Bugatti Residences By Binghatti construction progress

Bugatti Residences By Binghatti in Business Bay is 66% built at the Land Department inspection of September 2026. Developer Binghatti Developers. Completion registered for December 2025.

66%

Built, at the Land Department site inspection of 23 September 2026

9 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
June 2028
Construction started
March 2023
Registered with the Land Department
May 2023
Community
Business Bay
Units
187
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بوغاتي ريزيدنسز من بن غاطي
Land Department project number
2547
Land Department site inspections
4

Schedule

Bugatti Residences By Binghatti was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around June 2028.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 September 2026

66%+13 pts

  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 1, 23 September 2026
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 2, 23 September 2026
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 3, 23 September 2026
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 4, 23 September 2026

20 January 2026

52%+32 pts

  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 1, 20 January 2026
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 2, 20 January 2026
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 3, 20 January 2026
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 4, 20 January 2026

6 December 2024

20%+20 pts

  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 1, 6 December 2024
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 2, 6 December 2024
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 3, 6 December 2024
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 4, 6 December 2024

18 May 2023

0%

  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 1, 18 May 2023
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 2, 18 May 2023
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 3, 18 May 2023
  • Bugatti Residences By Binghatti construction site, Land Department inspection photo 4, 18 May 2023

All 29 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average. Bugatti Residences By Binghatti is ahead of that average.

Binghatti Developers has 36 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Bugatti Residences By Binghatti?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Bugatti Residences By Binghatti be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around June 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Bugatti Residences By Binghatti is built?
66%, measured at the Land Department site inspection on 23 September 2026. The Land Department engineers have inspected the site 4 times since May 2023.
Is Bugatti Residences By Binghatti delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Bugatti Residences By Binghatti?
The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
Which bank holds the escrow account for Bugatti Residences By Binghatti?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.