Trussardi Residences construction progress
Trussardi Residences in Al Furjan was registered to complete in January 2026 and is still under construction. At the last site inspection, in April 2026, it was 36% built. The developer is M I R A Developments.
36%
Built, at the site inspection of 6 April 2026
10 months past its registered completion date
- Registered completion date
- January 2026
- Finish at recent pace
- May 2029
- Construction started
- February 2024
- First registered
- January 2024
- Developer
- M I R A Developments
- Community
- Al Furjan
- Units
- 142
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- تروساردي ريزيدنسز
- Project number
- 2900
- Site inspections
- 5
Schedule
Trussardi Residences was registered to complete in January 2026, 10 months ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around May 2029.
Site inspections
6 April 2026
36%+9.0 pts
9 December 2025
27%+6.3 pts
7 July 2025
21%+13 pts
25 February 2025
8.1%+8.1 pts
28 December 2023
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
M I R A Developments has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Trussardi Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Trussardi Residences handover date?
- The registered completion date was January 2026, and the register still lists Trussardi Residences as under construction. At the pace of its recent inspections the site would reach 100% around May 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Trussardi Residences?
- Trussardi Residences was 36% built at the site inspection on 6 April 2026. The site has been inspected 5 times since December 2023. The Land Department took 29 site photos at its inspections.
- Is Trussardi Residences delayed?
- Yes. Its registered completion date of January 2026 has passed and the project is still listed as under construction.
- Who is building Trussardi Residences?
- The registered developer is M I R A Developments. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Trussardi Residences?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mira Villas Designed By Bentley HomeAlso by M I R A Developments. 32%, Due December 2026.
- Trussardi Residences 2Also by M I R A Developments. 6.6%, Due July 2027.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Primero Residences By Main RealtyNearby in Al Furjan. 21%, Due June 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.