Eywa Dubai construction progress
Eywa Dubai in Business Bay is 64% built at the Land Department inspection of September 2026. Developer Rvl Real Estate. Completion registered for April 2026.
64%
Built, at the Land Department site inspection of 21 September 2026
6 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- October 2027
- Construction started
- October 2023
- Registered with the Land Department
- June 2023
- Developer
- Rvl Real Estate
- Community
- Business Bay
- Units
- 53
- Escrow bank
- United Bank Limited
- Name in Arabic
- إيفا دبى
- Land Department project number
- 2621
- Land Department site inspections
- 14
Schedule
Eywa Dubai was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.8 points a month. Kept at that rate, the site would reach 100% around October 2027.
Site inspections
21 September 2026
64%+2.3 pts
31 August 2026
62%+1.9 pts
6 July 2026
60%+2.6 pts
11 June 2026
57%+1.7 pts
19 May 2026
56%+4.0 pts
29 April 2026
52%+4.2 pts
25 March 2026
48%+7.5 pts
26 January 2026
40%+6.3 pts
28 October 2025
34%+6.9 pts
25 July 2025
27%+6.5 pts
Context
Business Bay has 43 projects under construction, 35% built on average.
Own a unit in Eywa Dubai?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Eywa Dubai be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Eywa Dubai is built?
- 64%, measured at the Land Department site inspection on 21 September 2026. The Land Department engineers have inspected the site 14 times since March 2023.
- Is Eywa Dubai delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Eywa Dubai?
- The registered developer is Rvl Real Estate.
- Which bank holds the escrow account for Eywa Dubai?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
















.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)







.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)