Primero Residences By Main Realty in Al Furjan is 21% built at the Land Department inspection of August 2026. Developer Main Realty Real Estate. Completion registered for June 2026.

21%

Built, at the Land Department site inspection of 11 August 2026

4 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
August 2032
Construction started
June 2024
Registered with the Land Department
May 2024
Developer
Main Realty Real Estate
Community
Al Furjan
Units
86
Escrow bank
United Bank Limited
Name in Arabic
بريميرو ريزيدنسيز باي مين ريالتي
Land Department project number
3005
Land Department site inspections
8

Schedule

Primero Residences By Main Realty was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 1.1 points a month. Kept at that rate, the site would reach 100% around August 2032.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

11 August 2026

20%+5.3 pts

  • Primero Residences By Main Realty construction site, Land Department inspection photo 1, 11 August 2026
  • Primero Residences By Main Realty construction site, Land Department inspection photo 2, 11 August 2026
  • Primero Residences By Main Realty construction site, Land Department inspection photo 3, 11 August 2026
  • Primero Residences By Main Realty construction site, Land Department inspection photo 4, 11 August 2026

23 April 2026

15%+4.3 pts

  • Primero Residences By Main Realty construction site, Land Department inspection photo 1, 23 April 2026
  • Primero Residences By Main Realty construction site, Land Department inspection photo 2, 23 April 2026
  • Primero Residences By Main Realty construction site, Land Department inspection photo 3, 23 April 2026
  • Primero Residences By Main Realty construction site, Land Department inspection photo 4, 23 April 2026

23 December 2025

10%+2.3 pts

  • Primero Residences By Main Realty construction site, Land Department inspection photo 1, 23 December 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 2, 23 December 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 3, 23 December 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 4, 23 December 2025

22 September 2025

8.2%+3.5 pts

  • Primero Residences By Main Realty construction site, Land Department inspection photo 1, 22 September 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 2, 22 September 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 3, 22 September 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 4, 22 September 2025

11 June 2025

4.7%+1.8 pts

  • Primero Residences By Main Realty construction site, Land Department inspection photo 1, 11 June 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 2, 11 June 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 3, 11 June 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 4, 11 June 2025

8 May 2025

2.9%+2.9 pts

  • Primero Residences By Main Realty construction site, Land Department inspection photo 1, 8 May 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 2, 8 May 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 3, 8 May 2025
  • Primero Residences By Main Realty construction site, Land Department inspection photo 4, 8 May 2025

13 December 2024

0.1%+0.1 pts

  • Primero Residences By Main Realty construction site, Land Department inspection photo 1, 13 December 2024
  • Primero Residences By Main Realty construction site, Land Department inspection photo 2, 13 December 2024
  • Primero Residences By Main Realty construction site, Land Department inspection photo 3, 13 December 2024
  • Primero Residences By Main Realty construction site, Land Department inspection photo 4, 13 December 2024

4 April 2024

0%

  • Primero Residences By Main Realty construction site, Land Department inspection photo 1, 4 April 2024
  • Primero Residences By Main Realty construction site, Land Department inspection photo 2, 4 April 2024
  • Primero Residences By Main Realty construction site, Land Department inspection photo 3, 4 April 2024

All 41 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average. Primero Residences By Main Realty is behind that average.

Main Realty Real Estate has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Primero Residences By Main Realty?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Primero Residences By Main Realty be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around August 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Primero Residences By Main Realty is built?
21%, measured at the Land Department site inspection on 11 August 2026. The Land Department engineers have inspected the site 8 times since April 2024.
Is Primero Residences By Main Realty delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Primero Residences By Main Realty?
The registered developer is Main Realty Real Estate. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Primero Residences By Main Realty?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.