Celeste Heights By Zimaya Properties construction progress
The registered completion date for Celeste Heights By Zimaya Properties in Al Furjan is September 2027. At the last site inspection, in October 2026, it was 41% built. The developer is Zimaya Properties.
41%
Built, at the site inspection of 20 October 2026
Running behind its date
- Registered completion date
- September 2027
- Finish at recent pace
- May 2028
- Construction started
- May 2025
- First registered
- February 2025
- Developer
- Zimaya Properties
- Community
- Al Furjan
- Units
- 71
- Escrow bank
- Mashreq Bank
- Name in Arabic
- سيليستي هايتس من زيمايا للعقارات
- Project number
- 3511
- Site inspections
- 6
Schedule
Between December 2025 and October 2026 the site added about 3.1 points a month. At that rate it would finish around May 2028, more than three months after its registered date of September 2027.
Site inspections
20 October 2026
41%+10 pts
29 June 2026
31%+14 pts
23 March 2026
17%+8.2 pts
9 December 2025
9.0%+6.1 pts
22 July 2025
2.9%+2.9 pts
28 January 2025
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Zimaya Properties has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Celeste Heights By Zimaya Properties?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Celeste Heights By Zimaya Properties handover date?
- The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Celeste Heights By Zimaya Properties?
- Celeste Heights By Zimaya Properties was 41% built at the site inspection on 20 October 2026. The site has been inspected 6 times since January 2025. The Land Department took 42 site photos at its inspections.
- Is Celeste Heights By Zimaya Properties delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Celeste Heights By Zimaya Properties?
- The registered developer is Zimaya Properties. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Celeste Heights By Zimaya Properties?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Belle Reve By ZimayaAlso by Zimaya Properties. 92%, Due August 2026, passed.
- Belle Vie By ZimayaAlso by Zimaya Properties. 11%, Due March 2028.
- Lawncrest By ZimayaAlso by Zimaya Properties. 0%, Due June 2029.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.














.jpeg&w=3840&q=75)