Elire construction progress

The registered completion date for Elire in Business Bay is December 2028. At the last site inspection, in November 2026, it was 12% built. The developer is Qube Development.

12%

Built, at the site inspection of 16 November 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
March 2037
Construction started
April 2025
First registered
April 2025
Community
Business Bay
Units
101
Escrow bank
First Abu Dhabi Bank
Name in Arabic
إلير
Project number
3467
Site inspections
6

Schedule

Between February 2026 and November 2026 the site added about 0.7 points a month. At that rate it would finish around March 2037, more than three months after its registered date of December 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 November 2026

12%+3.9 pts

  • Elire construction site, inspection photo 1, 16 November 2026
  • Elire construction site, inspection photo 2, 16 November 2026
  • Elire construction site, inspection photo 3, 16 November 2026
  • Elire construction site, inspection photo 4, 16 November 2026

11 August 2026

8.2%+1.2 pts

  • Elire construction site, inspection photo 1, 11 August 2026
  • Elire construction site, inspection photo 2, 11 August 2026
  • Elire construction site, inspection photo 3, 11 August 2026
  • Elire construction site, inspection photo 4, 11 August 2026

7 May 2026

6.9%+1.6 pts

  • Elire construction site, inspection photo 1, 7 May 2026
  • Elire construction site, inspection photo 2, 7 May 2026
  • Elire construction site, inspection photo 3, 7 May 2026
  • Elire construction site, inspection photo 4, 7 May 2026

3 February 2026

5.4%+5.3 pts

  • Elire construction site, inspection photo 1, 3 February 2026
  • Elire construction site, inspection photo 2, 3 February 2026
  • Elire construction site, inspection photo 3, 3 February 2026
  • Elire construction site, inspection photo 4, 3 February 2026

1 October 2025

0.1%+0.1 pts

  • Elire construction site, inspection photo 1, 1 October 2025
  • Elire construction site, inspection photo 2, 1 October 2025
  • Elire construction site, inspection photo 3, 1 October 2025

23 December 2024

0%

  • Elire construction site, inspection photo 1, 23 December 2024
  • Elire construction site, inspection photo 2, 23 December 2024

All 27 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Qube Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Elire?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elire handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elire?
Elire was 12% built at the site inspection on 16 November 2026. The site has been inspected 6 times since December 2024. The Land Department took 27 site photos at its inspections.
Is Elire delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Elire?
The registered developer is Qube Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Elire?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.