Skip to content

Sparklz By Danube construction progress

The registered completion date for Sparklz By Danube in Al Furjan is May 2028. At the last site inspection, in August 2026, it was 7.8% built. The developer is Danube Properties Development.

7.8%

Built, at the site inspection of 25 August 2026

Running behind its date

Registered completion date
May 2028
Finish at recent pace
May 2037
Construction started
June 2025
First registered
April 2025
Community
Al Furjan
Units
358
Escrow bank
Ajman Bank
Name in Arabic
سباركلز من دانوب
Project number
3611
Site inspections
5

Schedule

Between October 2025 and August 2026 the site added about 0.7 points a month. At that rate it would finish around May 2037, more than three months after its registered date of May 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 August 2026

7.8%+3.9 pts

  • Sparklz By Danube construction site, inspection photo 1, 25 August 2026
  • Sparklz By Danube construction site, inspection photo 2, 25 August 2026
  • Sparklz By Danube construction site, inspection photo 3, 25 August 2026
  • Sparklz By Danube construction site, inspection photo 4, 25 August 2026

12 May 2026

3.8%+3.3 pts

  • Sparklz By Danube construction site, inspection photo 1, 12 May 2026
  • Sparklz By Danube construction site, inspection photo 2, 12 May 2026
  • Sparklz By Danube construction site, inspection photo 3, 12 May 2026
  • Sparklz By Danube construction site, inspection photo 4, 12 May 2026

10 March 2026

0.5%+0.5 pts

  • Sparklz By Danube construction site, inspection photo 1, 10 March 2026
  • Sparklz By Danube construction site, inspection photo 2, 10 March 2026
  • Sparklz By Danube construction site, inspection photo 3, 10 March 2026

2 October 2025

0.1%+0.1 pts

  • Sparklz By Danube construction site, inspection photo 1, 2 October 2025
  • Sparklz By Danube construction site, inspection photo 2, 2 October 2025
  • Sparklz By Danube construction site, inspection photo 3, 2 October 2025

19 March 2025

0%

  • Sparklz By Danube construction site, inspection photo 1, 19 March 2025
  • Sparklz By Danube construction site, inspection photo 2, 19 March 2025

All 18 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Sparklz By Danube?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sparklz By Danube handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sparklz By Danube?
Sparklz By Danube was 7.8% built at the site inspection on 25 August 2026. The site has been inspected 5 times since March 2025. The Land Department took 18 site photos at its inspections.
Is Sparklz By Danube delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Sparklz By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Sparklz By Danube?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.