Binghatti Skyrise construction progress
The registered completion date for Binghatti Skyrise in Business Bay is December 2026. At the last site inspection, in October 2026, it was 36% built. The developer is Binghatti Developers.
36%
Built, at the site inspection of 22 October 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- March 2029
- Construction started
- October 2024
- First registered
- October 2024
- Developer
- Binghatti Developers
- Community
- Business Bay
- Units
- 3,358
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بن غاطي سكاي رايز
- Project number
- 3349
- Site inspections
- 3
Schedule
Between April 2026 and October 2026 the site added about 2.3 points a month. At that rate it would finish around March 2029, more than three months after its registered date of December 2026.
Site inspections
22 October 2026
36%+13 pts
23 April 2026
22%+22 pts
15 October 2024
0.1%
Context
Business Bay has 43 projects under construction, 37% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Skyrise?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Skyrise handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Skyrise?
- Binghatti Skyrise was 36% built at the site inspection on 22 October 2026. The site has been inspected 3 times since October 2024. The Land Department took 30 site photos at its inspections.
- Is Binghatti Skyrise delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Binghatti Skyrise?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Skyrise?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)