Burj Capital construction progress

Burj Capital in Business Bay is 1.5% built at the Land Department inspection of July 2026. Developer Centurion Capital One Properties. Completion registered for December 2028.

1.5%

Built, at the Land Department site inspection of 28 July 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
October 2054
Construction started
June 2025
Registered with the Land Department
June 2025
Developer
Centurion Capital One Properties
Community
Business Bay
Units
296
Escrow bank
Emirates Islamic Bank
Name in Arabic
برج كابيتال
Land Department project number
3659
Land Department site inspections
3

Schedule

Between April 2026 and July 2026 the site added about 0.3 points a month. At that rate it would finish around October 2054, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

28 July 2026

1.5%+1.1 pts

  • Burj Capital construction site, Land Department inspection photo 1, 28 July 2026
  • Burj Capital construction site, Land Department inspection photo 2, 28 July 2026
  • Burj Capital construction site, Land Department inspection photo 3, 28 July 2026
  • Burj Capital construction site, Land Department inspection photo 4, 28 July 2026

8 April 2026

0.4%+0.4 pts

  • Burj Capital construction site, Land Department inspection photo 1, 8 April 2026
  • Burj Capital construction site, Land Department inspection photo 2, 8 April 2026
  • Burj Capital construction site, Land Department inspection photo 3, 8 April 2026

25 April 2025

0%

  • Burj Capital construction site, Land Department inspection photo 1, 25 April 2025
  • Burj Capital construction site, Land Department inspection photo 2, 25 April 2025

All 10 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Own a unit in Burj Capital?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Burj Capital be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around October 2054. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Burj Capital is built?
1.5%, measured at the Land Department site inspection on 28 July 2026. The Land Department engineers have inspected the site 3 times since April 2025.
Is Burj Capital delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Burj Capital?
The registered developer is Centurion Capital One Properties.
Which bank holds the escrow account for Burj Capital?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.