La Cle By Maaia Developers construction progress
La Cle By Maaia Developers in Al Furjan is 35% built at the Land Department inspection of June 2026. Developer Maaia Prime Real Estate Developers. Completion registered for January 2027.
35%
Built, at the Land Department site inspection of 29 June 2026
Running behind its date
- Completion date (Land Department)
- January 2027
- Finish at recent pace
- June 2028
- Construction started
- January 2025
- Registered with the Land Department
- January 2025
- Developer
- Maaia Prime Real Estate Developers
- Community
- Al Furjan
- Units
- 58
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- لي كلي باي مايا ديفيلوبرز
- Land Department project number
- 3412
- Land Department site inspections
- 4
Schedule
Between November 2025 and June 2026 the site added about 2.8 points a month. At that rate it would finish around June 2028, more than three months after the January 2027 date registered with the Land Department.
Site inspections
29 June 2026
35%+11 pts
26 March 2026
23%+10 pts
5 November 2025
13%+13 pts
16 December 2024
0%
Context
Al Furjan has 40 projects under construction, 33% built on average.
Maaia Prime Real Estate Developers has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in La Cle By Maaia Developers?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will La Cle By Maaia Developers be completed?
- The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around June 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of La Cle By Maaia Developers is built?
- 35%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 4 times since December 2024.
- Is La Cle By Maaia Developers delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building La Cle By Maaia Developers?
- The registered developer is Maaia Prime Real Estate Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for La Cle By Maaia Developers?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- La Vue ParcAlso by Maaia Prime Real Estate Developers. 15%, Due September 2027.
- Trussardi ResidencesNearby in Al Furjan. 36%.
- Rosalia ResidencesNearby in Al Furjan. 82%.
- Avenue Residence 6Nearby in Al Furjan. 82%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.