Celeste Heights By Zimaya Properties construction progress
Celeste Heights By Zimaya Properties in Al Furjan is 31% built at the Land Department inspection of June 2026. Developer Zimaya Properties. Completion registered for September 2027.
31%
Built, at the Land Department site inspection of 29 June 2026
Running behind its date
- Completion date (Land Department)
- September 2027
- Finish at recent pace
- October 2028
- Construction started
- May 2025
- Registered with the Land Department
- February 2025
- Developer
- Zimaya Properties
- Community
- Al Furjan
- Units
- 71
- Escrow bank
- Mashreq Bank
- Name in Arabic
- سيليستي هايتس من زيمايا للعقارات
- Land Department project number
- 3511
- Land Department site inspections
- 5
Schedule
Between July 2025 and June 2026 the site added about 2.5 points a month. At that rate it would finish around October 2028, more than three months after the September 2027 date registered with the Land Department.
Site inspections
29 June 2026
31%+14 pts
23 March 2026
17%+8.2 pts
9 December 2025
9.0%+6.1 pts
22 July 2025
2.9%+2.9 pts
28 January 2025
0%
Context
Al Furjan has 40 projects under construction, 33% built on average. Celeste Heights By Zimaya Properties is behind that average.
Zimaya Properties has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Celeste Heights By Zimaya Properties?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Celeste Heights By Zimaya Properties be completed?
- The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around October 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Celeste Heights By Zimaya Properties is built?
- 31%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 5 times since January 2025.
- Is Celeste Heights By Zimaya Properties delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Celeste Heights By Zimaya Properties?
- The registered developer is Zimaya Properties. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Celeste Heights By Zimaya Properties?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Belle Reve By ZimayaAlso by Zimaya Properties. 81%, Due August 2026, passed.
- Belle Vie By ZimayaAlso by Zimaya Properties. 11%, Due March 2028.
- Lawncrest By ZimayaAlso by Zimaya Properties. 0%.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)

