Eywa Dubai construction progress
Eywa Dubai in Business Bay was registered to complete in April 2026 and is still under construction. At the last site inspection, in October 2026, it was 66% built. The developer is Rvl Real Estate.
66%
Built, at the site inspection of 22 October 2026
8 months past its registered completion date
- Registered completion date
- April 2026
- Finish at recent pace
- November 2027
- Construction started
- October 2023
- First registered
- June 2023
- Developer
- Rvl Real Estate
- Community
- Business Bay
- Units
- 53
- Escrow bank
- United Bank Limited
- Name in Arabic
- إيفا دبى
- Project number
- 2621
- Site inspections
- 15
Schedule
Eywa Dubai was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around November 2027.
Site inspections
22 October 2026
66%+1.4 pts
21 September 2026
64%+2.3 pts
31 August 2026
62%+1.9 pts
6 July 2026
60%+2.6 pts
11 June 2026
57%+1.7 pts
19 May 2026
56%+4.0 pts
29 April 2026
52%+4.2 pts
25 March 2026
48%+7.5 pts
26 January 2026
40%+6.3 pts
28 October 2025
34%+6.9 pts
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in Eywa Dubai?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Eywa Dubai handover date?
- The registered completion date was April 2026, and the register still lists Eywa Dubai as under construction. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Eywa Dubai?
- Eywa Dubai was 66% built at the site inspection on 22 October 2026. The site has been inspected 15 times since March 2023. The Land Department took 125 site photos at its inspections.
- Is Eywa Dubai delayed?
- Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
- Who is building Eywa Dubai?
- The registered developer is Rvl Real Estate.
- Which bank holds the escrow account for Eywa Dubai?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






















.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)