Canal Heights 2 construction progress
The registered completion date for Canal Heights 2 in Business Bay is March 2027. At the last site inspection, in August 2026, it was 36% built. The developer is Resta Real Estate Development.
36%
Built, at the site inspection of 14 August 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- January 2030
- Construction started
- June 2023
- First registered
- March 2023
- Developer
- Resta Real Estate Development
- Community
- Business Bay
- Units
- 505
- Escrow bank
- Emirates NBD
- Name in Arabic
- قنال هايتس 2
- Project number
- 2615
- Site inspections
- 9
Schedule
Between August 2025 and August 2026 the site added about 1.6 points a month. At that rate it would finish around January 2030, more than three months after its registered date of March 2027.
Site inspections
14 August 2026
36%+8.3 pts
22 April 2026
28%+5.5 pts
27 December 2025
23%+4.5 pts
20 August 2025
18%+4.7 pts
11 April 2025
13%+4.9 pts
20 November 2024
8.5%+5.3 pts
5 July 2024
3.2%+3.1 pts
21 September 2023
0.1%+0.1 pts
16 March 2023
0%
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in Canal Heights 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Canal Heights 2 handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Canal Heights 2?
- Canal Heights 2 was 36% built at the site inspection on 14 August 2026. The site has been inspected 9 times since March 2023. The Land Department took 49 site photos at its inspections.
- Is Canal Heights 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Canal Heights 2?
- The registered developer is Resta Real Estate Development.
- Which bank holds the escrow account for Canal Heights 2?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpg&w=3840&q=75)






.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)







.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)