Symbolic Aura construction progress

No completion date is registered for Symbolic Aura in Al Furjan yet. At the last site inspection, in August 2026, it was 70% built. The developer is Speedex Aura Developers.

70%

Built, at the site inspection of 17 August 2026

Finish at recent pace
February 2027
Construction started
June 2024
First registered
May 2024
Developer
Speedex Aura Developers
Community
Al Furjan
Units
78
Escrow bank
Emirates NBD
Name in Arabic
سيمبوليك اورا
Project number
2988
Site inspections
5

Schedule

Since October 2025 Symbolic Aura has added about 4.8 points a month. At that rate the site reaches 100% around February 2027. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

17 August 2026

70%+26 pts

  • Symbolic Aura construction site, inspection photo 1, 17 August 2026
  • Symbolic Aura construction site, inspection photo 2, 17 August 2026
  • Symbolic Aura construction site, inspection photo 3, 17 August 2026
  • Symbolic Aura construction site, inspection photo 4, 17 August 2026

7 April 2026

44%+21 pts

  • Symbolic Aura construction site, inspection photo 1, 7 April 2026
  • Symbolic Aura construction site, inspection photo 2, 7 April 2026
  • Symbolic Aura construction site, inspection photo 3, 7 April 2026
  • Symbolic Aura construction site, inspection photo 4, 7 April 2026

24 October 2025

23%+10 pts

  • Symbolic Aura construction site, inspection photo 1, 24 October 2025
  • Symbolic Aura construction site, inspection photo 2, 24 October 2025
  • Symbolic Aura construction site, inspection photo 3, 24 October 2025
  • Symbolic Aura construction site, inspection photo 4, 24 October 2025

30 April 2025

13%+13 pts

  • Symbolic Aura construction site, inspection photo 1, 30 April 2025
  • Symbolic Aura construction site, inspection photo 2, 30 April 2025
  • Symbolic Aura construction site, inspection photo 3, 30 April 2025
  • Symbolic Aura construction site, inspection photo 4, 30 April 2025

7 March 2024

0%

  • Symbolic Aura construction site, inspection photo 1, 7 March 2024
  • Symbolic Aura construction site, inspection photo 2, 7 March 2024
  • Symbolic Aura construction site, inspection photo 3, 7 March 2024

All 34 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Symbolic Aura?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Symbolic Aura handover date?
No completion date is on record for Symbolic Aura yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Symbolic Aura?
Symbolic Aura was 70% built at the site inspection on 17 August 2026. The site has been inspected 5 times since March 2024. The Land Department took 34 site photos at its inspections.
Who is building Symbolic Aura?
The registered developer is Speedex Aura Developers.
Which bank holds the escrow account for Symbolic Aura?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.