Bugatti Residences By Binghatti construction progress

Bugatti Residences By Binghatti in Business Bay was registered to complete in December 2025 and is still under construction. At the last site inspection, in September 2026, it was 66% built. The developer is Binghatti Developers.

66%

Built, at the site inspection of 23 September 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
June 2028
Construction started
March 2023
First registered
May 2023
Community
Business Bay
Units
187
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بوغاتي ريزيدنسز من بن غاطي
Project number
2547
Site inspections
4

Schedule

Bugatti Residences By Binghatti was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around June 2028.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 September 2026

66%+13 pts

  • Bugatti Residences By Binghatti construction site, inspection photo 1, 23 September 2026
  • Bugatti Residences By Binghatti construction site, inspection photo 2, 23 September 2026
  • Bugatti Residences By Binghatti construction site, inspection photo 3, 23 September 2026
  • Bugatti Residences By Binghatti construction site, inspection photo 4, 23 September 2026

20 January 2026

52%+32 pts

  • Bugatti Residences By Binghatti construction site, inspection photo 1, 20 January 2026
  • Bugatti Residences By Binghatti construction site, inspection photo 2, 20 January 2026
  • Bugatti Residences By Binghatti construction site, inspection photo 3, 20 January 2026
  • Bugatti Residences By Binghatti construction site, inspection photo 4, 20 January 2026

6 December 2024

20%+20 pts

  • Bugatti Residences By Binghatti construction site, inspection photo 1, 6 December 2024
  • Bugatti Residences By Binghatti construction site, inspection photo 2, 6 December 2024
  • Bugatti Residences By Binghatti construction site, inspection photo 3, 6 December 2024
  • Bugatti Residences By Binghatti construction site, inspection photo 4, 6 December 2024

18 May 2023

0%

  • Bugatti Residences By Binghatti construction site, inspection photo 1, 18 May 2023
  • Bugatti Residences By Binghatti construction site, inspection photo 2, 18 May 2023
  • Bugatti Residences By Binghatti construction site, inspection photo 3, 18 May 2023
  • Bugatti Residences By Binghatti construction site, inspection photo 4, 18 May 2023

All 29 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Bugatti Residences By Binghatti?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Bugatti Residences By Binghatti handover date?
The registered completion date was December 2025, and the register still lists Bugatti Residences By Binghatti as under construction. At the pace of its recent inspections the site would reach 100% around June 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Bugatti Residences By Binghatti?
Bugatti Residences By Binghatti was 66% built at the site inspection on 23 September 2026. The site has been inspected 4 times since May 2023. The Land Department took 29 site photos at its inspections.
Is Bugatti Residences By Binghatti delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Bugatti Residences By Binghatti?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Bugatti Residences By Binghatti?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.