Enara By Omniyat construction progress

The registered completion date for Enara By Omniyat in Business Bay is December 2027. At the last site inspection, in June 2026, it was 7.3% built. The developer is Forty Two Downtown Real Estate Developments.

7.3%

Built, at the site inspection of 12 June 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
March 2048
Construction started
October 2024
First registered
September 2024
Developer
Forty Two Downtown Real Estate Developments
Community
Business Bay
Units
49
Escrow bank
Mashreq Bank
Name in Arabic
إنارة من أمنيات
Project number
3220
Site inspections
4

Schedule

Between August 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around March 2048, more than three months after its registered date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 June 2026

7.3%+1.6 pts

  • Enara By Omniyat construction site, inspection photo 1, 12 June 2026
  • Enara By Omniyat construction site, inspection photo 2, 12 June 2026
  • Enara By Omniyat construction site, inspection photo 3, 12 June 2026
  • Enara By Omniyat construction site, inspection photo 4, 12 June 2026

20 January 2026

5.6%+2.0 pts

  • Enara By Omniyat construction site, inspection photo 1, 20 January 2026
  • Enara By Omniyat construction site, inspection photo 2, 20 January 2026
  • Enara By Omniyat construction site, inspection photo 3, 20 January 2026
  • Enara By Omniyat construction site, inspection photo 4, 20 January 2026

8 August 2025

3.7%+3.7 pts

  • Enara By Omniyat construction site, inspection photo 1, 8 August 2025
  • Enara By Omniyat construction site, inspection photo 2, 8 August 2025
  • Enara By Omniyat construction site, inspection photo 3, 8 August 2025
  • Enara By Omniyat construction site, inspection photo 4, 8 August 2025

15 August 2024

0%

  • Enara By Omniyat construction site, inspection photo 1, 15 August 2024
  • Enara By Omniyat construction site, inspection photo 2, 15 August 2024

All 18 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Enara By Omniyat?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Enara By Omniyat handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2048. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Enara By Omniyat?
Enara By Omniyat was 7.3% built at the site inspection on 12 June 2026. The site has been inspected 4 times since August 2024. The Land Department took 18 site photos at its inspections.
Is Enara By Omniyat delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Enara By Omniyat?
The registered developer is Forty Two Downtown Real Estate Developments.
Which bank holds the escrow account for Enara By Omniyat?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.