Onda By Kasco construction progress

The registered completion date for Onda By Kasco in Business Bay is August 2027. At the last site inspection, in August 2026, it was 61% built. The developer is Kasco Real Estate Development.

70%

Built, at the site inspection of 19 August 2026

On pace for its date

Registered completion date
August 2027
Finish at recent pace
July 2027
Construction started
September 2024
First registered
August 2024
Community
Business Bay
Units
352
Escrow bank
Emirates NBD
Name in Arabic
اوندا - كاسكو
Project number
3052
Site inspections
7

Schedule

Since September 2025 Onda By Kasco has added about 3.7 points a month. That puts 100% around July 2027, within three months of its registered completion date of August 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 August 2026

61%+9.6 pts

  • Onda By Kasco construction site, inspection photo 1, 19 August 2026
  • Onda By Kasco construction site, inspection photo 2, 19 August 2026
  • Onda By Kasco construction site, inspection photo 3, 19 August 2026
  • Onda By Kasco construction site, inspection photo 4, 19 August 2026

7 May 2026

51%+16 pts

  • Onda By Kasco construction site, inspection photo 1, 7 May 2026
  • Onda By Kasco construction site, inspection photo 2, 7 May 2026
  • Onda By Kasco construction site, inspection photo 3, 7 May 2026
  • Onda By Kasco construction site, inspection photo 4, 7 May 2026

29 January 2026

36%+15 pts

  • Onda By Kasco construction site, inspection photo 1, 29 January 2026
  • Onda By Kasco construction site, inspection photo 2, 29 January 2026
  • Onda By Kasco construction site, inspection photo 3, 29 January 2026
  • Onda By Kasco construction site, inspection photo 4, 29 January 2026

15 September 2025

21%+6.3 pts

  • Onda By Kasco construction site, inspection photo 1, 15 September 2025
  • Onda By Kasco construction site, inspection photo 2, 15 September 2025
  • Onda By Kasco construction site, inspection photo 3, 15 September 2025
  • Onda By Kasco construction site, inspection photo 4, 15 September 2025

28 May 2025

14%+5.7 pts

  • Onda By Kasco construction site, inspection photo 1, 28 May 2025
  • Onda By Kasco construction site, inspection photo 2, 28 May 2025
  • Onda By Kasco construction site, inspection photo 3, 28 May 2025
  • Onda By Kasco construction site, inspection photo 4, 28 May 2025

12 February 2025

8.6%+8.6 pts

  • Onda By Kasco construction site, inspection photo 1, 12 February 2025
  • Onda By Kasco construction site, inspection photo 2, 12 February 2025
  • Onda By Kasco construction site, inspection photo 3, 12 February 2025
  • Onda By Kasco construction site, inspection photo 4, 12 February 2025

10 May 2024

0%

  • Onda By Kasco construction site, inspection photo 1, 10 May 2024
  • Onda By Kasco construction site, inspection photo 2, 10 May 2024

All 41 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Kasco Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Onda By Kasco?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Onda By Kasco handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Onda By Kasco?
Onda By Kasco was 70% built at the site inspection on 19 August 2026. The site has been inspected 7 times since May 2024. The Land Department took 41 site photos at its inspections.
Is Onda By Kasco delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of August 2027.
Who is building Onda By Kasco?
The registered developer is Kasco Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Onda By Kasco?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.