Binghatti Skyhall construction progress
Binghatti Skyhall in Business Bay was registered to complete in August 2026 and is still under construction. At the last site inspection, in April 2026, it was 31% built. The developer is Binghatti Developers.
31%
Built, at the site inspection of 30 April 2026
3 months past its registered completion date
- Registered completion date
- August 2026
- Finish at recent pace
- March 2029
- Construction started
- February 2025
- First registered
- March 2025
- Developer
- Binghatti Developers
- Community
- Business Bay
- Units
- 728
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بن غاطي سكاي هول
- Project number
- 3504
- Site inspections
- 2
Schedule
Binghatti Skyhall was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.0 points a month. Kept at that rate, the site would reach 100% around March 2029.
Site inspections
30 April 2026
31%+31 pts
16 January 2025
0%
Context
Business Bay has 43 projects under construction, 37% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Skyhall?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Skyhall handover date?
- The registered completion date was August 2026, and the register still lists Binghatti Skyhall as under construction. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Skyhall?
- Binghatti Skyhall was 31% built at the site inspection on 30 April 2026. The site has been inspected 2 times since January 2025. The Land Department took 12 site photos at its inspections.
- Is Binghatti Skyhall delayed?
- Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
- Who is building Binghatti Skyhall?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Skyhall?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.