Off-plan projects in Business Bay
43 projects in Business Bay are under construction. On average they are 37% built. 12 have passed their registered completion date. The next one due is Al Habtoor Tower, in December 2026.
- Burj PacificPacific Ventures Limited99%Due January 2023, passed
- Al Habtoor TowerAl Habtoor City Real Estate Development (Br. Of Dubai National Investment Co90%Due December 2026
- Chic TowerPax Investment84%Due July 2025, passed
- West Bay TowerOrion Real Estate Development83%Due February 2024, passed
- Urban LifeUrban Properties Development80%Due June 2026, passed
- Onda By KascoKasco Real Estate Development70%Due August 2027
- The QuaysideQuayside Developers70%Due March 2026, passed
- Eywa DubaiRvl Real Estate66%Due April 2026, passed
- Bugatti Residences By BinghattiBinghatti Developers66%Due December 2025, passed
- Dg1 LivingDar Dg Global Property Development65%Due April 2027
- The CrestmarkEllington Properties Development61%No date set
- Royal Regency SuitesAlseeb Real Estate Development57%Due December 2026
- Burj Binghatti Jacob & Co. ResidencesBinghatti Developers52%Due June 2026, passed
- Luxury Family Residence IIIKappa Acca Real Estate Development51%Due June 2025, passed
- One By BinghattiBinghatti Developers50%Due May 2026, passed
- Vela By OmniyatDowntown Creek Real Estate Development50%No date set
- One River PointDutco Ellington Canal Front Real Estate48%Due June 2027
- Vento TowerAnax Developments43%No date set
- Canal CrownGalaxy Sky Real Estate Development42%Due February 2027
- Aykon City 3Damac Canal One Property Development38%Due December 2027
- Canal Heights 2Resta Real Estate Development36%Due March 2027
- Canal HeightsVesta Real Estate Development36%Due December 2026
- Binghatti SkyriseBinghatti Developers36%Due December 2026
- Canal Crown 2One Quantem Real Estate Development33%Due March 2027
- Binghatti SkyhallBinghatti Developers31%Due August 2026, passed
- Binghatti AquariseBinghatti Developers28%Due October 2026, passed
- Vela Viento By OmniyatRoyal Creek Real Estate Development22%Due May 2027
- Regent Residences Dubai Sankari PlaceMarina Sky Villa Downtown16%Due December 2027
- 77s77 Shades Of Green Realestate Development14%Due December 2028
- ElireQube Development12%Due December 2028
- Tiger Sky TowerTiger Properties10%No date set
- One.B Tower1b Tower Co10%Due December 2028
- Bayz 101 By DanubeDanube Properties Development10%No date set
- Rove Home Marasi DriveIrth Signature Development10%Due August 2027
- Enara By OmniyatForty Two Downtown Real Estate Developments7.3%Due December 2027
- Bayz 102 By DanubeDanube Properties Development6.5%Due December 2029
- Burj CapitalCenturion Capital One Properties2.6%Due December 2028
- Downtown ResidencesDeyaar Development1.3%Due December 2030
- Eywa The Way Of WaterRevolution Palm Real Estate0%Due October 2028
- Lumena By OmniyatCreek Views Real Estate Development0%Due December 2029
- Lumena South Tower By OmniyatAzure Horizon Real Estate Developments0%Due April 2031
- VelorGinco Properties0%Due November 2027
- WedyanWedyan Al Ghurair Real Estate Development0%Due September 2029
Questions
How many off-plan projects are under construction in Business Bay?
43 projects are under construction in Business Bay, 37% built on average at the latest site inspections.
Which Business Bay projects are due to finish next?
By registered completion date: Al Habtoor Tower (December 2026, 90% built), Royal Regency Suites (December 2026, 57% built) and Canal Heights (December 2026, 36% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
How many Business Bay projects are past their completion date?
12 of 43, among them Burj Pacific, West Bay Tower and Luxury Family Residence III. A project counts as late once its registered completion date has passed before it reaches 100%.
Which developers are building in Business Bay?
The developers with the most projects here are Binghatti Developers (6) and Danube Properties Development (2), out of 37 building in Business Bay.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.