Evora Residences construction progress

Evora Residences in Al Furjan was registered to complete in August 2026 and is still under construction. At the last site inspection, in October 2026, it was 38% built. The developer is Anax Developments.

38%

Built, at the site inspection of 28 October 2026

3 months past its registered completion date

Registered completion date
August 2026
Finish at recent pace
March 2029
Construction started
December 2024
First registered
November 2024
Community
Al Furjan
Units
77
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
مساكن إيفورا
Project number
3191
Site inspections
5

Schedule

Evora Residences was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around March 2029.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

38%+17 pts

  • Evora Residences construction site, inspection photo 1, 28 October 2026
  • Evora Residences construction site, inspection photo 2, 28 October 2026
  • Evora Residences construction site, inspection photo 3, 28 October 2026
  • Evora Residences construction site, inspection photo 4, 28 October 2026

6 April 2026

21%+5.2 pts

  • Evora Residences construction site, inspection photo 1, 6 April 2026
  • Evora Residences construction site, inspection photo 2, 6 April 2026
  • Evora Residences construction site, inspection photo 3, 6 April 2026
  • Evora Residences construction site, inspection photo 4, 6 April 2026

15 December 2025

15%+11 pts

  • Evora Residences construction site, inspection photo 1, 15 December 2025
  • Evora Residences construction site, inspection photo 2, 15 December 2025
  • Evora Residences construction site, inspection photo 3, 15 December 2025
  • Evora Residences construction site, inspection photo 4, 15 December 2025

30 July 2025

4.1%+4.1 pts

  • Evora Residences construction site, inspection photo 1, 30 July 2025
  • Evora Residences construction site, inspection photo 2, 30 July 2025
  • Evora Residences construction site, inspection photo 3, 30 July 2025

6 August 2024

0%

  • Evora Residences construction site, inspection photo 1, 6 August 2024
  • Evora Residences construction site, inspection photo 2, 6 August 2024
  • Evora Residences construction site, inspection photo 3, 6 August 2024

All 24 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Anax Developments has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Evora Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Evora Residences handover date?
The registered completion date was August 2026, and the register still lists Evora Residences as under construction. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Evora Residences?
Evora Residences was 38% built at the site inspection on 28 October 2026. The site has been inspected 5 times since August 2024. The Land Department took 24 site photos at its inspections.
Is Evora Residences delayed?
Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
Who is building Evora Residences?
The registered developer is Anax Developments. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Evora Residences?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.