Eywa Dubai construction progress

Eywa Dubai in Business Bay is 64% built at the Land Department inspection of September 2026. Developer Rvl Real Estate. Completion registered for April 2026.

64%

Built, at the Land Department site inspection of 21 September 2026

6 months past its registered completion date

Completion date (Land Department)
April 2026
Finish at recent pace
October 2027
Construction started
October 2023
Registered with the Land Department
June 2023
Developer
Rvl Real Estate
Community
Business Bay
Units
53
Escrow bank
United Bank Limited
Name in Arabic
إيفا دبى
Land Department project number
2621
Land Department site inspections
14

Schedule

Eywa Dubai was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.8 points a month. Kept at that rate, the site would reach 100% around October 2027.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

21 September 2026

64%+2.3 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 21 September 2026
  • Eywa Dubai construction site, Land Department inspection photo 2, 21 September 2026
  • Eywa Dubai construction site, Land Department inspection photo 3, 21 September 2026
  • Eywa Dubai construction site, Land Department inspection photo 4, 21 September 2026

31 August 2026

62%+1.9 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 31 August 2026
  • Eywa Dubai construction site, Land Department inspection photo 2, 31 August 2026
  • Eywa Dubai construction site, Land Department inspection photo 3, 31 August 2026
  • Eywa Dubai construction site, Land Department inspection photo 4, 31 August 2026

6 July 2026

60%+2.6 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 6 July 2026
  • Eywa Dubai construction site, Land Department inspection photo 2, 6 July 2026
  • Eywa Dubai construction site, Land Department inspection photo 3, 6 July 2026
  • Eywa Dubai construction site, Land Department inspection photo 4, 6 July 2026

11 June 2026

57%+1.7 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 11 June 2026
  • Eywa Dubai construction site, Land Department inspection photo 2, 11 June 2026
  • Eywa Dubai construction site, Land Department inspection photo 3, 11 June 2026
  • Eywa Dubai construction site, Land Department inspection photo 4, 11 June 2026

19 May 2026

56%+4.0 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 19 May 2026
  • Eywa Dubai construction site, Land Department inspection photo 2, 19 May 2026
  • Eywa Dubai construction site, Land Department inspection photo 3, 19 May 2026
  • Eywa Dubai construction site, Land Department inspection photo 4, 19 May 2026

29 April 2026

52%+4.2 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 29 April 2026
  • Eywa Dubai construction site, Land Department inspection photo 2, 29 April 2026
  • Eywa Dubai construction site, Land Department inspection photo 3, 29 April 2026
  • Eywa Dubai construction site, Land Department inspection photo 4, 29 April 2026

25 March 2026

48%+7.5 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 25 March 2026
  • Eywa Dubai construction site, Land Department inspection photo 2, 25 March 2026
  • Eywa Dubai construction site, Land Department inspection photo 3, 25 March 2026
  • Eywa Dubai construction site, Land Department inspection photo 4, 25 March 2026

26 January 2026

40%+6.3 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 26 January 2026
  • Eywa Dubai construction site, Land Department inspection photo 2, 26 January 2026
  • Eywa Dubai construction site, Land Department inspection photo 3, 26 January 2026
  • Eywa Dubai construction site, Land Department inspection photo 4, 26 January 2026

28 October 2025

34%+6.9 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 28 October 2025
  • Eywa Dubai construction site, Land Department inspection photo 2, 28 October 2025
  • Eywa Dubai construction site, Land Department inspection photo 3, 28 October 2025
  • Eywa Dubai construction site, Land Department inspection photo 4, 28 October 2025

25 July 2025

27%+6.5 pts

  • Eywa Dubai construction site, Land Department inspection photo 1, 25 July 2025
  • Eywa Dubai construction site, Land Department inspection photo 2, 25 July 2025
  • Eywa Dubai construction site, Land Department inspection photo 3, 25 July 2025
  • Eywa Dubai construction site, Land Department inspection photo 4, 25 July 2025

All 109 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Own a unit in Eywa Dubai?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Eywa Dubai be completed?
The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Eywa Dubai is built?
64%, measured at the Land Department site inspection on 21 September 2026. The Land Department engineers have inspected the site 14 times since March 2023.
Is Eywa Dubai delayed?
Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
Who is building Eywa Dubai?
The registered developer is Rvl Real Estate.
Which bank holds the escrow account for Eywa Dubai?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.