Burj Binghatti Jacob & Co. Residences construction progress
Burj Binghatti Jacob & Co. Residences in Business Bay was registered to complete in June 2026 and is still under construction. At the last site inspection, in August 2026, it was 52% built. The developer is Binghatti Developers.
52%
Built, at the site inspection of 31 August 2026
5 months past its registered completion date
- Registered completion date
- June 2026
- Finish at recent pace
- July 2028
- Construction started
- October 2022
- First registered
- November 2022
- Developer
- Binghatti Developers
- Community
- Business Bay
- Units
- 325
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- برج بن غاطي جيكوب اند كو. ريزيدنسز
- Project number
- 2480
- Site inspections
- 6
Schedule
Burj Binghatti Jacob & Co. Residences was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around July 2028.
Site inspections
31 August 2026
52%+17 pts
22 December 2025
35%+12 pts
28 July 2025
23%+10 pts
30 January 2025
13%+10 pts
31 August 2023
2.7%+2.6 pts
12 October 2022
0.1%
Context
Business Bay has 43 projects under construction, 37% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Burj Binghatti Jacob & Co. Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Burj Binghatti Jacob & Co. Residences handover date?
- The registered completion date was June 2026, and the register still lists Burj Binghatti Jacob & Co. Residences as under construction. At the pace of its recent inspections the site would reach 100% around July 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Burj Binghatti Jacob & Co. Residences?
- Burj Binghatti Jacob & Co. Residences was 52% built at the site inspection on 31 August 2026. The site has been inspected 6 times since October 2022. The Land Department took 41 site photos at its inspections.
- Is Burj Binghatti Jacob & Co. Residences delayed?
- Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
- Who is building Burj Binghatti Jacob & Co. Residences?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Burj Binghatti Jacob & Co. Residences?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- One By BinghattiAlso by Binghatti Developers. 50%, Due May 2026, passed.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)