Bugatti Residences By Binghatti construction progress
Bugatti Residences By Binghatti in Business Bay is 66% built at the Land Department inspection of September 2026. Developer Binghatti Developers. Completion registered for December 2025.
66%
Built, at the Land Department site inspection of 23 September 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- June 2028
- Construction started
- March 2023
- Registered with the Land Department
- May 2023
- Developer
- Binghatti Developers
- Community
- Business Bay
- Units
- 187
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- بوغاتي ريزيدنسز من بن غاطي
- Land Department project number
- 2547
- Land Department site inspections
- 4
Schedule
Bugatti Residences By Binghatti was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around June 2028.
Site inspections
23 September 2026
66%+13 pts
20 January 2026
52%+32 pts
6 December 2024
20%+20 pts
18 May 2023
0%
Context
Business Bay has 43 projects under construction, 35% built on average. Bugatti Residences By Binghatti is ahead of that average.
Binghatti Developers has 36 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Bugatti Residences By Binghatti?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Bugatti Residences By Binghatti be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around June 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Bugatti Residences By Binghatti is built?
- 66%, measured at the Land Department site inspection on 23 September 2026. The Land Department engineers have inspected the site 4 times since May 2023.
- Is Bugatti Residences By Binghatti delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Bugatti Residences By Binghatti?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Bugatti Residences By Binghatti?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- One By BinghattiAlso by Binghatti Developers. 50%.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.