Maison Cannelle Residences By Casa Moderna construction progress
Maison Cannelle Residences By Casa Moderna in Al Furjan is 40% built at the Land Department inspection of June 2026. Developer Casa Moderna Real Estate Development. Completion registered for June 2026.
40%
Built, at the Land Department site inspection of 8 June 2026
4 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- February 2028
- Construction started
- June 2024
- Registered with the Land Department
- October 2025
- Developer
- Casa Moderna Real Estate Development
- Community
- Al Furjan
- Units
- 40
- Escrow bank
- Arab Bank
- Name in Arabic
- ميزون كانيل ريزيدنسيز من كازا مودرنا
- Land Department project number
- 3782
- Land Department site inspections
- 2
Schedule
Maison Cannelle Residences By Casa Moderna was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around February 2028.
Site inspections
8 June 2026
40%+34 pts
16 June 2025
6.6%
Context
Al Furjan has 40 projects under construction, 33% built on average.
Own a unit in Maison Cannelle Residences By Casa Moderna?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Maison Cannelle Residences By Casa Moderna be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Maison Cannelle Residences By Casa Moderna is built?
- 40%, measured at the Land Department site inspection on 8 June 2026. The Land Department engineers have inspected the site 2 times since June 2025.
- Is Maison Cannelle Residences By Casa Moderna delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Maison Cannelle Residences By Casa Moderna?
- The registered developer is Casa Moderna Real Estate Development.
- Which bank holds the escrow account for Maison Cannelle Residences By Casa Moderna?
- Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.png&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)