Burj Binghatti Jacob & Co. Residences construction progress
Burj Binghatti Jacob & Co. Residences in Business Bay is 52% built at the Land Department inspection of August 2026. Developer Binghatti Developers. Completion registered for June 2026.
52%
Built, at the Land Department site inspection of 31 August 2026
3 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- July 2028
- Construction started
- October 2022
- Registered with the Land Department
- November 2022
- Developer
- Binghatti Developers
- Community
- Business Bay
- Units
- 325
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- برج بن غاطي جيكوب اند كو. ريزيدنسز
- Land Department project number
- 2480
- Land Department site inspections
- 6
Schedule
Burj Binghatti Jacob & Co. Residences was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around July 2028.
Site inspections
31 August 2026
52%+17 pts
22 December 2025
35%+12 pts
28 July 2025
23%+10 pts
30 January 2025
13%+10 pts
31 August 2023
2.7%+2.6 pts
12 October 2022
0.1%
Context
Business Bay has 43 projects under construction, 35% built on average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Burj Binghatti Jacob & Co. Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Burj Binghatti Jacob & Co. Residences be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around July 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Burj Binghatti Jacob & Co. Residences is built?
- 52%, measured at the Land Department site inspection on 31 August 2026. The Land Department engineers have inspected the site 6 times since October 2022.
- Is Burj Binghatti Jacob & Co. Residences delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Burj Binghatti Jacob & Co. Residences?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Burj Binghatti Jacob & Co. Residences?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- One By BinghattiAlso by Binghatti Developers. 50%.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)