Pg Maison construction progress

The registered completion date for Pg Maison in Al Furjan is December 2027. At the last site inspection, in November 2026, it was 15% built. The developer is Pg Maison Real Estate Development.

15%

Built, at the site inspection of 12 November 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
October 2034
Construction started
February 2025
First registered
December 2024
Developer
Pg Maison Real Estate Development
Community
Al Furjan
Units
85
Escrow bank
Dubai Islamic Bank
Name in Arabic
بي جي ميزون
Project number
3151
Site inspections
7

Schedule

Between December 2025 and November 2026 the site added about 0.9 points a month. At that rate it would finish around October 2034, more than three months after its registered date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 November 2026

15%+5.0 pts

  • Pg Maison construction site, inspection photo 1, 12 November 2026
  • Pg Maison construction site, inspection photo 2, 12 November 2026
  • Pg Maison construction site, inspection photo 3, 12 November 2026
  • Pg Maison construction site, inspection photo 4, 12 November 2026

5 August 2026

10%+3.6 pts

  • Pg Maison construction site, inspection photo 1, 5 August 2026
  • Pg Maison construction site, inspection photo 2, 5 August 2026
  • Pg Maison construction site, inspection photo 3, 5 August 2026
  • Pg Maison construction site, inspection photo 4, 5 August 2026

5 March 2026

6.5%+0.9 pts

  • Pg Maison construction site, inspection photo 1, 5 March 2026
  • Pg Maison construction site, inspection photo 2, 5 March 2026

25 December 2025

5.6%+4.1 pts

  • Pg Maison construction site, inspection photo 1, 25 December 2025
  • Pg Maison construction site, inspection photo 2, 25 December 2025
  • Pg Maison construction site, inspection photo 3, 25 December 2025
  • Pg Maison construction site, inspection photo 4, 25 December 2025

8 September 2025

1.5%+1.5 pts

  • Pg Maison construction site, inspection photo 1, 8 September 2025
  • Pg Maison construction site, inspection photo 2, 8 September 2025
  • Pg Maison construction site, inspection photo 3, 8 September 2025

1 May 2025

0%+0.0 pts

  • Pg Maison construction site, inspection photo 1, 1 May 2025
  • Pg Maison construction site, inspection photo 2, 1 May 2025

27 June 2024

0%

  • Pg Maison construction site, inspection photo 1, 27 June 2024
  • Pg Maison construction site, inspection photo 2, 27 June 2024

All 22 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Pg Maison?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Pg Maison handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Pg Maison?
Pg Maison was 15% built at the site inspection on 12 November 2026. The site has been inspected 7 times since June 2024. The Land Department took 22 site photos at its inspections.
Is Pg Maison delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Pg Maison?
The registered developer is Pg Maison Real Estate Development.
Which bank holds the escrow account for Pg Maison?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.