Urban Life construction progress
Urban Life in Business Bay is 71% built at the Land Department inspection of August 2026. Developer Urban Properties Development. Completion registered for June 2026.
71%
Built, at the Land Department site inspection of 25 August 2026
4 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- January 2027
- Construction started
- January 2024
- Registered with the Land Department
- August 2024
- Developer
- Urban Properties Development
- Community
- Business Bay
- Units
- 147
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- اربن لايف
- Land Department project number
- 3041
- Land Department site inspections
- 6
Schedule
Urban Life was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 5.6 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
25 August 2026
71%+11 pts
9 July 2026
61%+16 pts
3 April 2026
45%+28 pts
14 May 2025
17%+4.0 pts
10 February 2025
13%+7.9 pts
9 July 2024
4.7%
Context
Business Bay has 43 projects under construction, 35% built on average.
Own a unit in Urban Life?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Urban Life be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Urban Life is built?
- 71%, measured at the Land Department site inspection on 25 August 2026. The Land Department engineers have inspected the site 6 times since July 2024.
- Is Urban Life delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Urban Life?
- The registered developer is Urban Properties Development.
- Which bank holds the escrow account for Urban Life?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.