Primero Residences By Main Realty construction progress
Primero Residences By Main Realty in Al Furjan is 21% built at the Land Department inspection of August 2026. Developer Main Realty Real Estate. Completion registered for June 2026.
21%
Built, at the Land Department site inspection of 11 August 2026
4 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- August 2032
- Construction started
- June 2024
- Registered with the Land Department
- May 2024
- Developer
- Main Realty Real Estate
- Community
- Al Furjan
- Units
- 86
- Escrow bank
- United Bank Limited
- Name in Arabic
- بريميرو ريزيدنسيز باي مين ريالتي
- Land Department project number
- 3005
- Land Department site inspections
- 8
Schedule
Primero Residences By Main Realty was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 1.1 points a month. Kept at that rate, the site would reach 100% around August 2032.
Site inspections
11 August 2026
20%+5.3 pts
23 April 2026
15%+4.3 pts
23 December 2025
10%+2.3 pts
22 September 2025
8.2%+3.5 pts
11 June 2025
4.7%+1.8 pts
8 May 2025
2.9%+2.9 pts
13 December 2024
0.1%+0.1 pts
4 April 2024
0%
Context
Al Furjan has 40 projects under construction, 33% built on average. Primero Residences By Main Realty is behind that average.
Main Realty Real Estate has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Primero Residences By Main Realty?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Primero Residences By Main Realty be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around August 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Primero Residences By Main Realty is built?
- 21%, measured at the Land Department site inspection on 11 August 2026. The Land Department engineers have inspected the site 8 times since April 2024.
- Is Primero Residences By Main Realty delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Primero Residences By Main Realty?
- The registered developer is Main Realty Real Estate. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Primero Residences By Main Realty?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Flow ResidencesAlso by Main Realty Real Estate. 4.1%, Due October 2027.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.