Sparklz By Danube construction progress
Sparklz By Danube in Al Furjan is 7.8% built at the Land Department inspection of August 2026. Developer Danube Properties Development. Completion registered for May 2028.
7.8%
Built, at the Land Department site inspection of 25 August 2026
Running behind its date
- Completion date (Land Department)
- May 2028
- Finish at recent pace
- May 2037
- Construction started
- June 2025
- Registered with the Land Department
- April 2025
- Developer
- Danube Properties Development
- Community
- Al Furjan
- Units
- 358
- Escrow bank
- Ajman Bank
- Name in Arabic
- سباركلز من دانوب
- Land Department project number
- 3611
- Land Department site inspections
- 5
Schedule
Between October 2025 and August 2026 the site added about 0.7 points a month. At that rate it would finish around May 2037, more than three months after the May 2028 date registered with the Land Department.
Site inspections
25 August 2026
7.8%+3.9 pts
12 May 2026
3.8%+3.3 pts
10 March 2026
0.5%+0.5 pts
2 October 2025
0.1%+0.1 pts
19 March 2025
0%
Context
Al Furjan has 40 projects under construction, 33% built on average.
Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.
Own a unit in Sparklz By Danube?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Sparklz By Danube be completed?
- The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around May 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Sparklz By Danube is built?
- 7.8%, measured at the Land Department site inspection on 25 August 2026. The Land Department engineers have inspected the site 5 times since March 2025.
- Is Sparklz By Danube delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
- Who is building Sparklz By Danube?
- The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Sparklz By Danube?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elitz By DanubeAlso by Danube Properties Development. 81%, Due December 2025, passed.
- Viewz 1 By DanubeAlso by Danube Properties Development. 50%, Due June 2026, passed.
- Viewz 2 By DanubeAlso by Danube Properties Development. 50%, Due June 2026, passed.
- Fashionz 1 By DanubeAlso by Danube Properties Development. 40%.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)