Binghatti Skyhall construction progress

Binghatti Skyhall in Business Bay was registered to complete in August 2026 and is still under construction. At the last site inspection, in April 2026, it was 31% built. The developer is Binghatti Developers.

31%

Built, at the site inspection of 30 April 2026

3 months past its registered completion date

Registered completion date
August 2026
Finish at recent pace
March 2029
Construction started
February 2025
First registered
March 2025
Community
Business Bay
Units
728
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بن غاطي سكاي هول
Project number
3504
Site inspections
2

Schedule

Binghatti Skyhall was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.0 points a month. Kept at that rate, the site would reach 100% around March 2029.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 April 2026

31%+31 pts

  • Binghatti Skyhall construction site, inspection photo 1, 30 April 2026
  • Binghatti Skyhall construction site, inspection photo 2, 30 April 2026
  • Binghatti Skyhall construction site, inspection photo 3, 30 April 2026
  • Binghatti Skyhall construction site, inspection photo 4, 30 April 2026

16 January 2025

0%

  • Binghatti Skyhall construction site, inspection photo 1, 16 January 2025
  • Binghatti Skyhall construction site, inspection photo 2, 16 January 2025
  • Binghatti Skyhall construction site, inspection photo 3, 16 January 2025

All 12 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Skyhall?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Skyhall handover date?
The registered completion date was August 2026, and the register still lists Binghatti Skyhall as under construction. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Skyhall?
Binghatti Skyhall was 31% built at the site inspection on 30 April 2026. The site has been inspected 2 times since January 2025. The Land Department took 12 site photos at its inspections.
Is Binghatti Skyhall delayed?
Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
Who is building Binghatti Skyhall?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Skyhall?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.