Off-plan projects in Business Bay
43 projects in Business Bay are under construction according to the Dubai Land Department. On average they are 35% built. 10 have passed their registered completion date. The next one due is Binghatti Aquarise, in October 2026.
- Burj PacificPacific Ventures Limited99%Due January 2023, passed
- Al Habtoor TowerAl Habtoor City Real Estate Development (Br. Of Dubai National Investment Co90%Due December 2026
- Chic TowerPax Investment84%Due July 2025, passed
- West Bay TowerOrion Real Estate Development83%Due February 2024, passed
- Urban LifeUrban Properties Development71%Due June 2026, passed
- Bugatti Residences By BinghattiBinghatti Developers66%Due December 2025, passed
- Dg1 LivingDar Dg Global Property Development65%No date set
- Eywa DubaiRvl Real Estate64%Due April 2026, passed
- The CrestmarkEllington Properties Development61%No date set
- Onda By KascoKasco Real Estate Development61%Due August 2027
- Royal Regency SuitesAlseeb Real Estate Development56%No date set
- The QuaysideQuayside Developers55%Due March 2026, passed
- Burj Binghatti Jacob & Co. ResidencesBinghatti Developers52%Due June 2026, passed
- Luxury Family Residence IiiKappa Acca Real Estate Development51%Due June 2025, passed
- One By BinghattiBinghatti Developers50%No date set
- Vela By OmniyatDowntown Creek Real Estate Development50%No date set
- Canal CrownGalaxy Sky Real Estate Development42%Due February 2027
- Canal Heights 2Resta Real Estate Development36%Due March 2027
- Canal HeightsVesta Real Estate Development36%Due December 2026
- One River PointDutco Ellington Canal Front Real Estate35%Due June 2027
- Vento TowerAnax Developments34%No date set
- Canal Crown 2One Quantem Real Estate Development33%Due March 2027
- Aykon City 3Damac Canal One Property Development31%Due December 2027
- Binghatti SkyhallBinghatti Developers31%Due August 2026, passed
- Binghatti SkyriseBinghatti Developers22%Due December 2026
- Vela Viento By OmniyatRoyal Creek Real Estate Development22%No date set
- Binghatti AquariseBinghatti Developers21%Due October 2026
- 77s77 Shades Of Green Realestate Development14%Due December 2028
- Tiger Sky TowerTiger Properties10%No date set
- Bayz 101 By DanubeDanube Properties Development10%No date set
- Rove Home Marasi DriveIrth Signature Development10%Due August 2027
- Regent Residences Dubai Sankari PlaceMarina Sky Villa Downtown8.9%Due December 2027
- ElireQube Development8.2%No date set
- Enara By OmniyatForty Two Downtown Real Estate Developments7.3%Due December 2027
- Bayz 102 By DanubeDanube Properties Development6.5%No date set
- One.B Tower1b Tower Co5.8%Due December 2028
- Burj CapitalCenturion Capital One Properties1.5%Due December 2028
- Downtown ResidencesDeyaar Development1.3%Due December 2030
- Eywa The Way Of WaterRevolution Palm Real Estate0%Due October 2028
- Lumena Alta By OmniyatAzure Horizon Real Estate Developments0%Due April 2031
- Lumena By OmniyatCreek Views Real Estate Development0%Due December 2029
- VelorGinco Properties0%Due November 2027
- WedyanWedyan Al Ghurair Real Estate Development0%Due September 2029
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.