Rove Home Marasi Drive construction progress

The registered completion date for Rove Home Marasi Drive in Business Bay is August 2027. At the last site inspection, in July 2026, it was 10% built. The developer is Irth Signature Development.

10%

Built, at the site inspection of 6 July 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
March 2042
Construction started
July 2024
First registered
April 2024
Developer
Irth Signature Development
Community
Business Bay
Units
811
Escrow bank
Commercial Bank of Dubai
Name in Arabic
روف منازل مراسي درايف
Project number
2966
Site inspections
8

Schedule

Between July 2025 and July 2026 the site added about 0.5 points a month. At that rate it would finish around March 2042, more than three months after its registered date of August 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 July 2026

10%+0.3 pts

  • Rove Home Marasi Drive construction site, inspection photo 1, 6 July 2026
  • Rove Home Marasi Drive construction site, inspection photo 2, 6 July 2026
  • Rove Home Marasi Drive construction site, inspection photo 3, 6 July 2026
  • Rove Home Marasi Drive construction site, inspection photo 4, 6 July 2026

23 March 2026

9.7%+0.8 pts

  • Rove Home Marasi Drive construction site, inspection photo 1, 23 March 2026
  • Rove Home Marasi Drive construction site, inspection photo 2, 23 March 2026
  • Rove Home Marasi Drive construction site, inspection photo 3, 23 March 2026
  • Rove Home Marasi Drive construction site, inspection photo 4, 23 March 2026

3 December 2025

8.9%+4.2 pts

  • Rove Home Marasi Drive construction site, inspection photo 1, 3 December 2025
  • Rove Home Marasi Drive construction site, inspection photo 2, 3 December 2025
  • Rove Home Marasi Drive construction site, inspection photo 3, 3 December 2025

30 July 2025

4.7%+0.3 pts

  • Rove Home Marasi Drive construction site, inspection photo 1, 30 July 2025
  • Rove Home Marasi Drive construction site, inspection photo 2, 30 July 2025
  • Rove Home Marasi Drive construction site, inspection photo 3, 30 July 2025

4 April 2025

4.4%+0.6 pts

  • Rove Home Marasi Drive construction site, inspection photo 1, 4 April 2025
  • Rove Home Marasi Drive construction site, inspection photo 2, 4 April 2025
  • Rove Home Marasi Drive construction site, inspection photo 3, 4 April 2025
  • Rove Home Marasi Drive construction site, inspection photo 4, 4 April 2025

6 January 2025

3.8%+0.2 pts

  • Rove Home Marasi Drive construction site, inspection photo 1, 6 January 2025
  • Rove Home Marasi Drive construction site, inspection photo 2, 6 January 2025

16 October 2024

3.6%+3.6 pts

  • Rove Home Marasi Drive construction site, inspection photo 1, 16 October 2024
  • Rove Home Marasi Drive construction site, inspection photo 2, 16 October 2024

14 February 2024

0%

  • Rove Home Marasi Drive construction site, inspection photo 1, 14 February 2024
  • Rove Home Marasi Drive construction site, inspection photo 2, 14 February 2024

All 27 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Rove Home Marasi Drive?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Rove Home Marasi Drive handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2042. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Rove Home Marasi Drive?
Rove Home Marasi Drive was 10% built at the site inspection on 6 July 2026. The site has been inspected 8 times since February 2024. The Land Department took 27 site photos at its inspections.
Is Rove Home Marasi Drive delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Rove Home Marasi Drive?
The registered developer is Irth Signature Development.
Which bank holds the escrow account for Rove Home Marasi Drive?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.