Onda By Kasco construction progress
The registered completion date for Onda By Kasco in Business Bay is August 2027. At the last site inspection, in August 2026, it was 61% built. The developer is Kasco Real Estate Development.
70%
Built, at the site inspection of 19 August 2026
On pace for its date
- Registered completion date
- August 2027
- Finish at recent pace
- July 2027
- Construction started
- September 2024
- First registered
- August 2024
- Developer
- Kasco Real Estate Development
- Community
- Business Bay
- Units
- 352
- Escrow bank
- Emirates NBD
- Name in Arabic
- اوندا - كاسكو
- Project number
- 3052
- Site inspections
- 7
Schedule
Since September 2025 Onda By Kasco has added about 3.7 points a month. That puts 100% around July 2027, within three months of its registered completion date of August 2027.
Site inspections
19 August 2026
61%+9.6 pts
7 May 2026
51%+16 pts
29 January 2026
36%+15 pts
15 September 2025
21%+6.3 pts
28 May 2025
14%+5.7 pts
12 February 2025
8.6%+8.6 pts
10 May 2024
0%
Context
Business Bay has 43 projects under construction, 37% built on average.
Kasco Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Onda By Kasco?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Onda By Kasco handover date?
- The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Onda By Kasco?
- Onda By Kasco was 70% built at the site inspection on 19 August 2026. The site has been inspected 7 times since May 2024. The Land Department took 41 site photos at its inspections.
- Is Onda By Kasco delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of August 2027.
- Who is building Onda By Kasco?
- The registered developer is Kasco Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Onda By Kasco?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Val By KascoAlso by Kasco Real Estate Development. 82%, Due December 2026.
- Fala By KascoAlso by Kasco Real Estate Development. 0%, Due November 2028.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.










.jpeg&w=3840&q=75)