Celeste Heights By Zimaya Properties construction progress

The registered completion date for Celeste Heights By Zimaya Properties in Al Furjan is September 2027. At the last site inspection, in October 2026, it was 41% built. The developer is Zimaya Properties.

41%

Built, at the site inspection of 20 October 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
May 2028
Construction started
May 2025
First registered
February 2025
Community
Al Furjan
Units
71
Escrow bank
Mashreq Bank
Name in Arabic
سيليستي هايتس من زيمايا للعقارات
Project number
3511
Site inspections
6

Schedule

Between December 2025 and October 2026 the site added about 3.1 points a month. At that rate it would finish around May 2028, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 October 2026

41%+10 pts

  • Celeste Heights By Zimaya Properties construction site, inspection photo 1, 20 October 2026
  • Celeste Heights By Zimaya Properties construction site, inspection photo 2, 20 October 2026
  • Celeste Heights By Zimaya Properties construction site, inspection photo 3, 20 October 2026
  • Celeste Heights By Zimaya Properties construction site, inspection photo 4, 20 October 2026

29 June 2026

31%+14 pts

  • Celeste Heights By Zimaya Properties construction site, inspection photo 1, 29 June 2026
  • Celeste Heights By Zimaya Properties construction site, inspection photo 2, 29 June 2026
  • Celeste Heights By Zimaya Properties construction site, inspection photo 3, 29 June 2026
  • Celeste Heights By Zimaya Properties construction site, inspection photo 4, 29 June 2026

23 March 2026

17%+8.2 pts

  • Celeste Heights By Zimaya Properties construction site, inspection photo 1, 23 March 2026
  • Celeste Heights By Zimaya Properties construction site, inspection photo 2, 23 March 2026
  • Celeste Heights By Zimaya Properties construction site, inspection photo 3, 23 March 2026
  • Celeste Heights By Zimaya Properties construction site, inspection photo 4, 23 March 2026

9 December 2025

9.0%+6.1 pts

  • Celeste Heights By Zimaya Properties construction site, inspection photo 1, 9 December 2025
  • Celeste Heights By Zimaya Properties construction site, inspection photo 2, 9 December 2025
  • Celeste Heights By Zimaya Properties construction site, inspection photo 3, 9 December 2025
  • Celeste Heights By Zimaya Properties construction site, inspection photo 4, 9 December 2025

22 July 2025

2.9%+2.9 pts

  • Celeste Heights By Zimaya Properties construction site, inspection photo 1, 22 July 2025
  • Celeste Heights By Zimaya Properties construction site, inspection photo 2, 22 July 2025
  • Celeste Heights By Zimaya Properties construction site, inspection photo 3, 22 July 2025
  • Celeste Heights By Zimaya Properties construction site, inspection photo 4, 22 July 2025

28 January 2025

0%

  • Celeste Heights By Zimaya Properties construction site, inspection photo 1, 28 January 2025
  • Celeste Heights By Zimaya Properties construction site, inspection photo 2, 28 January 2025
  • Celeste Heights By Zimaya Properties construction site, inspection photo 3, 28 January 2025

All 42 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Zimaya Properties has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Celeste Heights By Zimaya Properties?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Celeste Heights By Zimaya Properties handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Celeste Heights By Zimaya Properties?
Celeste Heights By Zimaya Properties was 41% built at the site inspection on 20 October 2026. The site has been inspected 6 times since January 2025. The Land Department took 42 site photos at its inspections.
Is Celeste Heights By Zimaya Properties delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Celeste Heights By Zimaya Properties?
The registered developer is Zimaya Properties. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Celeste Heights By Zimaya Properties?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.