Binghatti Skyrise construction progress

The registered completion date for Binghatti Skyrise in Business Bay is December 2026. At the last site inspection, in October 2026, it was 36% built. The developer is Binghatti Developers.

36%

Built, at the site inspection of 22 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
March 2029
Construction started
October 2024
First registered
October 2024
Community
Business Bay
Units
3,358
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي سكاي رايز
Project number
3349
Site inspections
3

Schedule

Between April 2026 and October 2026 the site added about 2.3 points a month. At that rate it would finish around March 2029, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

36%+13 pts

  • Binghatti Skyrise construction site, inspection photo 1, 22 October 2026
  • Binghatti Skyrise construction site, inspection photo 2, 22 October 2026
  • Binghatti Skyrise construction site, inspection photo 3, 22 October 2026
  • Binghatti Skyrise construction site, inspection photo 4, 22 October 2026

23 April 2026

22%+22 pts

  • Binghatti Skyrise construction site, inspection photo 1, 23 April 2026
  • Binghatti Skyrise construction site, inspection photo 2, 23 April 2026
  • Binghatti Skyrise construction site, inspection photo 3, 23 April 2026
  • Binghatti Skyrise construction site, inspection photo 4, 23 April 2026

15 October 2024

0.1%

  • Binghatti Skyrise construction site, inspection photo 1, 15 October 2024
  • Binghatti Skyrise construction site, inspection photo 2, 15 October 2024
  • Binghatti Skyrise construction site, inspection photo 3, 15 October 2024
  • Binghatti Skyrise construction site, inspection photo 4, 15 October 2024

All 30 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Skyrise?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Skyrise handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Skyrise?
Binghatti Skyrise was 36% built at the site inspection on 22 October 2026. The site has been inspected 3 times since October 2024. The Land Department took 30 site photos at its inspections.
Is Binghatti Skyrise delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Binghatti Skyrise?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Skyrise?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.