Eywa Dubai construction progress

Eywa Dubai in Business Bay was registered to complete in April 2026 and is still under construction. At the last site inspection, in October 2026, it was 66% built. The developer is Rvl Real Estate.

66%

Built, at the site inspection of 22 October 2026

8 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
November 2027
Construction started
October 2023
First registered
June 2023
Developer
Rvl Real Estate
Community
Business Bay
Units
53
Escrow bank
United Bank Limited
Name in Arabic
إيفا دبى
Project number
2621
Site inspections
15

Schedule

Eywa Dubai was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around November 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

66%+1.4 pts

  • Eywa Dubai construction site, inspection photo 1, 22 October 2026
  • Eywa Dubai construction site, inspection photo 2, 22 October 2026
  • Eywa Dubai construction site, inspection photo 3, 22 October 2026
  • Eywa Dubai construction site, inspection photo 4, 22 October 2026

21 September 2026

64%+2.3 pts

  • Eywa Dubai construction site, inspection photo 1, 21 September 2026
  • Eywa Dubai construction site, inspection photo 2, 21 September 2026
  • Eywa Dubai construction site, inspection photo 3, 21 September 2026
  • Eywa Dubai construction site, inspection photo 4, 21 September 2026

31 August 2026

62%+1.9 pts

  • Eywa Dubai construction site, inspection photo 1, 31 August 2026
  • Eywa Dubai construction site, inspection photo 2, 31 August 2026
  • Eywa Dubai construction site, inspection photo 3, 31 August 2026
  • Eywa Dubai construction site, inspection photo 4, 31 August 2026

6 July 2026

60%+2.6 pts

  • Eywa Dubai construction site, inspection photo 1, 6 July 2026
  • Eywa Dubai construction site, inspection photo 2, 6 July 2026
  • Eywa Dubai construction site, inspection photo 3, 6 July 2026
  • Eywa Dubai construction site, inspection photo 4, 6 July 2026

11 June 2026

57%+1.7 pts

  • Eywa Dubai construction site, inspection photo 1, 11 June 2026
  • Eywa Dubai construction site, inspection photo 2, 11 June 2026
  • Eywa Dubai construction site, inspection photo 3, 11 June 2026
  • Eywa Dubai construction site, inspection photo 4, 11 June 2026

19 May 2026

56%+4.0 pts

  • Eywa Dubai construction site, inspection photo 1, 19 May 2026
  • Eywa Dubai construction site, inspection photo 2, 19 May 2026
  • Eywa Dubai construction site, inspection photo 3, 19 May 2026
  • Eywa Dubai construction site, inspection photo 4, 19 May 2026

29 April 2026

52%+4.2 pts

  • Eywa Dubai construction site, inspection photo 1, 29 April 2026
  • Eywa Dubai construction site, inspection photo 2, 29 April 2026
  • Eywa Dubai construction site, inspection photo 3, 29 April 2026
  • Eywa Dubai construction site, inspection photo 4, 29 April 2026

25 March 2026

48%+7.5 pts

  • Eywa Dubai construction site, inspection photo 1, 25 March 2026
  • Eywa Dubai construction site, inspection photo 2, 25 March 2026
  • Eywa Dubai construction site, inspection photo 3, 25 March 2026
  • Eywa Dubai construction site, inspection photo 4, 25 March 2026

26 January 2026

40%+6.3 pts

  • Eywa Dubai construction site, inspection photo 1, 26 January 2026
  • Eywa Dubai construction site, inspection photo 2, 26 January 2026
  • Eywa Dubai construction site, inspection photo 3, 26 January 2026
  • Eywa Dubai construction site, inspection photo 4, 26 January 2026

28 October 2025

34%+6.9 pts

  • Eywa Dubai construction site, inspection photo 1, 28 October 2025
  • Eywa Dubai construction site, inspection photo 2, 28 October 2025
  • Eywa Dubai construction site, inspection photo 3, 28 October 2025
  • Eywa Dubai construction site, inspection photo 4, 28 October 2025

All 125 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Eywa Dubai?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Eywa Dubai handover date?
The registered completion date was April 2026, and the register still lists Eywa Dubai as under construction. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Eywa Dubai?
Eywa Dubai was 66% built at the site inspection on 22 October 2026. The site has been inspected 15 times since March 2023. The Land Department took 125 site photos at its inspections.
Is Eywa Dubai delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Eywa Dubai?
The registered developer is Rvl Real Estate.
Which bank holds the escrow account for Eywa Dubai?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.