Urban Life construction progress

Urban Life in Business Bay is 71% built at the Land Department inspection of August 2026. Developer Urban Properties Development. Completion registered for June 2026.

71%

Built, at the Land Department site inspection of 25 August 2026

4 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
January 2027
Construction started
January 2024
Registered with the Land Department
August 2024
Developer
Urban Properties Development
Community
Business Bay
Units
147
Escrow bank
Sharjah Islamic Bank
Name in Arabic
اربن لايف
Land Department project number
3041
Land Department site inspections
6

Schedule

Urban Life was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 5.6 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 August 2026

71%+11 pts

  • Urban Life construction site, Land Department inspection photo 1, 25 August 2026
  • Urban Life construction site, Land Department inspection photo 2, 25 August 2026
  • Urban Life construction site, Land Department inspection photo 3, 25 August 2026
  • Urban Life construction site, Land Department inspection photo 4, 25 August 2026

9 July 2026

61%+16 pts

  • Urban Life construction site, Land Department inspection photo 1, 9 July 2026
  • Urban Life construction site, Land Department inspection photo 2, 9 July 2026
  • Urban Life construction site, Land Department inspection photo 3, 9 July 2026
  • Urban Life construction site, Land Department inspection photo 4, 9 July 2026

3 April 2026

45%+28 pts

  • Urban Life construction site, Land Department inspection photo 1, 3 April 2026
  • Urban Life construction site, Land Department inspection photo 2, 3 April 2026
  • Urban Life construction site, Land Department inspection photo 3, 3 April 2026
  • Urban Life construction site, Land Department inspection photo 4, 3 April 2026

14 May 2025

17%+4.0 pts

  • Urban Life construction site, Land Department inspection photo 1, 14 May 2025
  • Urban Life construction site, Land Department inspection photo 2, 14 May 2025
  • Urban Life construction site, Land Department inspection photo 3, 14 May 2025
  • Urban Life construction site, Land Department inspection photo 4, 14 May 2025

10 February 2025

13%+7.9 pts

  • Urban Life construction site, Land Department inspection photo 1, 10 February 2025
  • Urban Life construction site, Land Department inspection photo 2, 10 February 2025
  • Urban Life construction site, Land Department inspection photo 3, 10 February 2025

9 July 2024

4.7%

  • Urban Life construction site, Land Department inspection photo 1, 9 July 2024
  • Urban Life construction site, Land Department inspection photo 2, 9 July 2024
  • Urban Life construction site, Land Department inspection photo 3, 9 July 2024
  • Urban Life construction site, Land Department inspection photo 4, 9 July 2024

All 46 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Own a unit in Urban Life?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Urban Life be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Urban Life is built?
71%, measured at the Land Department site inspection on 25 August 2026. The Land Department engineers have inspected the site 6 times since July 2024.
Is Urban Life delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Urban Life?
The registered developer is Urban Properties Development.
Which bank holds the escrow account for Urban Life?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.