Al Habtoor Tower construction progress

Al Habtoor Tower in Business Bay is 90% built at the Land Department inspection of August 2026. Developer Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co. Completion registered for December 2026.

90%

Built, at the Land Department site inspection of 31 August 2026

On pace for its date

Completion date (Land Department)
December 2026
Finish at recent pace
December 2026
Construction started
October 2022
Registered with the Land Department
June 2023
Developer
Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co
Community
Business Bay
Units
1,739
Escrow bank
Dubai Islamic Bank
Name in Arabic
برج الحبتور
Land Department project number
2656
Land Department site inspections
11

Schedule

Since October 2025 Al Habtoor Tower has added about 2.8 points a month. That puts 100% around December 2026, within three months of its registered completion date of December 2026.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 August 2026

90%+10.0 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 31 August 2026
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 31 August 2026
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 31 August 2026
  • Al Habtoor Tower construction site, Land Department inspection photo 4, 31 August 2026

5 May 2026

80%+8.7 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 5 May 2026
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 5 May 2026
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 5 May 2026
  • Al Habtoor Tower construction site, Land Department inspection photo 4, 5 May 2026

30 January 2026

71%+11 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 30 January 2026
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 30 January 2026
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 30 January 2026
  • Al Habtoor Tower construction site, Land Department inspection photo 4, 30 January 2026

14 October 2025

60%+7.7 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 14 October 2025
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 14 October 2025
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 14 October 2025
  • Al Habtoor Tower construction site, Land Department inspection photo 4, 14 October 2025

22 August 2025

53%+8.4 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 22 August 2025
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 22 August 2025
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 22 August 2025
  • Al Habtoor Tower construction site, Land Department inspection photo 4, 22 August 2025

24 April 2025

44%+15 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 24 April 2025
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 24 April 2025
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 24 April 2025
  • Al Habtoor Tower construction site, Land Department inspection photo 4, 24 April 2025

27 September 2024

29%+2.9 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 27 September 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 27 September 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 27 September 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 4, 27 September 2024

18 July 2024

26%+3.0 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 18 July 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 18 July 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 18 July 2024

18 April 2024

23%+6.4 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 18 April 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 18 April 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 18 April 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 4, 18 April 2024

15 February 2024

17%+6.5 pts

  • Al Habtoor Tower construction site, Land Department inspection photo 1, 15 February 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 2, 15 February 2024
  • Al Habtoor Tower construction site, Land Department inspection photo 3, 15 February 2024

All 78 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average. Al Habtoor Tower is ahead of that average.

Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Al Habtoor Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Al Habtoor Tower be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Al Habtoor Tower is built?
90%, measured at the Land Department site inspection on 31 August 2026. The Land Department engineers have inspected the site 11 times since June 2023.
Is Al Habtoor Tower delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building Al Habtoor Tower?
The registered developer is Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Al Habtoor Tower?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.