Binghatti Skyhall construction progress
Binghatti Skyhall in Business Bay is 31% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for August 2026.
31%
Built, at the Land Department site inspection of 30 April 2026
1 months past its registered completion date
- Completion date (Land Department)
- August 2026
- Finish at recent pace
- March 2029
- Construction started
- February 2025
- Registered with the Land Department
- March 2025
- Developer
- Binghatti Developers
- Community
- Business Bay
- Units
- 728
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بن غاطي سكاي هول
- Land Department project number
- 3504
- Land Department site inspections
- 2
Schedule
Binghatti Skyhall was registered to complete in August 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 2.0 points a month. Kept at that rate, the site would reach 100% around March 2029.
Site inspections
30 April 2026
31%+31 pts
16 January 2025
0%
Context
Business Bay has 43 projects under construction, 35% built on average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Skyhall?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Binghatti Skyhall be completed?
- The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around March 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Skyhall is built?
- 31%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 2 times since January 2025.
- Is Binghatti Skyhall delayed?
- Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
- Who is building Binghatti Skyhall?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Skyhall?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.