Sparklz By Danube construction progress

Sparklz By Danube in Al Furjan is 7.8% built at the Land Department inspection of August 2026. Developer Danube Properties Development. Completion registered for May 2028.

7.8%

Built, at the Land Department site inspection of 25 August 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
May 2037
Construction started
June 2025
Registered with the Land Department
April 2025
Community
Al Furjan
Units
358
Escrow bank
Ajman Bank
Name in Arabic
سباركلز من دانوب
Land Department project number
3611
Land Department site inspections
5

Schedule

Between October 2025 and August 2026 the site added about 0.7 points a month. At that rate it would finish around May 2037, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 August 2026

7.8%+3.9 pts

  • Sparklz By Danube construction site, Land Department inspection photo 1, 25 August 2026
  • Sparklz By Danube construction site, Land Department inspection photo 2, 25 August 2026
  • Sparklz By Danube construction site, Land Department inspection photo 3, 25 August 2026
  • Sparklz By Danube construction site, Land Department inspection photo 4, 25 August 2026

12 May 2026

3.8%+3.3 pts

  • Sparklz By Danube construction site, Land Department inspection photo 1, 12 May 2026
  • Sparklz By Danube construction site, Land Department inspection photo 2, 12 May 2026
  • Sparklz By Danube construction site, Land Department inspection photo 3, 12 May 2026
  • Sparklz By Danube construction site, Land Department inspection photo 4, 12 May 2026

10 March 2026

0.5%+0.5 pts

  • Sparklz By Danube construction site, Land Department inspection photo 1, 10 March 2026
  • Sparklz By Danube construction site, Land Department inspection photo 2, 10 March 2026
  • Sparklz By Danube construction site, Land Department inspection photo 3, 10 March 2026

2 October 2025

0.1%+0.1 pts

  • Sparklz By Danube construction site, Land Department inspection photo 1, 2 October 2025
  • Sparklz By Danube construction site, Land Department inspection photo 2, 2 October 2025
  • Sparklz By Danube construction site, Land Department inspection photo 3, 2 October 2025

19 March 2025

0%

  • Sparklz By Danube construction site, Land Department inspection photo 1, 19 March 2025
  • Sparklz By Danube construction site, Land Department inspection photo 2, 19 March 2025

All 18 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Sparklz By Danube?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Sparklz By Danube be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around May 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sparklz By Danube is built?
7.8%, measured at the Land Department site inspection on 25 August 2026. The Land Department engineers have inspected the site 5 times since March 2025.
Is Sparklz By Danube delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building Sparklz By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Sparklz By Danube?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.