The Quayside construction progress

The Quayside in Business Bay is 55% built at the Land Department inspection of June 2026. Developer Quayside Developers. Completion registered for March 2026.

55%

Built, at the Land Department site inspection of 9 June 2026

6 months past its registered completion date

Completion date (Land Department)
March 2026
Finish at recent pace
June 2027
Construction started
September 2023
Registered with the Land Department
November 2023
Developer
Quayside Developers
Community
Business Bay
Units
119
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا كيسايد
Land Department project number
2815
Land Department site inspections
6

Schedule

The Quayside was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around June 2027.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 June 2026

55%+18 pts

  • The Quayside construction site, Land Department inspection photo 1, 9 June 2026
  • The Quayside construction site, Land Department inspection photo 2, 9 June 2026
  • The Quayside construction site, Land Department inspection photo 3, 9 June 2026
  • The Quayside construction site, Land Department inspection photo 4, 9 June 2026

17 February 2026

36%+8.5 pts

  • The Quayside construction site, Land Department inspection photo 1, 17 February 2026
  • The Quayside construction site, Land Department inspection photo 2, 17 February 2026
  • The Quayside construction site, Land Department inspection photo 3, 17 February 2026
  • The Quayside construction site, Land Department inspection photo 4, 17 February 2026

30 October 2025

28%+11 pts

  • The Quayside construction site, Land Department inspection photo 1, 30 October 2025
  • The Quayside construction site, Land Department inspection photo 2, 30 October 2025
  • The Quayside construction site, Land Department inspection photo 3, 30 October 2025
  • The Quayside construction site, Land Department inspection photo 4, 30 October 2025

3 June 2025

17%+15 pts

  • The Quayside construction site, Land Department inspection photo 1, 3 June 2025
  • The Quayside construction site, Land Department inspection photo 2, 3 June 2025
  • The Quayside construction site, Land Department inspection photo 3, 3 June 2025
  • The Quayside construction site, Land Department inspection photo 4, 3 June 2025

14 May 2024

1.5%+1.5 pts

  • The Quayside construction site, Land Department inspection photo 1, 14 May 2024
  • The Quayside construction site, Land Department inspection photo 2, 14 May 2024
  • The Quayside construction site, Land Department inspection photo 3, 14 May 2024

17 October 2023

0%

  • The Quayside construction site, Land Department inspection photo 1, 17 October 2023
  • The Quayside construction site, Land Department inspection photo 2, 17 October 2023

All 33 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Own a unit in The Quayside?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Quayside be completed?
The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Quayside is built?
55%, measured at the Land Department site inspection on 9 June 2026. The Land Department engineers have inspected the site 6 times since October 2023.
Is The Quayside delayed?
Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
Who is building The Quayside?
The registered developer is Quayside Developers.
Which bank holds the escrow account for The Quayside?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.