Bayz 102 By Danube construction progress

The registered completion date for Bayz 102 By Danube in Business Bay is December 2029. At the last site inspection, in October 2026, it was 6.5% built. The developer is Danube Properties Development.

6.5%

Built, at the site inspection of 6 October 2026

Running behind its date

Registered completion date
December 2029
Finish at recent pace
February 2066
Construction started
December 2024
First registered
November 2024
Community
Business Bay
Units
1,088
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بايز 102 من دانوب
Project number
3125
Site inspections
7

Schedule

Between December 2025 and October 2026 the site added about 0.2 points a month. At that rate it would finish around February 2066, more than three months after its registered date of December 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 October 2026

6.5%+0.7 pts

  • Bayz 102 By Danube construction site, inspection photo 1, 6 October 2026
  • Bayz 102 By Danube construction site, inspection photo 2, 6 October 2026
  • Bayz 102 By Danube construction site, inspection photo 3, 6 October 2026
  • Bayz 102 By Danube construction site, inspection photo 4, 6 October 2026

30 June 2026

5.9%+0.7 pts

  • Bayz 102 By Danube construction site, inspection photo 1, 30 June 2026
  • Bayz 102 By Danube construction site, inspection photo 2, 30 June 2026
  • Bayz 102 By Danube construction site, inspection photo 3, 30 June 2026
  • Bayz 102 By Danube construction site, inspection photo 4, 30 June 2026

23 March 2026

5.2%+0.5 pts

  • Bayz 102 By Danube construction site, inspection photo 1, 23 March 2026
  • Bayz 102 By Danube construction site, inspection photo 2, 23 March 2026
  • Bayz 102 By Danube construction site, inspection photo 3, 23 March 2026

24 December 2025

4.7%+3.5 pts

  • Bayz 102 By Danube construction site, inspection photo 1, 24 December 2025
  • Bayz 102 By Danube construction site, inspection photo 2, 24 December 2025
  • Bayz 102 By Danube construction site, inspection photo 3, 24 December 2025

2 October 2025

1.1%+0.8 pts

  • Bayz 102 By Danube construction site, inspection photo 1, 2 October 2025
  • Bayz 102 By Danube construction site, inspection photo 2, 2 October 2025
  • Bayz 102 By Danube construction site, inspection photo 3, 2 October 2025
  • Bayz 102 By Danube construction site, inspection photo 4, 2 October 2025

23 June 2025

0.3%+0.3 pts

  • Bayz 102 By Danube construction site, inspection photo 1, 23 June 2025
  • Bayz 102 By Danube construction site, inspection photo 2, 23 June 2025
  • Bayz 102 By Danube construction site, inspection photo 3, 23 June 2025
  • Bayz 102 By Danube construction site, inspection photo 4, 23 June 2025

3 September 2024

0%

  • Bayz 102 By Danube construction site, inspection photo 1, 3 September 2024
  • Bayz 102 By Danube construction site, inspection photo 2, 3 September 2024

All 27 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Bayz 102 By Danube?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Bayz 102 By Danube handover date?
The registered completion date is December 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2066. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Bayz 102 By Danube?
Bayz 102 By Danube was 6.5% built at the site inspection on 6 October 2026. The site has been inspected 7 times since September 2024. The Land Department took 27 site photos at its inspections.
Is Bayz 102 By Danube delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Bayz 102 By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Bayz 102 By Danube?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.