The Hub Residences By Zazen construction progress

The registered completion date for The Hub Residences By Zazen in Al Furjan is January 2027. At the last site inspection, in October 2026, it was 34% built. The developer is Zazen Property Development.

34%

Built, at the site inspection of 19 October 2026

Running behind its date

Registered completion date
January 2027
Finish at recent pace
November 2028
Construction started
March 2025
First registered
December 2024
Developer
Zazen Property Development
Community
Al Furjan
Units
105
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذا هب ريزيدنسز باي زازن
Project number
3419
Site inspections
7

Schedule

Between December 2025 and October 2026 the site added about 2.6 points a month. At that rate it would finish around November 2028, more than three months after its registered date of January 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 October 2026

34%+6.8 pts

  • The Hub Residences By Zazen construction site, inspection photo 1, 19 October 2026
  • The Hub Residences By Zazen construction site, inspection photo 2, 19 October 2026
  • The Hub Residences By Zazen construction site, inspection photo 3, 19 October 2026
  • The Hub Residences By Zazen construction site, inspection photo 4, 19 October 2026

6 August 2026

27%+8.4 pts

  • The Hub Residences By Zazen construction site, inspection photo 1, 6 August 2026
  • The Hub Residences By Zazen construction site, inspection photo 2, 6 August 2026
  • The Hub Residences By Zazen construction site, inspection photo 3, 6 August 2026
  • The Hub Residences By Zazen construction site, inspection photo 4, 6 August 2026

22 May 2026

19%+8.0 pts

  • The Hub Residences By Zazen construction site, inspection photo 1, 22 May 2026
  • The Hub Residences By Zazen construction site, inspection photo 2, 22 May 2026
  • The Hub Residences By Zazen construction site, inspection photo 3, 22 May 2026
  • The Hub Residences By Zazen construction site, inspection photo 4, 22 May 2026

6 January 2026

11%+4.4 pts

  • The Hub Residences By Zazen construction site, inspection photo 1, 6 January 2026
  • The Hub Residences By Zazen construction site, inspection photo 2, 6 January 2026
  • The Hub Residences By Zazen construction site, inspection photo 3, 6 January 2026
  • The Hub Residences By Zazen construction site, inspection photo 4, 6 January 2026

5 December 2025

6.5%+3.5 pts

  • The Hub Residences By Zazen construction site, inspection photo 1, 5 December 2025
  • The Hub Residences By Zazen construction site, inspection photo 2, 5 December 2025
  • The Hub Residences By Zazen construction site, inspection photo 3, 5 December 2025
  • The Hub Residences By Zazen construction site, inspection photo 4, 5 December 2025

19 August 2025

3.0%+3.0 pts

  • The Hub Residences By Zazen construction site, inspection photo 1, 19 August 2025
  • The Hub Residences By Zazen construction site, inspection photo 2, 19 August 2025
  • The Hub Residences By Zazen construction site, inspection photo 3, 19 August 2025
  • The Hub Residences By Zazen construction site, inspection photo 4, 19 August 2025

9 December 2024

0%

  • The Hub Residences By Zazen construction site, inspection photo 1, 9 December 2024
  • The Hub Residences By Zazen construction site, inspection photo 2, 9 December 2024

All 43 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Zazen Property Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Hub Residences By Zazen?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Hub Residences By Zazen handover date?
The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Hub Residences By Zazen?
The Hub Residences By Zazen was 34% built at the site inspection on 19 October 2026. The site has been inspected 7 times since December 2024. The Land Department took 43 site photos at its inspections.
Is The Hub Residences By Zazen delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building The Hub Residences By Zazen?
The registered developer is Zazen Property Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Hub Residences By Zazen?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.