999 Residences By Reef Luxury Development construction progress
The registered completion date for 999 Residences By Reef Luxury Development in Al Furjan is June 2027. At the last site inspection, in August 2026, it was 13% built. The developer is Reef Luxury Development.
13%
Built, at the site inspection of 27 August 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- February 2030
- Construction started
- April 2025
- First registered
- January 2025
- Developer
- Reef Luxury Development
- Community
- Al Furjan
- Units
- 148
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ريزيدنس من ريف للتطوير العقاري الفاخر 999
- Project number
- 3400
- Site inspections
- 5
Schedule
Between March 2026 and August 2026 the site added about 2.1 points a month. At that rate it would finish around February 2030, more than three months after its registered date of June 2027.
Site inspections
27 August 2026
13%+7.2 pts
8 June 2026
6.0%+4.4 pts
10 March 2026
1.6%+1.6 pts
20 March 2025
0%
14 November 2024
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Reef Luxury Development has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in 999 Residences By Reef Luxury Development?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 999 Residences By Reef Luxury Development handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 999 Residences By Reef Luxury Development?
- 999 Residences By Reef Luxury Development was 13% built at the site inspection on 27 August 2026. The site has been inspected 5 times since November 2024. The Land Department took 21 site photos at its inspections.
- Is 999 Residences By Reef Luxury Development delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building 999 Residences By Reef Luxury Development?
- The registered developer is Reef Luxury Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for 999 Residences By Reef Luxury Development?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Reef 1000Also by Reef Luxury Development. 67%, Due December 2026.
- Reef 998Also by Reef Luxury Development. 2.1%, Due June 2028.
- 997 Residences By Reef Luxury DevelopmentAlso by Reef Luxury Development. 4.9%, Due March 2028.
- Reef 996Also by Reef Luxury Development. 0.1%, Due September 2028.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.