Binghatti Skyrise construction progress
Binghatti Skyrise in Business Bay is 22% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for December 2026.
22%
Built, at the Land Department site inspection of 23 April 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- August 2031
- Construction started
- October 2024
- Registered with the Land Department
- October 2024
- Developer
- Binghatti Developers
- Community
- Business Bay
- Units
- 3,358
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بن غاطي سكاي رايز
- Land Department project number
- 3349
- Land Department site inspections
- 2
Schedule
Between October 2024 and April 2026 the site added about 1.2 points a month. At that rate it would finish around August 2031, more than three months after the December 2026 date registered with the Land Department.
Site inspections
23 April 2026
22%+22 pts
15 October 2024
0.1%
Context
Business Bay has 43 projects under construction, 35% built on average. Binghatti Skyrise is behind that average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Skyrise?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Binghatti Skyrise be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around August 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Skyrise is built?
- 22%, measured at the Land Department site inspection on 23 April 2026. The Land Department engineers have inspected the site 2 times since October 2024.
- Is Binghatti Skyrise delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Binghatti Skyrise?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Skyrise?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)