Urban Life construction progress
Urban Life in Business Bay was registered to complete in June 2026 and is still under construction. At the last site inspection, in October 2026, it was 80% built. The developer is Urban Properties Development.
80%
Built, at the site inspection of 16 October 2026
5 months past its registered completion date
- Registered completion date
- June 2026
- Finish at recent pace
- February 2027
- Construction started
- January 2024
- First registered
- August 2024
- Developer
- Urban Properties Development
- Community
- Business Bay
- Units
- 147
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- اربن لايف
- Project number
- 3041
- Site inspections
- 7
Schedule
Urban Life was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 5.5 points a month. Kept at that rate, the site would reach 100% around February 2027.
Site inspections
16 October 2026
80%+8.7 pts
25 August 2026
71%+11 pts
9 July 2026
61%+16 pts
3 April 2026
45%+28 pts
14 May 2025
17%+4.0 pts
10 February 2025
13%+7.9 pts
9 July 2024
4.7%
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in Urban Life?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Urban Life handover date?
- The registered completion date was June 2026, and the register still lists Urban Life as under construction. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Urban Life?
- Urban Life was 80% built at the site inspection on 16 October 2026. The site has been inspected 7 times since July 2024. The Land Department took 58 site photos at its inspections.
- Is Urban Life delayed?
- Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
- Who is building Urban Life?
- The registered developer is Urban Properties Development.
- Which bank holds the escrow account for Urban Life?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)