Maison Cannelle Residences By Casa Moderna construction progress

Maison Cannelle Residences By Casa Moderna in Al Furjan is 40% built at the Land Department inspection of June 2026. Developer Casa Moderna Real Estate Development. Completion registered for June 2026.

40%

Built, at the Land Department site inspection of 8 June 2026

4 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
February 2028
Construction started
June 2024
Registered with the Land Department
October 2025
Developer
Casa Moderna Real Estate Development
Community
Al Furjan
Units
40
Escrow bank
Arab Bank
Name in Arabic
ميزون كانيل ريزيدنسيز من كازا مودرنا
Land Department project number
3782
Land Department site inspections
2

Schedule

Maison Cannelle Residences By Casa Moderna was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around February 2028.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

8 June 2026

40%+34 pts

  • Maison Cannelle Residences By Casa Moderna construction site, Land Department inspection photo 1, 8 June 2026
  • Maison Cannelle Residences By Casa Moderna construction site, Land Department inspection photo 2, 8 June 2026
  • Maison Cannelle Residences By Casa Moderna construction site, Land Department inspection photo 3, 8 June 2026
  • Maison Cannelle Residences By Casa Moderna construction site, Land Department inspection photo 4, 8 June 2026

16 June 2025

6.6%

  • Maison Cannelle Residences By Casa Moderna construction site, Land Department inspection photo 1, 16 June 2025
  • Maison Cannelle Residences By Casa Moderna construction site, Land Department inspection photo 2, 16 June 2025
  • Maison Cannelle Residences By Casa Moderna construction site, Land Department inspection photo 3, 16 June 2025

All 11 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average.

Own a unit in Maison Cannelle Residences By Casa Moderna?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Maison Cannelle Residences By Casa Moderna be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Maison Cannelle Residences By Casa Moderna is built?
40%, measured at the Land Department site inspection on 8 June 2026. The Land Department engineers have inspected the site 2 times since June 2025.
Is Maison Cannelle Residences By Casa Moderna delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Maison Cannelle Residences By Casa Moderna?
The registered developer is Casa Moderna Real Estate Development.
Which bank holds the escrow account for Maison Cannelle Residences By Casa Moderna?
Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.