Binghatti Skyrise construction progress

Binghatti Skyrise in Business Bay is 22% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for December 2026.

22%

Built, at the Land Department site inspection of 23 April 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
August 2031
Construction started
October 2024
Registered with the Land Department
October 2024
Community
Business Bay
Units
3,358
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي سكاي رايز
Land Department project number
3349
Land Department site inspections
2

Schedule

Between October 2024 and April 2026 the site added about 1.2 points a month. At that rate it would finish around August 2031, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 April 2026

22%+22 pts

  • Binghatti Skyrise construction site, Land Department inspection photo 1, 23 April 2026
  • Binghatti Skyrise construction site, Land Department inspection photo 2, 23 April 2026
  • Binghatti Skyrise construction site, Land Department inspection photo 3, 23 April 2026
  • Binghatti Skyrise construction site, Land Department inspection photo 4, 23 April 2026

15 October 2024

0.1%

  • Binghatti Skyrise construction site, Land Department inspection photo 1, 15 October 2024
  • Binghatti Skyrise construction site, Land Department inspection photo 2, 15 October 2024
  • Binghatti Skyrise construction site, Land Department inspection photo 3, 15 October 2024
  • Binghatti Skyrise construction site, Land Department inspection photo 4, 15 October 2024

All 17 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average. Binghatti Skyrise is behind that average.

Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.

Own a unit in Binghatti Skyrise?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Binghatti Skyrise be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around August 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Binghatti Skyrise is built?
22%, measured at the Land Department site inspection on 23 April 2026. The Land Department engineers have inspected the site 2 times since October 2024.
Is Binghatti Skyrise delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Binghatti Skyrise?
The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Skyrise?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.