The Quayside construction progress
The Quayside in Business Bay was registered to complete in March 2026 and is still under construction. At the last site inspection, in October 2026, it was 70% built. The developer is Quayside Developers.
70%
Built, at the site inspection of 27 October 2026
8 months past its registered completion date
- Registered completion date
- March 2026
- Finish at recent pace
- July 2027
- Construction started
- September 2023
- First registered
- November 2023
- Developer
- Quayside Developers
- Community
- Business Bay
- Units
- 119
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ذا كيسايد
- Project number
- 2815
- Site inspections
- 7
Schedule
The Quayside was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.5 points a month. Kept at that rate, the site would reach 100% around July 2027.
Site inspections
27 October 2026
70%+15 pts
9 June 2026
55%+18 pts
17 February 2026
36%+8.5 pts
30 October 2025
28%+11 pts
3 June 2025
17%+15 pts
14 May 2024
1.5%+1.5 pts
17 October 2023
0%
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in The Quayside?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Quayside handover date?
- The registered completion date was March 2026, and the register still lists The Quayside as under construction. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Quayside?
- The Quayside was 70% built at the site inspection on 27 October 2026. The site has been inspected 7 times since October 2023. The Land Department took 45 site photos at its inspections.
- Is The Quayside delayed?
- Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
- Who is building The Quayside?
- The registered developer is Quayside Developers.
- Which bank holds the escrow account for The Quayside?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.