenceAlso by Anax Developments. 0%, Due January 2028.
- Elle ResidencesAlso by Anax Developments. 0%, Due September 2027.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.