Maison Cannelle Residences By Casa Moderna construction progress

Maison Cannelle Residences By Casa Moderna in Al Furjan was registered to complete in June 2026 and is still under construction. At the last site inspection, in June 2026, it was 40% built. The developer is Casa Moderna Real Estate Development.

40%

Built, at the site inspection of 8 June 2026

6 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
February 2028
Construction started
June 2024
First registered
October 2025
Developer
Casa Moderna Real Estate Development
Community
Al Furjan
Units
40
Escrow bank
Arab Bank
Name in Arabic
ميزون كانيل ريزيدنسيز من كازا مودرنا
Project number
3782
Site inspections
2

Schedule

Maison Cannelle Residences By Casa Moderna was registered to complete in June 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around February 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 June 2026

40%+34 pts

  • Maison Cannelle Residences By Casa Moderna construction site, inspection photo 1, 8 June 2026
  • Maison Cannelle Residences By Casa Moderna construction site, inspection photo 2, 8 June 2026
  • Maison Cannelle Residences By Casa Moderna construction site, inspection photo 3, 8 June 2026
  • Maison Cannelle Residences By Casa Moderna construction site, inspection photo 4, 8 June 2026

16 June 2025

6.6%

  • Maison Cannelle Residences By Casa Moderna construction site, inspection photo 1, 16 June 2025
  • Maison Cannelle Residences By Casa Moderna construction site, inspection photo 2, 16 June 2025
  • Maison Cannelle Residences By Casa Moderna construction site, inspection photo 3, 16 June 2025

All 11 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Maison Cannelle Residences By Casa Moderna?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Maison Cannelle Residences By Casa Moderna handover date?
The registered completion date was June 2026, and the register still lists Maison Cannelle Residences By Casa Moderna as under construction. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Maison Cannelle Residences By Casa Moderna?
Maison Cannelle Residences By Casa Moderna was 40% built at the site inspection on 8 June 2026. The site has been inspected 2 times since June 2025. The Land Department took 11 site photos at its inspections.
Is Maison Cannelle Residences By Casa Moderna delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Maison Cannelle Residences By Casa Moderna?
The registered developer is Casa Moderna Real Estate Development.
Which bank holds the escrow account for Maison Cannelle Residences By Casa Moderna?
Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.