Rove Home Marasi Drive construction progress

Rove Home Marasi Drive in Business Bay is 10% built at the Land Department inspection of July 2026. Developer Irth Signature Development. Completion registered for August 2027.

10%

Built, at the Land Department site inspection of 6 July 2026

Running behind its date

Completion date (Land Department)
August 2027
Finish at recent pace
March 2042
Construction started
July 2024
Registered with the Land Department
April 2024
Developer
Irth Signature Development
Community
Business Bay
Units
811
Escrow bank
Commercial Bank of Dubai
Name in Arabic
روف منازل مراسي درايف
Land Department project number
2966
Land Department site inspections
8

Schedule

Between July 2025 and July 2026 the site added about 0.5 points a month. At that rate it would finish around March 2042, more than three months after the August 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 July 2026

10%+0.3 pts

  • Rove Home Marasi Drive construction site, Land Department inspection photo 1, 6 July 2026
  • Rove Home Marasi Drive construction site, Land Department inspection photo 2, 6 July 2026
  • Rove Home Marasi Drive construction site, Land Department inspection photo 3, 6 July 2026
  • Rove Home Marasi Drive construction site, Land Department inspection photo 4, 6 July 2026

23 March 2026

9.7%+0.8 pts

  • Rove Home Marasi Drive construction site, Land Department inspection photo 1, 23 March 2026
  • Rove Home Marasi Drive construction site, Land Department inspection photo 2, 23 March 2026
  • Rove Home Marasi Drive construction site, Land Department inspection photo 3, 23 March 2026
  • Rove Home Marasi Drive construction site, Land Department inspection photo 4, 23 March 2026

3 December 2025

8.9%+4.2 pts

  • Rove Home Marasi Drive construction site, Land Department inspection photo 1, 3 December 2025
  • Rove Home Marasi Drive construction site, Land Department inspection photo 2, 3 December 2025
  • Rove Home Marasi Drive construction site, Land Department inspection photo 3, 3 December 2025

30 July 2025

4.7%+0.3 pts

  • Rove Home Marasi Drive construction site, Land Department inspection photo 1, 30 July 2025
  • Rove Home Marasi Drive construction site, Land Department inspection photo 2, 30 July 2025
  • Rove Home Marasi Drive construction site, Land Department inspection photo 3, 30 July 2025

4 April 2025

4.4%+0.6 pts

  • Rove Home Marasi Drive construction site, Land Department inspection photo 1, 4 April 2025
  • Rove Home Marasi Drive construction site, Land Department inspection photo 2, 4 April 2025
  • Rove Home Marasi Drive construction site, Land Department inspection photo 3, 4 April 2025
  • Rove Home Marasi Drive construction site, Land Department inspection photo 4, 4 April 2025

6 January 2025

3.8%+0.2 pts

  • Rove Home Marasi Drive construction site, Land Department inspection photo 1, 6 January 2025
  • Rove Home Marasi Drive construction site, Land Department inspection photo 2, 6 January 2025

16 October 2024

3.6%+3.6 pts

  • Rove Home Marasi Drive construction site, Land Department inspection photo 1, 16 October 2024
  • Rove Home Marasi Drive construction site, Land Department inspection photo 2, 16 October 2024

14 February 2024

0%

  • Rove Home Marasi Drive construction site, Land Department inspection photo 1, 14 February 2024
  • Rove Home Marasi Drive construction site, Land Department inspection photo 2, 14 February 2024

All 27 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Own a unit in Rove Home Marasi Drive?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Rove Home Marasi Drive be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around March 2042. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Rove Home Marasi Drive is built?
10%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 8 times since February 2024.
Is Rove Home Marasi Drive delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Rove Home Marasi Drive?
The registered developer is Irth Signature Development.
Which bank holds the escrow account for Rove Home Marasi Drive?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.