Canal Heights 2 construction progress
Canal Heights 2 in Business Bay is 36% built at the Land Department inspection of August 2026. Developer Resta Real Estate Development. Completion registered for March 2027.
36%
Built, at the Land Department site inspection of 14 August 2026
Running behind its date
- Completion date (Land Department)
- March 2027
- Finish at recent pace
- January 2030
- Construction started
- June 2023
- Registered with the Land Department
- March 2023
- Developer
- Resta Real Estate Development
- Community
- Business Bay
- Units
- 505
- Escrow bank
- Emirates NBD
- Name in Arabic
- قنال هايتس 2
- Land Department project number
- 2615
- Land Department site inspections
- 9
Schedule
Between August 2025 and August 2026 the site added about 1.6 points a month. At that rate it would finish around January 2030, more than three months after the March 2027 date registered with the Land Department.
Site inspections
14 August 2026
36%+8.3 pts
22 April 2026
28%+5.5 pts
27 December 2025
23%+4.5 pts
20 August 2025
18%+4.7 pts
11 April 2025
13%+4.9 pts
20 November 2024
8.5%+5.3 pts
5 July 2024
3.2%+3.1 pts
21 September 2023
0.1%+0.1 pts
16 March 2023
0%
Context
Business Bay has 43 projects under construction, 35% built on average.
Own a unit in Canal Heights 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Canal Heights 2 be completed?
- The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around January 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Canal Heights 2 is built?
- 36%, measured at the Land Department site inspection on 14 August 2026. The Land Department engineers have inspected the site 9 times since March 2023.
- Is Canal Heights 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Canal Heights 2?
- The registered developer is Resta Real Estate Development.
- Which bank holds the escrow account for Canal Heights 2?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)







.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)