Pg Maison construction progress
Pg Maison in Al Furjan is 10% built at the Land Department inspection of August 2026. Developer Pg Maison Real Estate Development. Completion registered for December 2027.
10%
Built, at the Land Department site inspection of 5 August 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- February 2036
- Construction started
- February 2025
- Registered with the Land Department
- December 2024
- Developer
- Pg Maison Real Estate Development
- Community
- Al Furjan
- Units
- 85
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بي جي ميزون
- Land Department project number
- 3151
- Land Department site inspections
- 6
Schedule
Between September 2025 and August 2026 the site added about 0.8 points a month. At that rate it would finish around February 2036, more than three months after the December 2027 date registered with the Land Department.
Site inspections
5 August 2026
10%+3.6 pts
5 March 2026
6.5%+0.9 pts
25 December 2025
5.6%+4.1 pts
8 September 2025
1.5%+1.5 pts
1 May 2025
0%+0.0 pts
27 June 2024
0%
Context
Al Furjan has 40 projects under construction, 33% built on average.
Own a unit in Pg Maison?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Pg Maison be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around February 2036. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Pg Maison is built?
- 10%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 6 times since June 2024.
- Is Pg Maison delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Pg Maison?
- The registered developer is Pg Maison Real Estate Development.
- Which bank holds the escrow account for Pg Maison?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)







