Enara By Omniyat construction progress
The registered completion date for Enara By Omniyat in Business Bay is December 2027. At the last site inspection, in June 2026, it was 7.3% built. The developer is Forty Two Downtown Real Estate Developments.
7.3%
Built, at the site inspection of 12 June 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- March 2048
- Construction started
- October 2024
- First registered
- September 2024
- Developer
- Forty Two Downtown Real Estate Developments
- Community
- Business Bay
- Units
- 49
- Escrow bank
- Mashreq Bank
- Name in Arabic
- إنارة من أمنيات
- Project number
- 3220
- Site inspections
- 4
Schedule
Between August 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around March 2048, more than three months after its registered date of December 2027.
Site inspections
12 June 2026
7.3%+1.6 pts
20 January 2026
5.6%+2.0 pts
8 August 2025
3.7%+3.7 pts
15 August 2024
0%
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in Enara By Omniyat?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Enara By Omniyat handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2048. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Enara By Omniyat?
- Enara By Omniyat was 7.3% built at the site inspection on 12 June 2026. The site has been inspected 4 times since August 2024. The Land Department took 18 site photos at its inspections.
- Is Enara By Omniyat delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Enara By Omniyat?
- The registered developer is Forty Two Downtown Real Estate Developments.
- Which bank holds the escrow account for Enara By Omniyat?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.