Burj Capital construction progress

The registered completion date for Burj Capital in Business Bay is December 2028. At the last site inspection, in November 2026, it was 2.6% built. The developer is Centurion Capital One Properties.

2.6%

Built, at the site inspection of 9 November 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
July 2053
Construction started
June 2025
First registered
June 2025
Developer
Centurion Capital One Properties
Community
Business Bay
Units
296
Escrow bank
Emirates Islamic Bank
Name in Arabic
برج كابيتال
Project number
3659
Site inspections
4

Schedule

Between April 2026 and November 2026 the site added about 0.3 points a month. At that rate it would finish around July 2053, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 November 2026

2.6%+1.1 pts

  • Burj Capital construction site, inspection photo 1, 9 November 2026
  • Burj Capital construction site, inspection photo 2, 9 November 2026
  • Burj Capital construction site, inspection photo 3, 9 November 2026
  • Burj Capital construction site, inspection photo 4, 9 November 2026

28 July 2026

1.5%+1.1 pts

  • Burj Capital construction site, inspection photo 1, 28 July 2026
  • Burj Capital construction site, inspection photo 2, 28 July 2026
  • Burj Capital construction site, inspection photo 3, 28 July 2026
  • Burj Capital construction site, inspection photo 4, 28 July 2026

8 April 2026

0.4%+0.4 pts

  • Burj Capital construction site, inspection photo 1, 8 April 2026
  • Burj Capital construction site, inspection photo 2, 8 April 2026
  • Burj Capital construction site, inspection photo 3, 8 April 2026

25 April 2025

0%

  • Burj Capital construction site, inspection photo 1, 25 April 2025
  • Burj Capital construction site, inspection photo 2, 25 April 2025

All 17 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Burj Capital?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Burj Capital handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2053. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Burj Capital?
Burj Capital was 2.6% built at the site inspection on 9 November 2026. The site has been inspected 4 times since April 2025. The Land Department took 17 site photos at its inspections.
Is Burj Capital delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Burj Capital?
The registered developer is Centurion Capital One Properties.
Which bank holds the escrow account for Burj Capital?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.