Skip to content

Canal Crown construction progress

The registered completion date for Canal Crown in Business Bay is February 2027. At the last site inspection, in July 2026, it was 42% built. The developer is Galaxy Sky Real Estate Development.

42%

Built, at the site inspection of 15 July 2026

Running behind its date

Registered completion date
February 2027
Finish at recent pace
November 2028
Construction started
August 2023
First registered
May 2023
Developer
Galaxy Sky Real Estate Development
Community
Business Bay
Units
327
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
قنال كراون
Project number
2625
Site inspections
8

Schedule

Between October 2025 and July 2026 the site added about 2.1 points a month. At that rate it would finish around November 2028, more than three months after its registered date of February 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 July 2026

42%+9.4 pts

  • Canal Crown construction site, inspection photo 1, 15 July 2026
  • Canal Crown construction site, inspection photo 2, 15 July 2026
  • Canal Crown construction site, inspection photo 3, 15 July 2026
  • Canal Crown construction site, inspection photo 4, 15 July 2026

12 March 2026

33%+9.9 pts

  • Canal Crown construction site, inspection photo 1, 12 March 2026
  • Canal Crown construction site, inspection photo 2, 12 March 2026
  • Canal Crown construction site, inspection photo 3, 12 March 2026
  • Canal Crown construction site, inspection photo 4, 12 March 2026

7 October 2025

23%+4.7 pts

  • Canal Crown construction site, inspection photo 1, 7 October 2025
  • Canal Crown construction site, inspection photo 2, 7 October 2025
  • Canal Crown construction site, inspection photo 3, 7 October 2025
  • Canal Crown construction site, inspection photo 4, 7 October 2025

30 May 2025

18%+6.4 pts

  • Canal Crown construction site, inspection photo 1, 30 May 2025
  • Canal Crown construction site, inspection photo 2, 30 May 2025
  • Canal Crown construction site, inspection photo 3, 30 May 2025
  • Canal Crown construction site, inspection photo 4, 30 May 2025

22 January 2025

12%+3.3 pts

  • Canal Crown construction site, inspection photo 1, 22 January 2025
  • Canal Crown construction site, inspection photo 2, 22 January 2025
  • Canal Crown construction site, inspection photo 3, 22 January 2025
  • Canal Crown construction site, inspection photo 4, 22 January 2025

5 July 2024

8.5%+8.2 pts

  • Canal Crown construction site, inspection photo 1, 5 July 2024
  • Canal Crown construction site, inspection photo 2, 5 July 2024

1 November 2023

0.2%+0.2 pts

  • Canal Crown construction site, inspection photo 1, 1 November 2023
  • Canal Crown construction site, inspection photo 2, 1 November 2023
  • Canal Crown construction site, inspection photo 3, 1 November 2023
  • Canal Crown construction site, inspection photo 4, 1 November 2023

13 April 2023

0%

  • Canal Crown construction site, inspection photo 1, 13 April 2023
  • Canal Crown construction site, inspection photo 2, 13 April 2023

All 47 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Canal Crown?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Canal Crown handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Canal Crown?
Canal Crown was 42% built at the site inspection on 15 July 2026. The site has been inspected 8 times since April 2023. The Land Department took 47 site photos at its inspections.
Is Canal Crown delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Canal Crown?
The registered developer is Galaxy Sky Real Estate Development.
Which bank holds the escrow account for Canal Crown?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.