Canal Crown construction progress
The registered completion date for Canal Crown in Business Bay is February 2027. At the last site inspection, in July 2026, it was 42% built. The developer is Galaxy Sky Real Estate Development.
42%
Built, at the site inspection of 15 July 2026
Running behind its date
- Registered completion date
- February 2027
- Finish at recent pace
- November 2028
- Construction started
- August 2023
- First registered
- May 2023
- Developer
- Galaxy Sky Real Estate Development
- Community
- Business Bay
- Units
- 327
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- قنال كراون
- Project number
- 2625
- Site inspections
- 8
Schedule
Between October 2025 and July 2026 the site added about 2.1 points a month. At that rate it would finish around November 2028, more than three months after its registered date of February 2027.
Site inspections
15 July 2026
42%+9.4 pts
12 March 2026
33%+9.9 pts
7 October 2025
23%+4.7 pts
30 May 2025
18%+6.4 pts
22 January 2025
12%+3.3 pts
5 July 2024
8.5%+8.2 pts
1 November 2023
0.2%+0.2 pts
13 April 2023
0%
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in Canal Crown?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Canal Crown handover date?
- The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Canal Crown?
- Canal Crown was 42% built at the site inspection on 15 July 2026. The site has been inspected 8 times since April 2023. The Land Department took 47 site photos at its inspections.
- Is Canal Crown delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building Canal Crown?
- The registered developer is Galaxy Sky Real Estate Development.
- Which bank holds the escrow account for Canal Crown?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)






.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)