Burj Binghatti Jacob & Co. Residences construction progress

Burj Binghatti Jacob & Co. Residences in Business Bay was registered to complete in June 2026 and is still under construction. At the last site inspection, in August 2026, it was 52% built. The developer is Binghatti Developers.

52%

Built, at the site inspection of 31 August 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
July 2028
Construction started
October 2022
First registered
November 2022
Community
Business Bay
Units
325
Escrow bank
Sharjah Islamic Bank
Name in Arabic
برج بن غاطي جيكوب اند كو. ريزيدنسز
Project number
2480
Site inspections
6

Schedule

Burj Binghatti Jacob & Co. Residences was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around July 2028.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 August 2026

52%+17 pts

  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 1, 31 August 2026
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 2, 31 August 2026
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 3, 31 August 2026
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 4, 31 August 2026

22 December 2025

35%+12 pts

  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 1, 22 December 2025
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 2, 22 December 2025
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 3, 22 December 2025
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 4, 22 December 2025

28 July 2025

23%+10 pts

  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 1, 28 July 2025
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 2, 28 July 2025
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 3, 28 July 2025
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 4, 28 July 2025

30 January 2025

13%+10 pts

  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 1, 30 January 2025
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 2, 30 January 2025
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 3, 30 January 2025
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 4, 30 January 2025

31 August 2023

2.7%+2.6 pts

  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 1, 31 August 2023
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 2, 31 August 2023
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 3, 31 August 2023
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 4, 31 August 2023

12 October 2022

0.1%

  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 1, 12 October 2022
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 2, 12 October 2022
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 3, 12 October 2022
  • Burj Binghatti Jacob & Co. Residences construction site, inspection photo 4, 12 October 2022

All 41 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Burj Binghatti Jacob & Co. Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Burj Binghatti Jacob & Co. Residences handover date?
The registered completion date was June 2026, and the register still lists Burj Binghatti Jacob & Co. Residences as under construction. At the pace of its recent inspections the site would reach 100% around July 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Burj Binghatti Jacob & Co. Residences?
Burj Binghatti Jacob & Co. Residences was 52% built at the site inspection on 31 August 2026. The site has been inspected 6 times since October 2022. The Land Department took 41 site photos at its inspections.
Is Burj Binghatti Jacob & Co. Residences delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Burj Binghatti Jacob & Co. Residences?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Burj Binghatti Jacob & Co. Residences?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.