Symbolic Aura construction progress
No completion date is registered for Symbolic Aura in Al Furjan yet. At the last site inspection, in August 2026, it was 70% built. The developer is Speedex Aura Developers.
70%
Built, at the site inspection of 17 August 2026
- Finish at recent pace
- February 2027
- Construction started
- June 2024
- First registered
- May 2024
- Developer
- Speedex Aura Developers
- Community
- Al Furjan
- Units
- 78
- Escrow bank
- Emirates NBD
- Name in Arabic
- سيمبوليك اورا
- Project number
- 2988
- Site inspections
- 5
Schedule
Since October 2025 Symbolic Aura has added about 4.8 points a month. At that rate the site reaches 100% around February 2027. No completion date is on record to compare it with.
Site inspections
17 August 2026
70%+26 pts
7 April 2026
44%+21 pts
24 October 2025
23%+10 pts
30 April 2025
13%+13 pts
7 March 2024
0%
Context
Al Furjan has 38 projects under construction, 32% built on average.
Own a unit in Symbolic Aura?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Symbolic Aura handover date?
- No completion date is on record for Symbolic Aura yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Symbolic Aura?
- Symbolic Aura was 70% built at the site inspection on 17 August 2026. The site has been inspected 5 times since March 2024. The Land Department took 34 site photos at its inspections.
- Who is building Symbolic Aura?
- The registered developer is Speedex Aura Developers.
- Which bank holds the escrow account for Symbolic Aura?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Primero Residences By Main RealtyNearby in Al Furjan. 21%, Due June 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.