The Quayside construction progress
The Quayside in Business Bay is 55% built at the Land Department inspection of June 2026. Developer Quayside Developers. Completion registered for March 2026.
55%
Built, at the Land Department site inspection of 9 June 2026
6 months past its registered completion date
- Completion date (Land Department)
- March 2026
- Finish at recent pace
- June 2027
- Construction started
- September 2023
- Registered with the Land Department
- November 2023
- Developer
- Quayside Developers
- Community
- Business Bay
- Units
- 119
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ذا كيسايد
- Land Department project number
- 2815
- Land Department site inspections
- 6
Schedule
The Quayside was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around June 2027.
Site inspections
9 June 2026
55%+18 pts
17 February 2026
36%+8.5 pts
30 October 2025
28%+11 pts
3 June 2025
17%+15 pts
14 May 2024
1.5%+1.5 pts
17 October 2023
0%
Context
Business Bay has 43 projects under construction, 35% built on average.
Own a unit in The Quayside?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Quayside be completed?
- The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Quayside is built?
- 55%, measured at the Land Department site inspection on 9 June 2026. The Land Department engineers have inspected the site 6 times since October 2023.
- Is The Quayside delayed?
- Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
- Who is building The Quayside?
- The registered developer is Quayside Developers.
- Which bank holds the escrow account for The Quayside?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








-Elevation%2520%26%2520Fencing%2520(1).jpg&w=3840&q=75)
-Elevation%2520(2).jpg&w=3840&q=75)
%2520-Level-P-1%2520(3).jpg&w=3840&q=75)
%2520-Level-P-1%2520(13).jpg&w=3840&q=75)