Sparklz By Danube construction progress
The registered completion date for Sparklz By Danube in Al Furjan is May 2028. At the last site inspection, in August 2026, it was 7.8% built. The developer is Danube Properties Development.
7.8%
Built, at the site inspection of 25 August 2026
Running behind its date
- Registered completion date
- May 2028
- Finish at recent pace
- May 2037
- Construction started
- June 2025
- First registered
- April 2025
- Developer
- Danube Properties Development
- Community
- Al Furjan
- Units
- 358
- Escrow bank
- Ajman Bank
- Name in Arabic
- سباركلز من دانوب
- Project number
- 3611
- Site inspections
- 5
Schedule
Between October 2025 and August 2026 the site added about 0.7 points a month. At that rate it would finish around May 2037, more than three months after its registered date of May 2028.
Site inspections
25 August 2026
7.8%+3.9 pts
12 May 2026
3.8%+3.3 pts
10 March 2026
0.5%+0.5 pts
2 October 2025
0.1%+0.1 pts
19 March 2025
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Sparklz By Danube?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sparklz By Danube handover date?
- The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sparklz By Danube?
- Sparklz By Danube was 7.8% built at the site inspection on 25 August 2026. The site has been inspected 5 times since March 2025. The Land Department took 18 site photos at its inspections.
- Is Sparklz By Danube delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
- Who is building Sparklz By Danube?
- The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Sparklz By Danube?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 92%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 66%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 65%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)