Rosalia Residences construction progress
Rosalia Residences in Al Furjan is 82% built at the Land Department inspection of August 2026. Developer Deyaar Development.
82%
Built, at the Land Department site inspection of 5 August 2026
- Finish at recent pace
- April 2027
- Construction started
- September 2023
- Registered with the Land Department
- January 2024
- Developer
- Deyaar Development
- Community
- Al Furjan
- Units
- 118
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- روزاليا ريزيدنسز
- Land Department project number
- 2911
- Land Department site inspections
- 7
Schedule
Since November 2025 Rosalia Residences has added about 2.2 points a month. At that rate the site reaches 100% around April 2027. The Land Department has no completion date on record to compare it with.
Site inspections
5 August 2026
82%+11 pts
18 March 2026
71%+7.4 pts
27 November 2025
64%+18 pts
26 May 2025
46%+10 pts
5 February 2025
35%+19 pts
23 July 2024
17%+17 pts
8 January 2024
0%
Context
Al Furjan has 40 projects under construction, 33% built on average.
Deyaar Development has 10 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Rosalia Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Rosalia Residences be completed?
- The Land Department has no completion date on record for Rosalia Residences yet.
- How much of Rosalia Residences is built?
- 82%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 7 times since January 2024.
- Who is building Rosalia Residences?
- The registered developer is Deyaar Development. It has 9 other projects under construction in Dubai.
- Which bank holds the escrow account for Rosalia Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Deyaar ParkAlso by Deyaar Development. 0%, Due December 2012, passed.
- Mar CasaAlso by Deyaar Development. 56%, Due October 2026.
- Eleve By DeyaarAlso by Deyaar Development. 20%.
- Elm At Park FiveAlso by Deyaar Development. 16%, Due June 2027.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)