Onda By Kasco construction progress

Onda By Kasco in Business Bay is 61% built at the Land Department inspection of August 2026. Developer Kasco Real Estate Development. Completion registered for August 2027.

61%

Built, at the Land Department site inspection of 19 August 2026

On pace for its date

Completion date (Land Department)
August 2027
Finish at recent pace
July 2027
Construction started
September 2024
Registered with the Land Department
August 2024
Community
Business Bay
Units
352
Escrow bank
Emirates NBD
Name in Arabic
اوندا - كاسكو
Land Department project number
3052
Land Department site inspections
7

Schedule

Since September 2025 Onda By Kasco has added about 3.7 points a month. That puts 100% around July 2027, within three months of its registered completion date of August 2027.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 August 2026

61%+9.6 pts

  • Onda By Kasco construction site, Land Department inspection photo 1, 19 August 2026
  • Onda By Kasco construction site, Land Department inspection photo 2, 19 August 2026
  • Onda By Kasco construction site, Land Department inspection photo 3, 19 August 2026
  • Onda By Kasco construction site, Land Department inspection photo 4, 19 August 2026

7 May 2026

51%+16 pts

  • Onda By Kasco construction site, Land Department inspection photo 1, 7 May 2026
  • Onda By Kasco construction site, Land Department inspection photo 2, 7 May 2026
  • Onda By Kasco construction site, Land Department inspection photo 3, 7 May 2026
  • Onda By Kasco construction site, Land Department inspection photo 4, 7 May 2026

29 January 2026

36%+15 pts

  • Onda By Kasco construction site, Land Department inspection photo 1, 29 January 2026
  • Onda By Kasco construction site, Land Department inspection photo 2, 29 January 2026
  • Onda By Kasco construction site, Land Department inspection photo 3, 29 January 2026
  • Onda By Kasco construction site, Land Department inspection photo 4, 29 January 2026

15 September 2025

21%+6.3 pts

  • Onda By Kasco construction site, Land Department inspection photo 1, 15 September 2025
  • Onda By Kasco construction site, Land Department inspection photo 2, 15 September 2025
  • Onda By Kasco construction site, Land Department inspection photo 3, 15 September 2025
  • Onda By Kasco construction site, Land Department inspection photo 4, 15 September 2025

28 May 2025

14%+5.7 pts

  • Onda By Kasco construction site, Land Department inspection photo 1, 28 May 2025
  • Onda By Kasco construction site, Land Department inspection photo 2, 28 May 2025
  • Onda By Kasco construction site, Land Department inspection photo 3, 28 May 2025
  • Onda By Kasco construction site, Land Department inspection photo 4, 28 May 2025

12 February 2025

8.6%+8.6 pts

  • Onda By Kasco construction site, Land Department inspection photo 1, 12 February 2025
  • Onda By Kasco construction site, Land Department inspection photo 2, 12 February 2025
  • Onda By Kasco construction site, Land Department inspection photo 3, 12 February 2025
  • Onda By Kasco construction site, Land Department inspection photo 4, 12 February 2025

10 May 2024

0%

  • Onda By Kasco construction site, Land Department inspection photo 1, 10 May 2024
  • Onda By Kasco construction site, Land Department inspection photo 2, 10 May 2024

All 41 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Kasco Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Onda By Kasco?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Onda By Kasco be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Onda By Kasco is built?
61%, measured at the Land Department site inspection on 19 August 2026. The Land Department engineers have inspected the site 7 times since May 2024.
Is Onda By Kasco delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of August 2027.
Who is building Onda By Kasco?
The registered developer is Kasco Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Onda By Kasco?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.