Repose Residence construction progress

The registered completion date for Repose Residence in Al Furjan is March 2027. At the last site inspection, in October 2026, it was 37% built. The developer is Saion Real Estate Development.

37%

Built, at the site inspection of 15 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
August 2028
Construction started
August 2025
First registered
September 2025
Developer
Saion Real Estate Development
Community
Al Furjan
Units
80
Escrow bank
Sharjah Islamic Bank
Name in Arabic
ريبوسي ريزيدنس
Project number
4012
Site inspections
4

Schedule

Between February 2026 and October 2026 the site added about 2.8 points a month. At that rate it would finish around August 2028, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

37%+14 pts

  • Repose Residence construction site, inspection photo 1, 15 October 2026
  • Repose Residence construction site, inspection photo 2, 15 October 2026
  • Repose Residence construction site, inspection photo 3, 15 October 2026
  • Repose Residence construction site, inspection photo 4, 15 October 2026

25 June 2026

24%+7.6 pts

  • Repose Residence construction site, inspection photo 1, 25 June 2026
  • Repose Residence construction site, inspection photo 2, 25 June 2026
  • Repose Residence construction site, inspection photo 3, 25 June 2026
  • Repose Residence construction site, inspection photo 4, 25 June 2026

25 February 2026

16%+16 pts

  • Repose Residence construction site, inspection photo 1, 25 February 2026
  • Repose Residence construction site, inspection photo 2, 25 February 2026
  • Repose Residence construction site, inspection photo 3, 25 February 2026
  • Repose Residence construction site, inspection photo 4, 25 February 2026

31 July 2025

0%

  • Repose Residence construction site, inspection photo 1, 31 July 2025
  • Repose Residence construction site, inspection photo 2, 31 July 2025

All 25 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Repose Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Repose Residence handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Repose Residence?
Repose Residence was 37% built at the site inspection on 15 October 2026. The site has been inspected 4 times since July 2025. The Land Department took 25 site photos at its inspections.
Is Repose Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Repose Residence?
The registered developer is Saion Real Estate Development.
Which bank holds the escrow account for Repose Residence?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.