Regent Residences Dubai Sankari Place construction progress
Regent Residences Dubai Sankari Place in Business Bay is 8.9% built at the Land Department inspection of July 2026. Developer Marina Sky Villa Downtown. Completion registered for December 2027.
8.9%
Built, at the Land Department site inspection of 21 July 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- March 2033
- Construction started
- July 2024
- Registered with the Land Department
- March 2024
- Developer
- Marina Sky Villa Downtown
- Community
- Business Bay
- Units
- 65
- Escrow bank
- Mashreq Bank
- Name in Arabic
- ريجنت ريزيدنسز دبى سنكرى بليس
- Land Department project number
- 2876
- Land Department site inspections
- 4
Schedule
Between April 2026 and July 2026 the site added about 1.1 points a month. At that rate it would finish around March 2033, more than three months after the December 2027 date registered with the Land Department.
Site inspections
21 July 2026
8.9%+3.3 pts
23 April 2026
5.6%+4.3 pts
18 November 2024
1.3%+1.3 pts
19 December 2023
0%
Context
Business Bay has 43 projects under construction, 35% built on average.
Own a unit in Regent Residences Dubai Sankari Place?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Regent Residences Dubai Sankari Place be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around March 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Regent Residences Dubai Sankari Place is built?
- 8.9%, measured at the Land Department site inspection on 21 July 2026. The Land Department engineers have inspected the site 4 times since December 2023.
- Is Regent Residences Dubai Sankari Place delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Regent Residences Dubai Sankari Place?
- The registered developer is Marina Sky Villa Downtown.
- Which bank holds the escrow account for Regent Residences Dubai Sankari Place?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.