Binghatti Skyhall construction progress

Binghatti Skyhall in Business Bay is 31% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for August 2026.

31%

Built, at the Land Department site inspection of 30 April 2026

1 months past its registered completion date

Completion date (Land Department)
August 2026
Finish at recent pace
March 2029
Construction started
February 2025
Registered with the Land Department
March 2025
Community
Business Bay
Units
728
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بن غاطي سكاي هول
Land Department project number
3504
Land Department site inspections
2

Schedule

Binghatti Skyhall was registered to complete in August 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 2.0 points a month. Kept at that rate, the site would reach 100% around March 2029.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 April 2026

31%+31 pts

  • Binghatti Skyhall construction site, Land Department inspection photo 1, 30 April 2026
  • Binghatti Skyhall construction site, Land Department inspection photo 2, 30 April 2026
  • Binghatti Skyhall construction site, Land Department inspection photo 3, 30 April 2026
  • Binghatti Skyhall construction site, Land Department inspection photo 4, 30 April 2026

16 January 2025

0%

  • Binghatti Skyhall construction site, Land Department inspection photo 1, 16 January 2025
  • Binghatti Skyhall construction site, Land Department inspection photo 2, 16 January 2025
  • Binghatti Skyhall construction site, Land Department inspection photo 3, 16 January 2025

All 12 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.

Own a unit in Binghatti Skyhall?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Binghatti Skyhall be completed?
The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around March 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Binghatti Skyhall is built?
31%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 2 times since January 2025.
Is Binghatti Skyhall delayed?
Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
Who is building Binghatti Skyhall?
The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Skyhall?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.